==Dear Mr. Ford:==
==Dear Mr. Ford:==
By letter dated December 17, 2015, Entergy Nuclear Operations, Inc. (Entergy) submitted, for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, decommissioning funding plan updates (DFP Updates) for the independent spent fuel storage installations (ISFSIs) at Big Rock Point, Indian Point Nuclear Generating Stations Units 1, 2, and 3 (Indian Point 1, 2, and 3), Pilgrim Nuclear Power Station (Pilgrim), Palisades Nuclear Plant (Palisades),  James A. FitzPatrick Nuclear Power Plant (FitzPatrick), and Vermont Yankee Nuclear Power Station (Vermont Yankee)
By letter dated December 17, 2015, Entergy Nuclear Operations, Inc. (Entergy) submitted, for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, decommissioning funding plan updates (DFP Updates) for the independent spent fuel storage installations (ISFSIs) at Big Rock Point, Indian Point Nuclear Generating Stations Units 1, 2, and 3 (Indian Point 1, 2, and 3), Pilgrim Nuclear Power Station (Pilgrim), Palisades Nuclear Plant (Palisades),  James A. FitzPatrick Nuclear Power Plant (FitzPatrick), and Vermont Yankee Nuclear Power Station (Vermont Yankee)
(Agencywide Documents Access and Management System Accession No. ML15351A524). The NRC staff reviewed Entergy's DFP updates for each ISFSI and believes Entergy's submittal was not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). Specifically, the DFP updates do not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)
(Agencywide Documents Access and Management System Accession No. ML15351A524). The NRC staff reviewed Entergy's DFP updates for each ISFSI and believes Entergy's submittal was not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). Specifically, the DFP updates do not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)
-(4) ha ve been considered.
-(4) ha ve been considered.
The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty
The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty

Revision as of 15:40, 25 April 2019

Letter to B. S. Ford RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for ISFSI Docket Nos.: 72-43, 72-51, 72-1044, 72-07, 72-12, and 72-59
ML18094B093
Person / Time
Site: Palisades, Indian Point, Pilgrim, Vermont Yankee, Big Rock Point, FitzPatrick  Entergy icon.png
Issue date: 04/05/2018
From: Pamela Longmire
Spent Fuel Licensing Branch
To: Bryan Ford
Entergy Operations
Longmire P
Shared Package
ML18094B091 List:
References
CAC 001028, EPID No.: L-2017-FPR-0007, EPID No.: L-2017-FPR-0026, EPID No.: L-2017-FPR-0035, EPID No.: L-2017-FPR-0050, EPID No.: L-2017-FPR-0054, EPID No.: L-2017-FPR-0071
Download: ML18094B093 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555

-0001 April 5, 2018 Mr. Bryan S. Ford Senior Manager Fleet Regulator Assurance Entergy Operations, Inc.

1340 Echelon Parkway Jackson, MS 39213

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION REGARDING ENTERGY OPERATIONS, INC.'S DECOMMISSIONING FUNDING PLAN UPDATE FOR BIG ROCK POINT, INDIAN POINT NUCLEAR GENERATING STATIONS UNITS 1, 2, AND 3, PILGRIM NUCLEAR POWER STATION, PALISADES NUCLEAR PLANT, JAMES A. FITZPATRICK NUCLEAR POWER PLANT, AND VERMONT YANKEE NUCLEAR POWER STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS DOCKET NOS. 72

-43, 72-51, 72-1 0 44, 72-0 7, 72-12, AND 72

-59

Dear Mr. Ford:

By letter dated December 17, 2015, Entergy Nuclear Operations, Inc. (Entergy) submitted, for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, decommissioning funding plan updates (DFP Updates) for the independent spent fuel storage installations (ISFSIs) at Big Rock Point, Indian Point Nuclear Generating Stations Units 1, 2, and 3 (Indian Point 1, 2, and 3), Pilgrim Nuclear Power Station (Pilgrim), Palisades Nuclear Plant (Palisades), James A. FitzPatrick Nuclear Power Plant (FitzPatrick), and Vermont Yankee Nuclear Power Station (Vermont Yankee)

(Agencywide Documents Access and Management System Accession No. ML15351A524). The NRC staff reviewed Entergy's DFP updates for each ISFSI and believes Entergy's submittal was not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). Specifically, the DFP updates do not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)

-(4) ha ve been considered.

The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty

-five (45) working day of the date of this letter

. Inform us at your earliest convenience, but no later than 2 weeks prior to the due date, if you are not able to provide the information by that date.

To assist us in re

-scheduling your review, you should include a new proposed submittal date and the reasons for the delay.

Discussion of the request for additional information (RAI) and RAI response date occurred March 28, 2018. In future correspondence related to this request, please reference CAC No. 001028, the Docket Numbers, and EPID Number s listed in the table.

ISFSI Docket Numb er EPID Numbers Big Rock Point 72-43 L-2017- FPR-0007 Indian Point 72-51 L-2017-FPR-0035 Pilgrim 72-1044 L-2017-FPR-0054 Palisades 72-07 L-2017-FPR-0050 Fitzpatrick 72-12 L-2017-FPR-0026 Vermont Yankee 72-59 L-2017-FPR-0071 The staff is available to clarify these questions, and if necessary to meet and discuss your proposed responses.

If you have any questions regarding this matter, please contact me by e-mail at pamela.longmire@nrc.gov

. Sincerely, /RA John McKirgan Acting for

/ Pamela Longmire, Ph.D.

Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No s.: 72-43, 72-51, 72-1044, 72-07, 72-12, and 72

-59 CAC No.:

001028 EPID s: L-2017- FPR-000 7 , L-2017-FPR-00 35 , L-2017-FPR-00 54 , L-2017-FPR-0050, L-2017-FPR-0026, and L-2017-FPR-00 71

Enclosure:

Request for Additional Information

REQUEST FOR ADDITIONAL INFORMATION REGARDING ENTERGY OPERATIONS, INC.'S DECOMMISSIONING FUNDING PLAN UPDATE FOR BIG ROCK POINT, INDIAN POINT NUCLEAR GENERATING STATIONS UNITS 1, 2, AND 3, PILGRIM NUCLEAR POWER STATION, PALISADES NUCLEAR PLANT, JAMES A. FITZPATRICK NUCLEAR POWER PLANT, AND VERMONT YANKEE NUCLEAR POWER STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS DOCKET NOS. 72

-43, 72-51, 72-1044, 72-07, 72-12, AND 72-59, DOCUMENT DATE: April 5, 2018 DISTRIBUTION:

SFM R/F JMcKirgan ABowers SHarwell KLois MHenderson BWatson KConway JParrott G:/SFST/72.30 Decommissioning Funding Plans/RAIs/Entergy(2)/Entergy(2)-RAI.docx G:/SFST/72.30 Decommissioning Funding Plans/RAIs/Entergy(2)/Entergy(2)-Enclosure.docx ADAMS Package No.: ML18094B091 LTR: ML18094B093 Enc.: ML18094B092 C = COVER E = COVER & ENCLOSURE N = NO COPY OFC NMSS/DSFM NMSS/DSFM NMSS/DSFM NAME PLongmire WWheatley JMcKirgan DATE 3/28/18 03/29/18 04/05/18 OFFICIAL RECORD COPY