MONTHYEARJAFP-09-0025, James A. Fitzpatrick - Request for Exemption from 10 CFR 50 Appendix R Section III.G.2 Requirements Based on Manual Actions2009-02-18018 February 2009 James A. Fitzpatrick - Request for Exemption from 10 CFR 50 Appendix R Section III.G.2 Requirements Based on Manual Actions Project stage: Request ML0907700582009-03-20020 March 2009 ME0727 - Request for Supplemental Information Required for Completion of Acceptance Review Project stage: Acceptance Review JAFP-09-0038, Response to the Request for Supplemental Information to Complete Acceptance Review - Request for Exemption from 10 CFR, Appendix R, Section III.G.2 Requirements Based on Manual Actions (Redacted Version)2009-03-30030 March 2009 Response to the Request for Supplemental Information to Complete Acceptance Review - Request for Exemption from 10 CFR, Appendix R, Section III.G.2 Requirements Based on Manual Actions (Redacted Version) Project stage: Supplement ML0909602142009-03-30030 March 2009 James A. FitzPatrick, Response to Request for Information Required for Acceptance Review Regarding: Request for Exemption Project stage: Response to RAI ML0909701102009-04-0707 April 2009 ME0727, Acceptance Review - Request for Exemption from 10 CFR 50 Appendix R Requirements Based on Manual Actions Project stage: Acceptance Review ML0916903972009-06-12012 June 2009 ME0727, Comments from Ny State on Application for Exemption from 10 CFR 50, Appendix R Section III.G.2 Requirements Based on Manual Actions Project stage: Other ML0925906182009-08-16016 August 2009 ME0727, RAIs from Afpb on Request for Exemption from 10 CFR 50, Appendix R, Section III.G.2 Based on Manual Actions Project stage: RAI ML0932700752009-11-17017 November 2009 James A. FitzPatrick Nuclear Power Plant - Response to Request for Additional Information Re Request for Exemption from 10 CFR 50, App R, Section III.G.2 Project stage: Response to RAI JAFP-09-0130, Response to Request for Additional Information on Exemption2009-11-17017 November 2009 Response to Request for Additional Information on Exemption Project stage: Response to RAI JAFP-09-0144, Response to Request for Additional Information Regarding: Request for Exemption2009-12-11011 December 2009 Response to Request for Additional Information Regarding: Request for Exemption Project stage: Response to RAI ML1001312422010-01-13013 January 2010 ME0727, Follow-up RAI Request for Exemption from Requirements of 10 CFR 50, Appendix R, Section III.G.2 for Manual Action Project stage: RAI JAFP-10-0011, Response to Request for Additional Information Regarding: Request for Exemption2010-01-19019 January 2010 Response to Request for Additional Information Regarding: Request for Exemption Project stage: Response to RAI ML0912401422010-03-0404 March 2010 Environmental Assessment and Finding of No Significant Impact Project stage: Other ML1003406702010-03-11011 March 2010 Exemption from Requirements of 10 CFR Part 50, Appendix R, Section III.G.2 Project stage: Approval ML1003406612010-03-11011 March 2010 FRN: General Notice. James A. FitzPatrick Nuclear Power Plant, ME0727, Exemption from Appendix R Section G.III.2 Requirements for a Manual Action Project stage: Approval NRC-2010-0095, FRN: General Notice. James A. FitzPatrick Nuclear Power Plant, ME0727, Exemption from Appendix R Section G.III.2 Requirements for a Manual Action2010-03-11011 March 2010 FRN: General Notice. James A. FitzPatrick Nuclear Power Plant, ME0727, Exemption from Appendix R Section G.III.2 Requirements for a Manual Action Project stage: Approval 2009-04-07
[Table View] |
|
---|
Category:Federal Register Notice
MONTHYEARML21294A3762021-11-16016 November 2021 Federal Register Notice for Order Approving Indirect Transfer of Licenses ML21145A0142021-05-26026 May 2021 Fleet and the Associated Independent Spent Fuel Storage Installations - Extension of Comment Period for Notice of Consideration of Approval of Transfer of Licenses and Conforming Amendments and Opportunity to Request a Hearing EPID L-2021-L ML21145A0152021-05-26026 May 2021 FRN Exelon License Transfer - Extend Comment Period ML21102A0752021-04-28028 April 2021 Fleet - Notice of Consideration of Approval of Transfer of Licenses and Conforming Amendments and Opportunity for a Hearing (FRN) ML20269A2002020-09-30030 September 2020 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L2020-LLR-0117 ML20243A0002020-09-23023 September 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for August 2020 ML20216A3742020-08-0505 August 2020 Letter with Withdrawal of an Amendment Request ML20146A0042020-07-21021 July 2020 Federal Register Notice - Exemption from the Requirements of Appendix