Line 3: |
Line 3: |
| | issue date = 04/18/2013 | | | issue date = 04/18/2013 |
| | title = Senior Reactor and Reactor Operator Initial License Examinations - Hope Creek Generating Station | | | title = Senior Reactor and Reactor Operator Initial License Examinations - Hope Creek Generating Station |
| | author name = Jackson D E | | | author name = Jackson D |
| | author affiliation = NRC/RGN-I/DRS/OB | | | author affiliation = NRC/RGN-I/DRS/OB |
| | addressee name = Joyce T P | | | addressee name = Joyce T |
| | addressee affiliation = PSEG Nuclear, LLC | | | addressee affiliation = PSEG Nuclear, LLC |
| | docket = 05000354 | | | docket = 05000354 |
| | license number = NPF-057 | | | license number = NPF-057 |
| | contact person = Jackson D E | | | contact person = Jackson D |
| | package number = ML13077A118 | | | package number = ML13077A118 |
| | document type = Letter, License-Operator, Part 55 Examination Related Material | | | document type = Letter, License-Operator, Part 55 Examination Related Material |
|
---|
Category:Letter
MONTHYEARIR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 ML24030A8752024-02-0101 February 2024 Operator Licensing Examination Approval ML24009A1022024-01-26026 January 2024 Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 ML23341A1372024-01-16016 January 2024 Issuance of Amendment No. 235 Revise Trip and Standby Auto-Start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning ML23335A1122023-12-15015 December 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers ML23307A1532023-12-15015 December 2023 NRC Investigation Report No. 1-2023-001 ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000354/20230032023-11-0707 November 2023 Integrated Inspection Report 05000354/2023003 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0065, Submittal of 2023 Annual 10 CFR 50.46 Report2023-10-0202 October 2023 Submittal of 2023 Annual 10 CFR 50.46 Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20230052023-08-31031 August 2023 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2023005) ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 IR 05000354/20230102023-08-0303 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000354/2023010 LR-N23-0052, Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.12023-07-31031 July 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers Per Technical Specification 4.6.2.1 LR-N23-0042, Spent Fuel Cask Registration2023-07-12012 July 2023 Spent Fuel Cask Registration LR-N23-0046, Emergency Plan Document Revisions Implemented June 28, 20232023-07-10010 July 2023 Emergency Plan Document Revisions Implemented June 28, 2023 IR 05000354/20230112023-05-0101 May 2023 Commercial Grade Dedication Report 05000354/2023011 ML23121A1412023-05-0101 May 2023 Senior Reactor and Reactor Operator Initial License Examinations LR-N23-0034, 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station2023-04-27027 April 2023 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station LR-N23-0035, 2022 Annual Radioactive Effluent Release Report (ARERR)2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report (ARERR) IR 05000354/20230012023-04-26026 April 2023 Integrated Inspection Report 05000354/2023001 LR-N23-0010, License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location2023-04-21021 April 2023 License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location LR-N23-0009, License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains2023-04-18018 April 2023 License Amendment Request (LAR) to Revise the Hope Creek Trip and Standby Auto-start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning (HVAC) Trains ML23087A1492023-04-17017 April 2023 NRC to PSEG Salem, Transmittal of the National Marine Fisheries Service'S March 24, 2023, Biological Opinion GAR-2020-02842 Concerning Salem and Hope Creek ML23089A0942023-04-17017 April 2023 NRC to PSEG Hope Creek, Transmittal of the National Marine Fisheries Service'S March 24, 2023, Biological Opinion GAR-2020-02842 Concerning Salem and Hope Creek ML23103A3232023-04-13013 April 2023 Submittal of Updated Final Safety Analysis Report, Rev. 26, Summary of Revised Regulatory Commitments for Hope Creek, Summary of Changes to PSEG Nuclear LLC, Quality Assurance Topical Report, NO-AA-10, Rev. 89 ML23095A3682023-04-12012 April 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Threshold Determination for Proposed Transfer of Land Ownership LR-N23-0024, Submittal of Hope Creek Generating Station Technical Specification Bases Changes2023-03-29029 March 2023 Submittal of Hope Creek Generating Station Technical Specification Bases Changes LR-N23-0006, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-24024 