Line 2: |
Line 2: |
| | number = ML112590334 | | | number = ML112590334 |
| | issue date = 09/16/2011 | | | issue date = 09/16/2011 |
| | title = Fort Calhoun, Unit 1 - E-mail, Draft Request for Additional Information, Amendment Request to Establish Ultimate Heat Sink LCOs in TS 2.16, River Level, and Add Surveillance Requirements to TS 3.2, Equipment and Sampling Tests (TAC No. ME58 | | | title = E-mail, Draft Request for Additional Information, Amendment Request to Establish Ultimate Heat Sink LCOs in TS 2.16, River Level, and Add Surveillance Requirements to TS 3.2, Equipment and Sampling Tests (TAC No. ME5830) |
| | author name = Wilkins L E | | | author name = Wilkins L E |
| | author affiliation = NRC/NRR/DORL/LPLIV | | | author affiliation = NRC/NRR/DORL/LPLIV |
Revision as of 04:49, 30 January 2019
Letter Sequence Draft RAI |
---|
|
|
MONTHYEARLIC-11-0017, License Amendment Request (LAR) 10-06, Proposed Change to Establish the Ultimate Heat Sink (UHS) Limiting Condition for Operation (LCO) and Addition of UHS Level and Temperature Surveillance Requirements2011-03-0404 March 2011 License Amendment Request (LAR) 10-06, Proposed Change to Establish the Ultimate Heat Sink (UHS) Limiting Condition for Operation (LCO) and Addition of UHS Level and Temperature Surveillance Requirements Project stage: Request ML1109605292011-04-0606 April 2011 Acceptance Review Email, License Amendment Request, Establish Ultimate Heat Sink LCOs in Technical Specification (TS) 2.16, River Level, and Add Surveillance Requirements to TS 3.2, Equipment and Sampling Tests. Project stage: Acceptance Review ML1125903392011-09-16016 September 2011 Draft Request for Additional Information, Amendment Request to Establish Ultimate Heat Sink LCOs in TS 2.16, River Level, and Add Surveillance Requirements to TS 3.2, Equipment and Sampling Tests Project stage: Draft RAI ML1125903342011-09-16016 September 2011 E-mail, Draft Request for Additional Information, Amendment Request to Establish Ultimate Heat Sink LCOs in TS 2.16, River Level, and Add Surveillance Requirements to TS 3.2, Equipment and Sampling Tests Project stage: Draft RAI ML1127703142011-10-19019 October 2011 Request for Additional Information, Amendment Request to Establish Ultimate Heat Sink LCOs in TS 2.16, River Level, and Add Surveillance Requirements to TS 3.2, Equipment and Sampling Tests Project stage: RAI LIC-11-0127, Retraction of License Amendment Request (LAR) 10-062012-01-0404 January 2012 Retraction of License Amendment Request (LAR) 10-06 Project stage: Request ML1202701822012-02-0202 February 2012 Withdrawal of an Amendment Request to Establish Ultimate Heat Sink LCOs in TS 2.16, River Level, and Add Surveillance Requirements to TS 3.2, Equipment and Sampling Tests Project stage: Withdrawal 2011-04-06
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24289A2052024-10-0909 October 2024 E-mail with Responses to Clarification Questions on Response to Request for Additional Information on the Phase 1 Final Status Survey Reports ML24025A1792024-01-23023 January 2024 State Consultation Response e-mail on Fort Calhoun Station, Unit 1 License Termination Plan License Amendment– (License No. DPR-40, Docket No. 50-285) ML24024A2242024-01-22022 January 2024 State Consultation e-mail on Fort Calhoun Station, Unit 1 License Termination Plan License Amendment- (License No. DPR-40, Docket No. 50-285) ML23311A0862023-11-0505 November 2023 Letter to M Morales Re Ft Calhoun License Termination Section 7 Determination for Ipac 2022-0029456 ML23038A1882023-01-31031 January 2023 Request for Additional Time to Respond to Request for Additional Information on License Amendment Request for Approval of License Termination Plan (License No. DPR-40, Docket No. 50-285) ML22222A1192022-08-0808 August 2022 Email Section 106 NHPA- Ft Calhoun Station License Termination Plan ML21069A2482021-03-10010 March 2021 Umax, 07200054, 05000361, 05000362, FSAR Revision 4 for San Onofre ISFSI ML21335A3352021-01-25025 January 2021 January 25, 2021 e-mail from J. Parrott, NRC to C. Cameron, OPPD Use of Resrad Model to Represent Well Water Concentrations in a Basement Substructure (License No. DPR-40, Docket