Issue date | Title | Topic | |
---|---|---|---|
ML16280A435 | 30 September 2016 | 2016-09 Final Written Exam | Shutdown Margin Half scram Grab sample Post Accident Monitoring Hydrostatic Squib Locked High Radiation Area Pressure boundary leak |
ML16285A017 | 30 September 2016 | 2016-09 Public Forms | |
ML16280A465 | 30 September 2016 | 2016-09 Final Outlines | Shutdown Margin |
ML16280A449 | 30 September 2016 | 2016-09-Written Handouts Package | Safe Shutdown High winds Post Accident Monitoring Internal Flooding Operating Basis Earthquake Earthquake Pressure Boundary Leakage |
ML16280A464 | 30 September 2016 | 2016-09 Draft Written Exam | Hot Short Safe Shutdown Shutdown Margin Half scram Grab sample Post Accident Monitoring Hydrostatic Squib Locked High Radiation Area Fuel cladding |
ML16280A453 | 30 September 2016 | 2016-09 Draft Op Test Comments | |
ML16280A456 | 30 September 2016 | 2016-09 Draft Op Test | Half scram Squib Scram Discharge Volume Unidentified leakage |
ML16280A462 | 30 September 2016 | 2016-09 Draft Written Comments | |
ML16280A460 | 30 September 2016 | 2016-09 Draft Outlines | Shutdown Margin Half scram |
ML16280A459 | 30 September 2016 | 2016-09 Draft Outline Comments | |
ML16259A362 | 29 September 2016 | River Bend Station, Unit 1 - Staff Review of Mitigation Strategies Assessment Report of the Impact of the Reevaluated Seismic Hazard Developed in Response to the March 12, 2012, 50.54(f) Letter | |
ML16278A641 | 23 September 2016 | FEMA, Submittal of After Action Report/Improvement Plan for the River Bend Station Exercise Evaluated on June 29, 2016 | |
ML16278A471 | 22 September 2016 | Notification of 10 CFR Part 21 Condition, Masterpact Breaker Fail to Close | |
ML16281A270 | 22 September 2016 | Part 21 - Initial Notification of Masterpact Breaker Fail to Close | |
CAC:MF6856 | 19 September 2016 | ||
ML16224B075 | 19 September 2016 | NRC Response to Request for Interpretation of Technical Specifications | Safe Shutdown Ultimate heat sink Functionality Assessment |
ML16251A620 | 13 September 2016 | Entergy Fleet Request for Approval of Change to the Entergy Quality Assurance Program Manual (CAC Nos. MF7086 - MF7097) | |
IR 05000458/2016005 | 12 September 2016 | Errata for Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2016005) | B.5.b Spent Fuel Pool Instrumentation License Renewal |
RBG-47709, Response to Request for Additional Information on Nineteenth Fuel Cycle Core Operating Limits Report | 12 September 2016 | Response to Request for Additional Information on Nineteenth Fuel Cycle Core Operating Limits Report | |
RBG-47710, Report of Changes and Errors | 12 September 2016 | Report of Changes and Errors | |
ML16280A437 | 12 September 2016 | 2016-09 Final Op Test | Half scram Squib Scram Discharge Volume Offsite Circuit Unidentified leakage |
ML16246A001 | 1 September 2016 | NRC Initial Operator Licensing Examination Approval 05000458/2016301 | |
ML16242A326 | 31 August 2016 | Mid-Cycle Assessment Letter for River Bend Station (Report 05000458/2016005) | Spent Fuel Pool Instrumentation B.5.b Mitigating Strategies |
ML16204A207 | 31 August 2016 | River Bend Station, Unit 1 - Staff Assessment of Response to 10 CFR 50.54(f) Information Request - Flood-Causing Mechanism Reevaluation (CAC MF3675) | |
RBG-47706, Unit 1- Seismic Mitigating Strategies Assessment Report | 31 August 2016 | Unit 1- Seismic Mitigating Strategies Assessment Report | Safe Shutdown Earthquake FLEX Fukushima Dai-Ichi |
IR 05000458/2016401 | 31 August 2016 | Non-Public Security Inspection Plan for River Bend Station (NRC Physical Security Inspection Report Number 05000458/2016401) | |
ML16252A274 | 29 August 2016 | Azz/Nli - Part 21 Report - Potential Allen Bradley Timing Relay | |
ML16243A474 | 26 August 2016 | Potential Part 21 Unqualified Component in Certain Allen Bradley Timing Relays | |