J to 10 CFR Part 50 ML20177A6452020-07-15015 July 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for June 2020 ML20035C4082020-02-18018 February 2020 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 02/25/2020 ML20021A2232020-01-24024 January 2020 FRN - James A. Fitzpatrick Nuclear Power Plant - Individual Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License and Opportunity for a Hearing ML19295F0902019-11-0505 November 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 11/05/2019 ML19238A3692019-09-0303 September 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 09/10/2019 ML19085A2172019-03-29029 March 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 04/09/2019 ML18304A3042018-11-23023 November 2018 Federal Register Notice: Environmental Assessment and Finding of No Significant Impact Regarding Exelon Generation Company, LLC License Amendment Request to Change Emergency Plan Staffing NRC-2018-0262, Federal Register Notice: Environmental Assessment and Finding of No Significant Impact Regarding Exelon Generation Company, LLC License Amendment Request to Change Emergency Plan Staffing2018-11-23023 November 2018 Federal Register Notice: Environmental Assessment and Finding of No Significant Impact Regarding Exelon Generation Company, LLC License Amendment Request to Change Emergency Plan Staffing ML18184A2422018-07-0606 July 2018 Letter, Individual SUNSI Notice of Consideration of Issuance of Amendment, Revise Technical Specification 2.1.1, 'Reactor Core Sls, to Change Cycle 24 Safety Limit Minimum Critical Power Ratio Numeric Values NRC-2018-0140, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/20182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML18180A2182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML17240A0482017-11-0808 November 2017 FRN Order Approving Direct Transfer of Renewed Facility Operating License and Independent Spent Fuel Storage Installation General License and Conforming Amendment NRC-2017-0177, FRN Order Approving Direct Transfer of Renewed Facility Operating License and Independent Spent Fuel Storage Installation General License and Conforming Amendment2017-11-0808 November 2017 FRN Order Approving Direct Transfer of Renewed Facility Operating License and Independent Spent Fuel Storage Installation General License and Conforming Amendment ML17221A0372017-08-14014 August 2017 Notice of Consideration of Approval of Transfer of Facility Operating License and Conforming Amendment and Opportunity for a Hearing ML17221A0392017-08-14014 August 2017 Federal Register Notice of Consideration of Approval of Transfer or License and Conforming Amendment NRC-2017-0128, FRN Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Sig. Hazards Consideration Determination, and Opportunity for Hearing2017-05-24024 May 2017 FRN Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Sig. Hazards Consideration Determination, and Opportunity for Hearing ML17143A1172017-05-24024 May 2017 FRN Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Sig. Hazards Consideration Determination, and Opportunity for Hearing ML17041A2742017-03-0101 March 2017 Federal Register Notice - Order Approving Direct License Transfer of FitzPatrick Power Plant from Entergy Nuclear FitzPatrick, LLC and Entergy Nuclear Operations, Inc. to Exelon Generation Company, LLC ML16336A5002017-01-27027 January 2017 Federal Register Notice of Issuance of Order for Mta Transfer of Indian Pt 3 and FitzPatrick to Entergy Nuclear Operations, Inc. NRC-2017-0015, Federal Register Notice of Issuance of Order for Mta Transfer of Indian Pt 3 and FitzPatrick to Entergy Nuclear Operations, Inc. (CAC Nos. MF8286 and MF8287)2017-01-27027 January 2017 Federal Register Notice of Issuance of Order for Mta Transfer of Indian Pt 3 and FitzPatrick to Entergy Nuclear Operations, Inc. (CAC Nos. MF8286 and MF8287) ML16244A7382016-10-20020 October 2016 FRN Regarding Exemption from the Requirements of 10 CFR Part 73, Sections 55(p)(1)(i) and (p)(1)(ii) Related to the Suspension of Security Measures in an Emergency or During Severe Weather NRC-2016-0221, FRN Regarding Exemption from the Requirements of 10 CFR Part 73, Sections 55(p)(1)(i) and (p)(1)(ii) Related to the Suspension of Security Measures in an Emergency or During Severe Weather2016-10-20020 October 2016 FRN Regarding Exemption from the Requirements of 10 CFR Part 73, Sections 55(p)(1)(i) and (p)(1)(ii) Related to the Suspension of Security Measures in an Emergency or During Severe Weather ML16271A0922016-09-28028 September 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: October 11, 2016 NRC-2016-0202, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 