No. 50-285) ML20204B0782020-07-22022 July 2020 Donna Gilmore Email Holtec Umax Materials (07200054, 05000361, 05000362) ML20113F0622020-04-22022 April 2020 E-mail Results of Acceptance Review of OPPD Request for Exemption from 10 CFR 20, App G, Section Iii.E (License No. DPR-40, Docket No. 50-285) ML20100J2272020-03-26026 March 2020 E-mail Notification to the State of Nebraska on the Issuance of the License Amendment for Revised Security Plans to Reflect an ISFSI-only Configuration (License No. DPR-40, Docket Nos. 50-285 and 72-54) ML20100L7232020-03-15015 March 2020 Email: Town of Desoto National Register of Historic Places Eligibility ML19353C3612019-12-11011 December 2019 E-mail to State of Nebraska Informing of the Pending Revision to the Emergency Plan to Reflect Independent Spent Fuel Storage Installation Only Status (License DPR-40, Docket Nos. 50-285 and 72-054) ML19309F1112019-10-11011 October 2019 ISFSI-Only Tech Specs ML19241A1812019-08-21021 August 2019 Request for Additional Information on Proposed Changes to the FCS Emergency Plan and Emergency Action Level Scheme to Reflect an ISFSI-only Status ML19175A0212019-06-19019 June 2019 Acceptance Review - License Amendment Request to Revise Security and Safeguards Requirements to Reflect ISFSI-Only Configuration ML19130A2082019-05-0808 May 2019 Email - NRC Email to FEMA Dated May 8, 2019: NRC Response to Comment on FEMA Review of Proposed Changes to DBNPS Emergency Plan for Permanently Defueled Condition ML19126A2802019-05-0101 May 2019 Acceptance Review - License Amendment Request for ISFSI-Only EP and EAL Scheme ML18100A2712018-04-0909 April 2018 04-09-18 OPPD E-Mail (FCS Permanently Defueled Emergency Plan Implementation) ML17236A3462017-08-24024 August 2017 NRR E-mail Capture - Final RAI for Fort Calhoun LAR Regarding Permanently Defueled TS (MF9567) ML17236A3442017-08-24024 August 2017 NRR E-mail Capture - Final RAI for Fort Calhoun Exemption from 10 CFR 140.11(a)(4), Off-site Primary and Secondary Liability Insurance (MF9664) ML17234A4692017-08-22022 August 2017 NRR E-mail Capture - Final RAI for Fort Calhoun LAR Regarding Removal of Dry Cask Loading Limits (MF9831) ML17194A9732017-07-13013 July 2017 NRR E-mail Capture - Final RAI for Fort Calhoun Ultimate Strength Design for Aux. Bldg LAR (MF8525) ML17191B0212017-07-10010 July 2017 NRR E-mail Capture - Fort Calhoun - Acceptance Review of Modification of LC 3.C to Delete Commission-approved CSP ML17184A0042017-06-30030 June 2017 NRR E-mail Capture - Fort Calhoun - Acceptance Review of Removal of Dry Cask Loading Limits ML17139C8342017-05-19019 May 2017 NRR E-mail Capture - Fort Calhoun - Acceptance Review Partial Exemption from Record Retention Requirements ML17139C5082017-05-19019 May 2017 NRR E-mail Capture - (External_Sender) Need Corrected Page 6 for LIC-17-0043 ML17144A0132017-05-19019 May 2017 NRR E-mail Capture - Fort Calhoun PSDAR - Findings and Concerns ML17142A0202017-05-19019 May 2017 NRR E-mail Capture - (External_Sender) Need Corrected Page 6 to TQ-DC-FC-101 ML17139B6762017-05-18018 May 2017 NRR E-mail Capture - Fort Calhoun - Acceptance Review Exemption from 10 CFR 140.11(a)(4), Off-Site Liability Insurance ML17139B6782017-05-18018 May 2017 NRR E-mail Capture - Fort Calhoun - Acceptance Review Exemption from 10 CFR 50.54(w)(1), On-Site Property Damage Insurance ML17136A1692017-05-16016 May 2017 NRR E-mail Capture - (External_Sender) OPPD FCS Decommissioning Financial Reports ML17115A4722017-04-25025 April 2017 NRR E-mail Capture - (External_Sender) Corrected Page 18 to TQ-DC-FC-201 ML17114A3112017-04-24024 April 2017 NRR E-mail Capture - Fort Calhoun - Acceptance Review TS Changes to Align for Decommissioning ML17112A0362017-04-20020 April 2017 NRR E-mail Capture - Fort Calhoun Station - Final RAI Regarding Permanently Defueled EP and EAL Scheme Change LAR ML17090A3942017-03-31031 March 2017 NRR E-mail Capture - Fort Calhoun - Final RAI Regarding Administrative Control TS Change LAR (MF8437) ML17082A0022017-03-22022 March 2017 NRR E-mail Capture - Fort Calhoun Station - Final Nsir/Dpr RAI Regarding Proposed Emergency Planning Exemption ML17081A0192017-03-21021 March 2017 NRR E-mail