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23086A0912023-03-24024 March 2023 NMFS to NRC, Transmittal of Biological Opinion for Continued Operations of Salem and Hope Creek Nuclear Generating Stations LR-N23-0019, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2023-03-21021 March 2023 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums ML23037A9712023-03-0909 March 2023 and Salem Nuclear, Unit Nos. 1 and 2 Issuance of Amendment Nos. 233, 344, and 325 Relocate Technical Specification Staff Qualification Requirements to the PSEG Quality Assurance Topical Report IR 05000354/20220062023-03-0101 March 2023 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2022006) LR-N23-0016, and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments2023-02-28028 February 2023 and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments LR-N23-0018, Technical Specification 6.9.1.5.b - 2022 Annual Report of SRV Challenges2023-02-27027 February 2023 Technical Specification 6.9.1.5.b - 2022 Annual Report of SRV Challenges LR-N23-0012, Annual Property Insurance Status Report2023-02-24024 February 2023 Annual Property Insurance Status Report LR-N23-0014, Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.7172023-02-23023 February 2023 Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.717 IR 05000354/20220042023-01-24024 January 2023 Integrated Inspection Report 05000354/2022004 LR-N23-0011, In-Service Inspection Activities - 90 Day Report: Twenty-Fourth Refueling Outage2023-01-19019 January 2023 In-Service Inspection Activities - 90 Day Report: Twenty-Fourth Refueling Outage LR-N22-0096, and Salem Generating Station, Units 1 and 2 - Request for Threshold Determination2023-01-0505 January 2023 and Salem Generating Station, Units 1 and 2 - Request for Threshold Determination LR-N22-0094, Emergency Plan Document Revisions Implemented November 21, 20222022-12-14014 December 2022 Emergency Plan Document Revisions Implemented November 21, 2022 LR-N22-0091, Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments2022-12-0202 December 2022 Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments ML22335A0412022-12-0101 December 2022 Notification of Commercial Grade Dedication Inspection (05000354/2023011) and Request for Information IR 05000354/20220032022-11-0303 November 2022 Integrated Inspection Report 05000354/2022003 2024-02-01
[Table view] Category:License-Operator
MONTHYEARNTD-23-038, Response to RIS 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-05-11011 May 2023 Response to RIS 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23121A1412023-05-0101 May 2023 Senior Reactor and Reactor Operator Initial License Examinations ML22312A4352022-10-0303 October 2022 Exam Form 1.3-1 ML23055A3812022-07-31031 July 2022 Exam Forms 2.3-1, 2.3-2, 3.4-1 ML22003A0042022-01-0303 January 2022 Senior Reactor and Reactor Operator Initial License Examinations ML21117A0842021-04-0909 April 2021 Final Q/A Related - Forms (Folder 1) ML21076A0632021-03-0909 March 2021 Final Written Examination and Operating Test Outlines (Folder 3) ML21076A0642021-03-0909 March 2021 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML21075A1042021-03-0909 March 2021 Draft Written Examination and Operating Test Outlines (Folder 2) ML21075A1022021-03-0909 March 2021 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML21075A1032021-03-0909 March 2021 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML21075A1052021-03-0909 March 2021 Draft Written Examination (Folder 2) ML21076A0622021-03-0909 March 2021 Draft Operating Test (Section a, Section B, Section C)(Folder 2) ML21076A0662021-03-0909 March 2021 Final Operating Test (Section a, B, and C) (Folder 3) ML21032A1022021-02-0101 February 2021 Operator Licensing Examination Approval ML21117A0832021-01-28028 January 2021 Final Q/A Related Form ES-401-6 (Folder 1) ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 NTD-20-014, Response to RIS 2020-01, Preparation and Scheduling of Operator Licensing Examinations2020-03-18018 March 2020 Response to RIS 2020-01, Preparation and Scheduling of Operator Licensing Examinations ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML21041A1732019-10-0101 October 2019 Original Question for Modified Question 80 ML19219A1022019-08-0606 August 2019 Operator Licensing Examination Approval ML19302F9902019-01-0808 January 2019 NRC Corporate Notification Letter (Folder 1) ML18311A1572018-07-24024 July 2018 Operating Test Retake - Examination Approval Letter (Folder 1) ML18311A1562018-07-14014 July 2018 NRC Corporate Notification Letter (Folder 1) NTD-18-044, Response to RIS 2018-02, Preparation and Scheduling of Operator Licensing