27, 20162016-09-19019 September 2016 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 27, 2016 ML16257A5172016-09-19019 September 2016 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 27, 2016 ML16243A0562016-09-0909 September 2016 FRN for License Transfer for FitzPatrick NPP: from ENO to Exelon ML16243A0552016-09-0909 September 2016 Notice of Consideration of Approval of Transfer of Renewed Facility Operating License and Conforming Amendment, and Opportunity for a Hearing - James A. Fitzpatrick Nuclear Power Plant NRC-2016-0071, FRN - Withdrawal of Amendment Request to Revise Technical Specification 5.5.6 for Extension of Type a and Type C Leak Rate Test Frequencies2016-03-29029 March 2016 FRN - Withdrawal of Amendment Request to Revise Technical Specification 5.5.6 for Extension of Type a and Type C Leak Rate Test Frequencies ML16082A4962016-03-29029 March 2016 Letter - Withdrawal of Amendment Request to Revise Technical Specification 5.5.6 for Extension of Type a and Type C Leak Rate Test Frequencies ML16082A4682016-03-29029 March 2016 FRN - Withdrawal of Amendment Request to Revise Technical Specification 5.5.6 for Extension of Type a and Type C Leak Rate Test Frequencies ML16004A1182016-01-0707 January 2016 FRN, Issuance of Confirmatory Orders, Authorize Use of Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended ML15320A0212015-12-0808 December 2015 Cover Letter for Transmitting Final Fonsi EA Related to Preemption Authority Requests (Firearms) ML15177A2162015-10-22022 October 2015 James. a FitzPatrick Nuclear Power Plant - Draft Environmental Assessment ML15177A2082015-10-22022 October 2015 Draft Environmental Assessment and Finding of No Significant Impact Related to Preemption Authority Requests ML15162A6902015-08-27027 August 2015 G20130211 - Transmittal Letter to Petitioner Judson Regarding Final Director'S Decision for James A. FitzPatrick Power Plant, Pilgrim Nuclear Power Station and Vermont Yankee Nuclear Power Station ML15204A2792015-07-27027 July 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 4, 2015 ML14335A6302015-01-15015 January 2015 G20110262 - Final Response to Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units ML14335A6482015-01-15015 January 2015 G20110262 - FRN - Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units NRC-2015-0009, G20110262 - FRN - Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units2015-01-15015 January 2015 G20110262 - FRN - Paul Gunter and Kevin Kamps Letter 2.206 - Immediately Suspend the Operating License of General Electric Boiling Water Reactors Mark I Units ML14205A3142014-07-28028 July 2014 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations- Published July 22, 2014 ML14189A6652014-07-24024 July 2014 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information - August 5, 2014 ML14177A6452014-06-27027 June 2014 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations 2021-05-26
[Table view] Category:Letter
MONTHYEARIR 05000333/20230042024-02-0707 February 2024 Integrated Inspection Report 05000333/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200012/2023001 ML24037A0102024-02-0606 February 2024 Requalification Program Inspection ML24018A0012024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000333/2024010) and Request for Information ML24004A2302024-01-0808 January 2024 Project Manager Reassignment ML23356A0832024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0058 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines JAFP-23-0065, License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications2023-12-14014 December 2023 License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications IR 05000333/20234012023-12-0808 December 2023 Cybersecurity Inspection Report 05000333/2023401 (Cover Letter Only) RS-23-126, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) JAFP-23-0069, Supplemental Response to Part 73 Exemption Request Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements2023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements JAFP-23-0057, and Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-22022 November 2023 and Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation JAFP-23-0064, Emergency Plan Document Revision2023-11-15015 November 2023 Emergency Plan Document Revision JAFP-23-0063, Registration of Spent Fuel Cask Use2023-11-13013 November 2023 Registration of Spent Fuel Cask Use IR 05000333/20230032023-11-13013 November 2023 Integrated Inspection Report 05000333/2023003 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000333/20230102023-10-26026 October 2023 Biennial Problem Identification and Resolution Inspection