IR 05000388/2013009: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 3: Line 3:
| issue date = 04/01/2013
| issue date = 04/01/2013
| title = Susquehanna - Assessment Follow-up Letter (05000388/2013009)
| title = Susquehanna - Assessment Follow-up Letter (05000388/2013009)
| author name = Roberts D J
| author name = Roberts D
| author affiliation = NRC/RGN-I/DRP
| author affiliation = NRC/RGN-I/DRP
| addressee name = Rausch T S
| addressee name = Rausch T
| addressee affiliation = PPL Susquehanna, LLC
| addressee affiliation = PPL Susquehanna, LLC
| docket = 05000388
| docket = 05000388
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES  NUCLEAR REGULATORY COMMISSION    REGION I  2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 April 1, 2013 Mr. Timothy Senior Vice President and Chief Nuclear Officer
{{#Wiki_filter:April 1, 2013


PPL Susquehanna, LLC
==SUBJECT:==
 
ASSESSMENT FOLLOW-UP LETTER SUSQUEHANNA STEAM ELECTRIC STATION, UNlT 2 (05000388/2013009)
769 Salem Boulevard Berwick, PA 18603-0467
 
SUBJECT: ASSESSMENT FOLLOW-UP LETTER SUSQUEHANNA STEAM ELECTRIC STATION, UNlT 2 (05000388/2013009)


==Dear Mr. Rausch:==
==Dear Mr. Rausch:==

Revision as of 05:35, 22 June 2019

Susquehanna - Assessment Follow-up Letter (05000388/2013009)
ML13092A011
Person / Time
Site: Susquehanna Talen Energy icon.png
Issue date: 04/01/2013
From: Darrell Roberts
Division Reactor Projects I
To: Rausch T
Susquehanna
gray, mel
References
IR-13-009
Download: ML13092A011 (3)


Text

April 1, 2013

SUBJECT:

ASSESSMENT FOLLOW-UP LETTER SUSQUEHANNA STEAM ELECTRIC STATION, UNlT 2 (05000388/2013009)

Dear Mr. Rausch:

As a result of its continuous review of plant performance, the U. S. Nuclear Regulatory Commission (NRC) updated its assessment of Susquehanna Steam Electric Station (Susquehanna) Unit 2. The NRC's evaluation consisted of a review of performance indicators and inspection results. This letter informs you of the NRC's assessment of and its plans for a future inspection at your facility. This letter supplements, but does not supersede, the annual assessment letter issued on March 4, 2013.

As discussed in the annual assessment letter, the NRC determined the performance of Susquehanna Unit 2 during 2012 was within the Licensee Response column of the NRC's Reactor Oversight Process (ROP) Action Matrix. Subsequently on March 20, 2013, PPL staff submitted a revision for the "Unplanned Scrams with Complications" Performance Indicator (PI). The revision reported the December 16, 2012 automatic plant shutdown (scram) as complicated because operators re-entered emergency operating procedures after the scram had occurred.

The NRC's review of Susquehanna Unit 2 identified the revised Unplanned Scrams with Complications PI crossed the green-to-white threshold (i.e., greater than one complicated scram). Specifically, Unit 2 had complicated scrams on November 9, 2012 and December 16, 2012. As a result, the NRC revised its assessment of Susquehanna Unit 2 to conclude that during the fourth quarter 2012, performance of Susquehanna Unit 2 is in the Regulatory Response column of the NRC's ROP Action Matrix because the "Unplanned Scrams with Complications" PI is in the white band. Therefore, the NRC plans to schedule and perform a supplemental inspection using Inspection Procedure (IP) 95001, "Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area." The NRC requests that your staff provide notification of your readiness for the NRC to conduct this supplemental inspection.

In accordance with 10 CFR 2.390 of the NRC

=s A Rules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Mr. Mel Gray at 610-337-5209 with any questions you have regarding this letter.

Sincerely,

/RA/

Darrell J. Roberts, Director

Division of Reactor Projects Docket Nos. 50-388 License No. NPF-22

cc: Distribution via ListServ

ML13092A011 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME JAyala/JA MGray/MG DRoberts/DJR DATE 03/26/13 03/26/13 04/01/13