ML16236A370 | 25 August 2016 | Reassignment of U.S. Nuclear Regulatory Commission Branch Chief to Stephen S. Koenick for Plant Licensing IV-2 and Decommissioning Transition Branch, Effective September 4, 2016 | |
ML16236A382 | 25 August 2016 | Project Manager Assignment to James Kim Effective September 4, 2016 for Plant Licensing IV-2 and Decommissioning Transition Branch | |
RBG-47703, Updated Schedule of Submittal of Future License Renewal Application | 18 August 2016 | Updated Schedule of Submittal of Future License Renewal Application | |
ML16232A604 | 15 August 2016 | Potentially Unqualified Component in Certain Allen Bradley Timing Relays | |
ML16238A186 | 15 August 2016 | Update - Report of Potential l0CFR Part 21, Allen Bradley Timing Relay Model 700RTC-NRC Event Number 51030, Accession Number ML15134A016 | |
RBG-47701, Notification of Readiness for 92702, Follow-up on Corrective Actions for Violations and Deviations | 15 August 2016 | Notification of Readiness for 92702, Follow-up on Corrective Actions for Violations and Deviations | |
ML15292A508 | 11 August 2016 | Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 | High winds Shutdown Margin Ultimate heat sink Mission time Tornado Missile Time to boil Safe Shutdown Earthquake Internal Flooding Emergency Lighting FLEX Tornado-Generated Missile Fukushima Dai-Ichi Spent Fuel Pool Instrumentation B.5.b Mitigating Strategies Earthquake Fire Protection Program |
IR 05000458/2016011 | 10 August 2016 | NRC Supplemental Inspection Report 05000458/2016011 | Reactor Vessel Water Level Temporary Modification |
IR 05000458/2016002 | 29 July 2016 | NRC Integrated Inspection Report 5000458/2016002 & 07200049/2016001 | Safe Shutdown High winds High Radiation Area Non-Destructive Examination Hydrostatic Temporary Modification Functionality Assessment Locked High Radiation Area Condition Adverse to Quality Significance Determination Process Annual Radiological Environmental Operating Report Operability Determination Liquid penetrant Fire Protection Program |
RBG-47695, Response to Request to Additional Information Regarding RBS License Amendment Request to Extend Type a and Type C Test Frequencies | 27 July 2016 | Response to Request to Additional Information Regarding RBS License Amendment Request to Extend Type a and Type C Test Frequencies | High winds Safe Shutdown Earthquake Internal Flooding Probabilistic Risk Assessment FLEX Fukushima Dai-Ichi Large early release frequency |
05000458/LER-2016-007 | 25 July 2016 | 1 Operations Prohibited by Technical Specifications Due to Failure to Implement Required Actions Within Completion Time LER 16-007-00 for River Bend Station, Unit 1, Regarding Operations Prohibited by Technical Specifications Due to Failure to Implement Required Actions Within Completion Time | Time of Discovery |
ML16202A110 | 19 July 2016 | Notification of NRC Integrated Inspection 05000458/2016004 and Request for Information | |
CNRO-2016-00017, Entergy Nuclear Operations - Request for Approval of Change to the Quality Assurance Program Manual | 19 July 2016 | Entergy Nuclear Operations - Request for Approval of Change to the Quality Assurance Program Manual | |
ML16209A048 | 13 July 2016 | Part 21 - Initial Notification of Masterpact Breaker Fail to Close | |
ML16197A007 | 13 July 2016 | NRR E-mail Capture - (External_Sender) RAI Response Extension | |
RBG-47689, Response to Regulatory Issue Summary 2016-09 - River Bend Station, Unit 1 | 12 July 2016 | Response to Regulatory Issue Summary 2016-09 - River Bend Station, Unit 1 | |
05000458/LER-2016-006 | 12 July 2016 | Potential Loss of Safety Function of Multiple Systems Due to Design Deficiency in 480-volt Circuit Breakers LER 16-006-00 for River Bend Station re: Potential Loss of Safety Function of Multiple Systems Due to Design Deficiency in 480-volt Circuit Breakers |