Report 05000333/2023010 JAFP-23-0059, Registration of Spent Fuel Cask Use2023-10-24024 October 2023 Registration of Spent Fuel Cask Use IR 05000333/20233012023-10-19019 October 2023 Initial Operator Licensing Examination Report 05000333/2023301 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans JAFP-23-0050, Physical Security Plan, Revision 242023-08-31031 August 2023 Physical Security Plan, Revision 24 JAFP-23-0048, Supplemental Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2023-08-31031 August 2023 Supplemental Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis IR 05000333/20230052023-08-31031 August 2023 Updated Inspection Plan for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2023005) JAFP-23-0047, Correction to the 2022 Annual Radioactive Effluent Release Report2023-08-30030 August 2023 Correction to the 2022 Annual Radioactive Effluent Release Report ML23228A1342023-08-16016 August 2023 Licensed Operator Positive Fitness-For-Duty Test IR 05000333/20230022023-08-0707 August 2023 Integrated Inspection Report 05000333/2023002 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor JAFP-23-0040, License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2023-08-0303 August 2023 License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis JAFP-23-0043, 10 CFR 50.46 Annual Report2023-07-31031 July 2023 10 CFR 50.46 Annual Report JAFP-23-0038, License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance2023-07-28028 July 2023 License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance ML23208A1622023-07-27027 July 2023 Operator Licensing Examination Approval IR 05000333/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000333/2023402 IR 05000333/20230112023-07-25025 July 2023 Post-Approval Site Inspection for License Renewal - Phase 4 Inspection Report 05000333/2023011 IR 05000333/20235012023-07-20020 July 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000333/2023501 JAFP-23-0033, License Amendment Request - Technical Specifications (TS) Section 3.3.1.2, Source Range Monitors (SRM) Instrumentation2023-06-28028 June 2023 License Amendment Request - Technical Specifications (TS) Section 3.3.1.2, Source Range Monitors (SRM) Instrumentation IR 05000333/20234202023-06-26026 June 2023 Security Baseline Inspection Report 05000333 2023420 RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23164A0322023-06-13013 June 2023 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000333/2023010 ML23152A0042023-06-0101 June 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000333/2023401 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling JAFP-23-0025, 2022 Annual Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Annual Radiological Environmental Operating Report IR 05000333/20230012023-05-0303 May 2023 Integrated Inspection Report 05000333/2023001 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI JAFP-23-0023, 2022 Annual Radioactive Effluent Release Report2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report IR 05000333/20230122023-04-13013 April 2023 Quadrennial Fire Protection Inspection Report 05000333/2023012 ML23095A3722023-04-0505 April 2023 2023 Updated Final Safety Analysis Report, Technical Specification Bases and Technical Requirements Manual Changes Transmittal RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations IR 05000333/20220042023-03-20020 March 2023 Integrated Inspection Report 05000333/2022004 JAFP-23-0010, 2022 REIRS Transmittal of NRC Form 52023-03-20020 March 2023 2022 REIRS Transmittal of NRC Form 5 ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 2024-02-07
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 HaTch 4, 2010 Vice President, Operations Entergy Nuclear Operations, Inc. James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 SUB..JAMES A. FITZPATRICK NUCLEAR POWER PLANT -ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT (TAC NO. ME0727)
Dear Sir or Madam:
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your application for exemption dated February 18, 2009, as supplemented by letters dated March 30, November 17, December 11, 2009, and January 19, 2010. The proposed exemption would allow operator manual action, in a safe area of the reactor building, that will prevent the failure of the systems in Fire Area 10 from affecting the ability to achieve and maintain hot shutdown conditions of the reactor as required by Title 10 of the Code of Federal Regulations Part 50, Appendix R,Section III.G.2. The environmental assessment is being forwarded to the Office of the Federal Register for publication.
Sincerely, Bhalchandra K. Vaidya, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.