Capture - Fort Calhoun Station - Final RAI Regarding Proposed Emergency Planning Exemption ML17052A0272017-02-15015 February 2017 NRR E-mail Capture - Fort Calhoun Station, Unit No. 1 - Acceptance of Requested Amendment Revise Permanently Defueled Emergency Plan and EAL Scheme ML17033A9692017-02-0202 February 2017 NRR E-mail Capture - Fort Calhoun Station - Final Request for Additional Information Concerning Post-Shutdown Eplan Amendment ML16351A0432016-12-15015 December 2016 NRR E-mail Capture - (External_Sender) Fort Calhoun Station Offsite Response Organizations ML16350A0392016-12-15015 December 2016 NRR E-mail Capture - Acceptance Review (CAC No. MF8858) Fort Calhoun, Unit 1 - License Amendment Request (LAR) 16-06; Removal of License Condition 3.D., Fire Protection Program ML16334A3002016-11-29029 November 2016 NRR E-mail Capture - Acceptance Review (CAC No. MF8525) Fort Calhoun, Unit 1 - License Amendment Request LAR-16-04 to Revise Current Licensing Basis to Use Aci Ultimate Strength Requirements ML16333A2312016-11-28028 November 2016 NRR E-mail Capture - Acceptance Review (CAC No. MF8843)Fort Calhoun, Unit 1, Request for Rescission of Interim Compensatory Measure B.1.a from EA-02-026, Order for Interim Safeguards and Security Compensatory Measures. ML16333A0992016-11-28028 November 2016 NRR E-mail Capture - Acceptance Review (CAC No. MF8452), Fort Calhoun, Unit 1 - Request for Exemption from Specific Provisions in 10 CFR 73.55 ML16286A0812016-10-12012 October 2016 NRR E-mail Capture - Acceptance Review Fort Calhoun Station, Unit 1, License Amendment Request 16-03, Technical Specifications to Align Staffing Requirements to Those Required for Decommissioning ML16278A0292016-10-0303 October 2016 NRR E-mail Capture - Acceptance Review Fort Calhoun Station Radiological Emergency Response Plan (RERP) for Decommissioning ML16257A0262016-09-12012 September 2016 NRR E-mail Capture - (External_Sender) OPPD Slides for 9/13/16 Pre-Application Meeting on Class 1 Structures ML16207A0182016-07-22022 July 2016 NRR E-mail Capture - Acceptance Review ML16137A0092016-05-16016 May 2016 NRR E-mail Capture - Acceptance Review CAC No. MF7574 2024-10-09
[Table view] |
Text
From: Wilkins, Lynnea Sent: Friday, September 16, 2011 1:30 PM To: HANSHER, BILL R Cc: Lent, Susan; Burkhardt, Janet
Subject:
DRAFT RAIs for Fort Calhoun Station Re: UHS Attachments: ME5830 RAIs Email.docx Bill, By letter dated March 4, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML110680093), Omaha Public Power District (OPPD, the licensee) requested an amendment to the Facility Operating License No. DPR-40 for Fort Calhoun Station, Unit 1. The proposed amendment would establish the limiting condition for operation (LCO) requirements for the ultimate heat sink (UHS) in Technical Specification (TS) 2.16, River Level, and adds two new surveillance requirements (SRs) for UHS level and temperature to TS 3.2, Equipment and Sampling Tests, Table 3-5, Minimum Frequencies for Equipment Tests. Specifically, this proposed change: revises the title of LCO 2.16 from "River Level" to "Ultimate Heat Sink (UHS);" provides more explicit applicability for the LCO 2.16; removes the existing LCOs for river level in TS 2.16, Items 1) and (2); and, reformats TS LCO 2.16 to provide required actions for an inoperable UHS. In addition, two new SRs, Items 25 and 26, will be added to TS 3.2, Table 3-5, to test the river level and temperature on a daily frequency; and for consistency, the columns will be reformatted to allow adding the column header to Table 3-5 for Items 17 through 24. The Table of Contents is also revised to reflect the title change of LCO 2.16. The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the information provided in your application and determined that additional information is required in order to complete its review. A public teleconference will be scheduled to discuss your responses to the staff's questions.
Please contact me if you have any questions.
Lynnea Wilkins, Project Manager Fort Calhoun Station, Unit 1 Cooper Nuclear Station Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation US Nuclear Regulatory Commission Phone: 301-415-1377