Examinations2018-04-26026 April 2018 Response to RIS 2018-02, Preparation and Scheduling of Operator Licensing Examinations IR 05000354/20183012018-04-0303 April 2018 Initial Operator Licensing Examination Report 05000354/2018301 ML18086B0252018-02-16016 February 2018 Facility Cover Letter - Ri - March 2018 - GFE ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17178A3092017-06-22022 June 2017 Senior Reactor and Reactor Operator Initial License Examinations LR-N17-0098, Response to RIS-2017-03, Preparation and Scheduling of Operator Licensing Examinations2017-05-0505 May 2017 Response to RIS-2017-03, Preparation and Scheduling of Operator Licensing Examinations ML17034A1062017-02-0202 February 2017 December 7, 2016, NRC Generic Fundamentals Examination Results for Hope Creek Generating Station (Cover Letter Publicly Available, Enclosures Withheld from Public) ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 ML16293A1232016-10-18018 October 2016 September 7, 2016, NRC Generic Fundamentals Examination Results for Hope Creek Generating Station (Cover Letter Publicly Available, Enclosures Withheld from Public) ML16295A0562016-10-11011 October 2016 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML16295A0552016-10-10010 October 2016 Post Exam Comments and Resolution (Folder 1) ML16295A0572016-10-0101 October 2016 Final Operating Exam (Sections a, B, and C) (Folder 3) ML17186A1212016-08-16016 August 2016 Final Qa/Related Forms (Folder 1) ML17186A1452016-08-14014 August 2016 Final Outlines (Folder 3) ML17186A2442016-07-28028 July 2016 Draft - Outlines (Folder 2) ML17186A2372016-07-28028 July 2016 Facility Comments on Draft Facility-Developed Exam (Written) (Folder 2) LR-N16-0125, Response to RIS 2016-09, Preparation of Scheduling of Operator Licensing Examination2016-07-0808 July 2016 Response to RIS 2016-09, Preparation of Scheduling of Operator Licensing Examination ML16053A1032016-02-22022 February 2016 Senior Reactor and Reactor Operator Initial License Examinations - Hope Creek Generating Station ML15163A2462015-12-17017 December 2015 Draft Operating Exam (Sections a, B, and C) (Folder 2) ML15163A2452015-12-17017 December 2015 Draft Written Exam (Folder 2) ML15198A2332015-07-14014 July 2015 June 10, 2015, NRC Generic Fundamentals Examination Results for Hope Creek Generating Station (Cover Letter Publicly Available, Enclosures Withheld from Public) ML15163A2412015-06-10010 June 2015 Final Outlines (Folder 3) ML16145A2442015-03-31031 March 2015 Final Qa/Related Forms (Folder 1) ML15091A2402015-03-30030 March 2015 March 4, 2015, NRC Generic Fundamentals Examination Results for Hope Creek, (Cover Letter Publicly Available, Enclosures Withheld from Public) ML15100A0422015-03-0606 March 2015 Final Operating Exam (Sections a, B, and C) (Folder 3) ML15100A0412015-03-0606 March 2015 Handouts to Applicants (Folder 3) 2023-05-11
[Table view] Category:Part 55 Examination Related Material
MONTHYEARNTD-23-038, Response to RIS 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-05-11011 May 2023 Response to RIS 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23121A1412023-05-0101 May 2023 Senior Reactor and Reactor Operator Initial License Examinations ML22312A4352022-10-0303 October 2022 Exam Form 1.3-1 ML23055A3812022-07-31031 July 2022 Exam Forms 2.3-1, 2.3-2, 3.4-1 ML22003A0042022-01-0303 January 2022 Senior Reactor and Reactor Operator Initial License Examinations ML21117A0842021-04-0909 April 2021 Final Q/A Related - Forms (Folder 1) ML21075A1022021-03-0909 March 2021 NRC Comments on Draft Licensee-Developed Written Exam (Folder 2) ML21076A0632021-03-0909 March 2021 Final Written Examination and Operating Test Outlines (Folder 3) ML21076A0642021-03-0909 March 2021 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML21076A0622021-03-0909 March 2021 Draft Operating Test (Section a, Section B, Section C)(Folder 2) ML21075A1052021-03-0909 March 2021 Draft Written Examination (Folder 2) ML21076A0662021-03-0909 March 2021 Final Operating Test (Section a, B, and C) (Folder 3) ML21075A1042021-03-0909 March 2021 Draft Written Examination and Operating Test Outlines (Folder 2) ML21075A1032021-03-0909 March 2021 NRC Comments on Draft Licensee-Developed Operating Test (Folder 2) ML21032A1022021-02-0101 February 2021 Operator Licensing Examination Approval ML21117A0832021-01-28028 January 2021 Final Q/A Related Form ES-401-6 (Folder 1) ML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 NTD-20-014, Response to RIS 2020-01, Preparation and Scheduling of Operator Licensing Examinations2020-03-18018 March 2020 Response to RIS 2020-01, Preparation and Scheduling of Operator Licensing Examinations ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML21041A1732019-10-0101 October 2019 Original Question for Modified Question 80 ML19219A1022019-08-0606 August 2019 Operator Licensing Examination Approval ML19302F9902019-01-0808 January 2019 NRC Corporate Notification Letter (Folder 1) ML18311A1572018-07-24024 July 2018 Operating Test Retake - Examination Approval Letter (Folder 1) ML18311A1562018-07-14014 July 2018 NRC Corporate Notification Letter (Folder 1) NTD-18-044, Response to RIS 2018-02, Preparation and Scheduling of Operator Licensing Examinations2018-04-26026 April 2018 Response to RIS 2018-02, Preparation and Scheduling of Operator Licensing Examinations IR 05000354/20183012018-04-0303 April 2018 Initial Operator Licensing Examination Report 05000354/2018301 ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17178A3092017-06-22022 June 2017 Senior Reactor and Reactor Operator Initial License Examinations LR-N17-0098, Response to RIS-2017-03, Preparation and Scheduling of Operator Licensing Examinations2017-05-0505 May 2017 Response to RIS-2017-03, Preparation and Scheduling of Operator Licensing Examinations ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 ML16293A1232016-10-18018 October 2016 September 7, 2016, NRC Generic Fundamentals Examination Results for Hope Creek Generating Station (Cover Letter Publicly Available, Enclosures Withheld from Public) ML16295A0562016-10-11011 October 2016 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML16295A0552016-10-10010 October 2016 Post Exam Comments and Resolution (Folder 1) ML16295A0572016-10-0101 October 2016 Final Operating Exam (Sections a, B, and C) (Folder 3) ML17186A1212016-08-16016 August 2016 Final Qa/Related Forms (Folder 1) ML17186A1452016-08-14014 August 2016 Final Outlines (Folder 3) ML17186A2442016-07-28028 July 2016 Draft - Outlines (Folder 2) ML17186A2372016-07-28028 July 2016 Facility Comments on Draft Facility-Developed Exam (Written) (Folder 2) ML16053A1032016-02-22022 February 2016 Senior Reactor and Reactor Operator Initial License Examinations - Hope Creek Generating Station ML15163A2462015-12-17017 December 2015 Draft Operating Exam (Sections a, B, and C) (Folder 2) ML15163A2452015-12-17017 December 2015 Draft Written Exam (Folder 2) ML15198A2332015-07-14014 July 2015 June 10, 2015, NRC Generic Fundamentals Examination Results for Hope Creek Generating Station (Cover Letter Publicly Available, Enclosures Withheld from Public) ML15163A2412015-06-10010 June 2015 Final Outlines (Folder 3) ML16145A2442015-03-31031 March 2015 Final Qa/Related Forms (Folder 1) ML15100A0422015-03-0606 March 2015 Final Operating Exam (Sections a, B, and C) (Folder 3) ML15100A0412015-03-0606 March 2015 Handouts to Applicants (Folder 3) ML15100A0402015-03-0303 March 2015 Final Written Examination with Answer Key (401-5 Format) (Folder 2) ML15163A2442015-02-17017 February 2015 Draft - Outlines (Folder 2) ML15163A2432015-02-17017 February 2015 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML15163A2422015-02-17017 February 2015 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) 2023-05-11
[Table view] |
Text
r;--w UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA. PENNSYLVANIA 19406-1415 April 18,2013 Mr. Thomas P. Joyce President and Chief Nuclear Officer PSEG Nuclear LLC P. O. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
SENIOR REACTOR AND REACTOR OPERATOR lNlTlAL LICENSE EXAMINATIONS - HOPE CREEK GENERATING STATION
Dear Mr. Joyce:
ln a telephone conversation on April 18,2013, between Mr. T. Fish, Chief Examiner, and Mr. T. Fowler, Operations Training Manager, arrangements were made for the administration of licensing examinations at Hope Creek during the week of August 19, 2013.As agreed during the telephone conversation, the staff of the U.S. Nuclear Regulatory Commission (NRC) will prepare the examinations based on the guidelines in NUREG-1021,"Operator Licensing Examination Standards for Power Reactors," Revision 9, Supplement 1.Your staff will be given the opportunity to review the examinations during the week of July 22,2013.Your staff previously provided us the supporting reference materials identified in Attachment 3 of ES-201.In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.9., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final. Appendix E of NUREG-1021contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications (Office of Management and Budget (OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024), and waiver requests (if any) (OMB approval number 3150-0090) at least 30 days before the first examination date. lf the applications are not received at least 30 days before the examination date, a postponement may be necessary.
Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.
T. Joyce After you have been notified by the NRC Chief Examiner or Branch Chief that operator licenses have been issued, please direct any inquiries concerning a formal presentation of certificates to this office. Our goal is to have the operator certificates available for your celebration.
At least one month advance notice of your celebration arrangements would be appreciated to plan our senior manager attendance and process the certificates.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The OMB, under approval number 3150-0018, approved these information collections.
The public reporting burden for this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information.
Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by electronic mail to infocollects@nrc.qov; and to the Desk Officer, Office of lnformation and Regulatory Affairs, NEOB-1 0202, (3150-0018), Office of Management and Budget, Washington, DC 20503. The NRC may not conduct or sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number.ln accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRC's public Web site at http://www.nrc.qov/readinq-rm/adams/web-based.html.
Thank you for your cooperation in this matter. Mr. Fowler has been advised of the policies and guidelines referenced in this letter. lf you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. T. Fish at (610) 337-5369, or me at (610) 337-5306.Operations Branch Division of Reactor Safety Docket No. 50-354 License No. NPF-57 cc: Distribution via ListServ T. Joyce After you have been notified by the NRC Chief Examiner or Branch Chief that operator licenses have been issued, please direct any inquiries concerning a formal presentation of certificates to this office. Our goal is to have the operator certificates available for your celebration.
At least one month advance notice of your celebration arrangements would be appreciated to plan our senior manager attendance and process the certificates.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The OMB, under approval number 3150-0018, approved these information collections.
The public reporting burden for this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information.
Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by electronic mail to infocollects@nrc.qov; and to the Desk Officer, Office of lnformation and Regulatory Affairs, NEOB-1 0202, (3150-0018), Office of Management and Budget, Washington, DC 20503. The NRC may not conduct or sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number.In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS), ADAMS is accessible from the Electronic Reading Room page of the NRC's public Web site at http://www.nrc.sov/reading-rm/adams/web-based.html.
Thank you for your cooperation in this matter. Mr. Fowler has been advised of the policies and guidelines referenced in this letter. lf you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. T. Fish at (610) 337-5369, or me at (610) 337-5306.Sincerely,/RA/Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket No. 50-354 License No. NPF-57 cc: Distribution via ListServ Distribution w/encl: (via E-mail) see next page.DOCUMENT NAME: G:\DRS\Operations Branch\FISH\Exam 13-HC Aug 19 (U01872XNRC Dev)\l20dayexamltr.docx AIJAMS PKG: ML13O77A11E ADAMS ACGESSION NUMtsER: ML131064195 V suNslReview V Non-Sensitive n Sensitive V Publicly Available n Non-PubliclyAvailable OFFICE RI/DRS/OB RI/DRS/OB NAME TFishiTF DJackson/TEJ DATE o4t18t2013 o4t18t2013 OFFICIAL 3 Distribution Mencl: (via E-mail)W. Dean, RA (RIORAMAIL Resource)D. Lew, DRA (RIORAMAIL Resource)D. Roberts, DRP (RIDRPMAIL Resource)M. Layton, DRP (RlDRPMail Resource)C. Miller, DRS (RiDRSMail Resource)J. Clifford, DRS (RlDRSMail Resource)G. Dentel, DRP R. Barkley, DRP M. Draxton,DRP R. Montgomery, DRP F. Bower, DRP, SRI S. lbarrola, DRP K. McKenzie, DRP, AA D. Huyck, Rl OEDO RidsN rrPM HopeCreek Resource Rids N rrDorlLpll
-2 Resou rce D. Jackson, DRS T. Fish, DRS DRS Master Exam File (C. Bixler) (w/concurrences)