Environmental cc w/encl: Distnbution via Listserv 7590-01-P UNITED STATES NUCLEAR REGULATORY COMMISSION JAMES A. FITZPATRICK NUCLEAR POWER PLANT DOCKET NO. 50-333 ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT The U. S. Nuclear Regulatory Commission (NRC) is considering issuance of an exemption from the requirements of Part 50 of Title 10 of the Code of Federal Regulations (10 CFR), Appendix R, "Fire Protection Program for Nuclear Power Facilities Operating Prior to January 1, 1979," issued to Entergy Nuclear Operations, Inc. (the licensee), for the operation of the James A. FitzPatrick Nuclear Power Plant (JAFNPP) located in Oswego County, NY. Therefore, as required by 10 CFR 51.21, the NRC is issuing this environmental assessment and finding of no significant impact. ENVIRONMENTAL ASSESSMENT Identification of Proposed Action: Regulatory Issue Summary (RIS) 2006-10 documents the NRC position on the use of operator manual actions as part of a compliance strategy to meet the requirements of 10 CFR Part 50, Appendix R, Section III.G.2. The NRC requires plants which credit manual actions for 10 CFR Part 50, Appendix R, Section III.G.2 compliance to obtain NRC approval for the manual action using the exemption process in accordance with the requirements of 10 CFR 50.12. In response to RIS 2006-10, the licensee requested this licensing action which would exempt the JAFI\IPP from the requirements of 10 CFR Part 50, Appendix R, Section III.G.2. The proposed exemption would allow operator manual action, in a safe area of the reactor bUilding, that will prevent the failure of the systems in Fire Area 10 from affecting the ability to achieve and
-2 maintain hot shutdown conditions of the reactor as required by Title 10 of the Code of Federal Regulations Part 50, Appendix R,Section III.G.2. The proposed action is in accordance with the licensee's application dated February 18, 2009, as supplemented by letters dated March 30, November 17, December 11, 2009, and January 19, 2010. Portions of letters dated February 18 and March 30, 2009, contain security related sensitive information, and are withheld from public disclosure in accordance with 10 CFR 2.390. Publicly available versions of the letters dated February 18, and March 30, 2009, are accessible electronically from the Agencywide Documents Access and Management System (ADAMS) with Accession Nos. ML090860980 and ML091320387, respectively.
Also, the letters dated November 17, December 11, 2009, and January 19, 2010, are accessible electronically from ADAMS with Accession Nos. ML093270075, ML093520408, and ML100210195, respectively.
The Need for the Proposed Action: The proposed action is needed to allow the licensee an alternate method, not authorized in 10 CFR Part 50, to achieve and maintain hot shutdown conditions in the event of a fire that could disable electrical cables and equipment in Fire Area 10. The criteria for granting specific exemptions from 10 CFR Part 50 Regulations are specified in 10 CFR 50.12. In accordance with 10 CFR 50.12(a)(1), the NRC is authorized to grant an exemption upon determining that the exemption is authorized by law, will not present an undue risk to the public health and safety, and is consistent with the common defense and security.
-Environmental Impacts of the Proposed Action: The NRC has completed its evaluation of the environmental impact of the proposed action. The staff has concluded that such actions would not adversely affect the environment.
The proposed action would not result in an increased radiological hazard. There will be no change to the radioactive effluent releases that effect radiation exposures to plant workers and members of the public. The proposed action will be performed inside the reactor building.
No changes will be made to plant structures or the site property.
Therefore, no changes or different types of radiological impacts are expected as a result of the proposed exemption.
The proposed action does not result in changes to land use or water use, or result in changes to the quality or quantity of non-radiological effluents.
No changes to the National Pollution Discharge Elimination System permit are needed. No effects on the aquatic or terrestrial habitat in the vicinity or the plant, or to threatened, endangered, or protected species under the Endangered Species Act, or impacts to essential fish habitat covered by the Magnuson-Steven's Act are expected.
There are no impacts to historical and cultural resources.
There would be no impact to socioeconomic resources.
Therefore, no changes or different types of non-radiological environmental impacts are expected as a result of the proposed exemption.
Accordingly, the NRC concludes that there are no significant environmental impacts associated with the proposed action. The details of the staff's safety evaluation will be provided in the license exemption that will be issued as part of the letter to the licensee approving the exemption to the regulation.
Environmental Impacts of the Alternatives to the Proposed Action: As an alternative to the proposed action, the NRC staff considered denial of the proposed action (i.e., the "no-action" alternative).
Denial of the application would result in no
-change in current environmental impacts. The environmental impacts of the proposed action and the alternative action are similar. Alternative Use of Resources:
The action does not involve the use of any different resources than those previously considered in the Final Environmental Statement for the James A. FitzPatrick Nuclear Power Plant, Docket No. 50-333, dated March 1973 and "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding James A. FitzPatrick Nuclear Power Plant (NUREG-1437, Supplement
- 31) Final Report." Agencies and Persons Consulted:
In accordance with its stated policy and the requirements of 10 CFR 51.30(a)(2), on May 4,2009, the NRC staff consulted with the New York State official, at the New York State Energy Research and Development Authority, regarding the environmental impact of the proposed action. The New York State official provided comments bye-mail dated June 12, 2009 (ADAMS Accession No. ML091690397).
One comment is related to Federal Regulations governing the exemption process. Regulations under 10 CFR 50.12, "Specific exemptions," do not include comment period and opportunity for a hearing. The public can pursue other avenues, such as petition for changes to the regulatory framework to allow hearings via the rulemaking process (10 CFR 2.802), or a petition for enforcement action (10 CFR 2.206) where stakeholders assert that license holders are not meeting regulatory requirements.
The other comments from the New York State addressed the security issues, the feasibility of the proposed manual action during a fire, and the cumulative effects of this change in conjunction with previous fire protection changes. Based on its review the NRC staff has determined that the comments do not pertain to the environmental impacts associated with the
-proposed exemption request and therefore, do not alter the staff's finding that there are no significant environmental impacts associated with the proposed exemption request. However, the comments related to the safety aspect of the exemption request will be appropriately considered in the NRC staff's safety evaluation.
FINDING OF NO SIGNIFICANT IMPACT On the basis of the environmental assessment, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment.
Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action. For further details with respect to the proposed action, see the licensee's letter dated February 18, 2009, as supplemented by letters dated March 30, November 17, December 11, 2009, and January 19, 2010. Portions of letters dated February 18 and March 30, 2009, contain security related sensitive information, and are withheld from public disclosure in accordance with 10 CFR 2.390. Publicly available versions of the letters dated February 18, and March 30, 2009, are accessible electronically from the Agencywide Documents Access and Management System (ADAMS) with Accession Nos. ML090860980 and ML091320387, respectively.
Also, the letters dated November 17, December 11,2009, and January 19, 2010, are accessible electronically from ADAMS with Accession Nos. ML093270075, ML093520408, and ML100210195, respectively.
Publicly available versions of the documents may be examined, and/or copied for a fee, at the NRC's Public Document Room (PDR), located at One White Flint North, Public File Area 01 F21, 11555 Rockville Pike (first floor), Rockville, Maryland.
Publicly available records will be accessible electronically from the ADAMS Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html.
-6 Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or send an e-mail to pdr.resource@nrc.gov.
Dated at Rockville, Maryland, this 4th day of March 2010. FOR THE NUCLEAR REGULATORY COMMISSION -' Bhalchandra K. Vaidya, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Vice President, Operations Entergy Nuclear Operations, Inc. James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 JAMES A. FITZPATRICK NUCLEAR POWER PLANT -ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT (TAC NO. ME0727)
Dear Sir or Madam:
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your application for exemption dated February 18, 2009, as supplemented by letters dated March 30, November 17, December 11,2009, and January 19, 2010. The proposed exemption would allow operator manual action, in a safe area of the reactor building, that will prevent the failure of the systems in Fire Area 10 from affecting the ability to achieve and maintain hot shutdown conditions of the reactor as required by Title 10 of the Code of Federal Regulations Part 50, Appendix R,Section III.G.2. The environmental assessment is being forwarded to the Office of the Federal Register for publication.
Sincerely, IRA! Bhalchandra K. Vaidya, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.
Environmental cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL 1-1 R/F RidsNrrDorlLpl-1 RidsOGCMailCenter RidsAcrsAcnwMailCenter RidsNrrPMFitzPatrick (paper copy) RidsNrrDlrRerb RidsNrrLASLittle (paper copy) MGray, RI RidsRgn1 MailCenter RidsOgcRp Resource ADAMS Accession No ML091240142 , OFFICE NRR/LPL 1-1/PM NRR/LPL 1-1/LA N RR/DLR/RERB/BC NRR/DRAlAFPB/BC NAME BVaidya SLittie Almboden AKlein DATE 01/26/10 01/19/10 01/29/10 02/23/10 OFFICE OGC/NLO NRRIILPL 1-1/BC NRR/LPL1-1/PM NAME LSubin NSalQado BVaidya DATE 02/25/10 03/02/10 03/04/10 OFFICIAL RECORD COPY