IR 05000277/1990080 | 9 November 1990 | SSFI Rept 50-277/90-80 & 50-278/90-80 on 900917-1003. Significant Weaknesses Identified.Major Areas Inspected: Adequacy of Licensee Corrective Actions Implemented | Safe Shutdown Operability Determination Biofouling |
IR 05000277/1990017 | 5 October 1990 | Insp Repts 50-277/90-17 & 50-278/90-17 on 900814-0924.No Violations Noted.Major Areas Inspected:Operational Safety, Radiation Protection,Physical Security,Control Room Activities & Surveillance Testing | Reactor Vessel Water Level Packing leak High Radiation Area Half scram Excess Flow Check Valve |
IR 05000277/1990015 | 6 September 1990 | Insp Repts 50-277/90-15 & 50-278/90-15 on 900723-27. Violations Noted.Major Areas Inspected:Cleaning & Testing of Both Diesel Engine & Generator | Hydrostatic |
ML20056A506 | 30 July 1990 | Insp Repts 50-277/90-13 & 50-278/90-13 on 900516-0702. Violations Noted.Major Areas Inspected:Operational Safety, Radiation Protection,Physical Security,Control Room Activities,Licensee Events & Maint | Packing leak High Radiation Area Fire Protection Program Fire Watch |
IR 05000277/1990010 | 15 June 1990 | Insp Repts 50-277/90-10 & 50-278/90-10 on 900403-0515.No Violations Noted.Major Areas Inspected:Operational Safety, Radiation Protection,Physical Security,Licensee Events, Control Room Activities,Surveillance Testing & Maint | High Radiation Area Missed surveillance Scram Discharge Volume Fire Protection Program Grace period |
IR 05000277/1989021 | 27 September 1989 | Insp Repts 50-277/89-21 & 50-278/89-21 on 890828-0901.No Violations Noted.Major Areas Inspected:Posting & Labeling, Organization & Staffing,Radiation Work Permits,Abandoned Radwaste Sys & Auditing | |
IR 05000277/1989020 | 21 September 1989 | Insp Repts 50-277/89-20 & 50-278/89-20 on 890730-0902.No Violations Noted.Major Areas Inspected:Onsite Regular, Backshift Insp (236 H Unit 2,135 H Unit 3) of Accessible Portions of Unit 2 & 3,operational Safety & Security | High Radiation Area Grace period |
IR 05000277/1989019 | 22 August 1989 | Onsite Regular,Backshift & Deep Backshift Special Power Ascension & Restart Insps 50-277/89-19 & 50-278/89-19 on 890618-0729.No Violations Noted.Major Areas Inspected: Accessible Portions of Units 2 & 3 & Physical Security | Reactor Vessel Water Level High Radiation Area Half scram Scram Discharge Volume Earthquake Biofouling |
IR 05000277/1989017 | 27 June 1989 | Insp Repts 50-277/89-17 & 50-278/89-17 on 890613-15.No Violations Noted.Major Areas Inspected:Licensee Partial Participation in Annual Emergency Preparedness Exercise on 890614 | |
IR 05000277/1989016 | 22 June 1989 | Restart Safety Insp Repts 50-277/89-16 & 50-278/89-16 on 890507-0617.Major Areas Inspected:Unit 2 Power Ascension Transient Testing & steady-state Operation at 35% Power Plateau,Radiation Protection & Physical Security | High Radiation Area Stroke time Locked High Radiation Area Missed surveillance Scram Discharge Volume Inattentive |
IR 05000277/1989012 | 25 May 1989 | Insp Repts 50-277/89-12 & 50-278/89-12 on 890410-13.No Violations Noted.Major Areas Inspected:Changes to Emergency Preparedness Program,Emergency Facilities,Independent/ Reviews/Audits & Notifications & Communications | Siren |
IR 05000277/1989015 | 18 May 1989 | Insp Repts 50-277/89-15 & 50-278/89-15 on 890402-0506.No Violations Noted.Major Areas Inspected:Operational Safety, Unit 2 Prestartup Activities & Power Ascension & Testing, Radiation Protection & Physical Security | Safe Shutdown Unanalyzed Condition Shutdown Margin Packing leak High Radiation Area Half scram Squib Earthquake Fire Protection Program |
IR 05000277/1989013 | 10 May 1989 | Insp Repts 50-277/89-13 & 50-278/89-13 on 890405-07.No Violations or Deviations Noted.Major Areas Inspected: Licensee Action on Previously Noted Insp Findings in Electrical Area | |
IR 05000277/1989011 | 20 April 1989 | Insp Repts 50-277/89-11 & 50-278/89-11 on 890405-11.No Violations Noted.Major Areas Inspected:Implementation of Unit 2 Restart Power Testing Program,Including Review of Program & Verification Re in-plant Program | |
IR 05000277/1989006 | 12 April 1989 | Safety Insp Repts 50-277/89-06 & 50-278/89-06 on 890227-0307.No Violations or Deviations Noted.Major Areas Inspected:Previously Identified Open Items in Inservice Testing & Local Leak Rate Testing Areas | Stroke time Hydrostatic Excess Flow Check Valve Exemption Request |
IR 05000277/1989014 | 11 April 1989 | Physical Security Insp Repts 50-277/89-14 & 278/89-14 on 890405.All Commitments Made to Resolve Open Items Met.Major Areas Inspected:Progress to Date on Open Items in Insp Repts 50-277/89-80 & 50-278/89-80 | |
ML20248D615 | 28 March 1989 | Insp Repts 50-277/89-04 & 50-278/89-04 on 890109-14.No Violations Noted.Major Areas Inspected:Licensee Actions in Response to NRC Ltr to Pepco Re Allegations on motor- Operated Valve Refurbishment | |
IR 05000277/1989007 | 21 March 1989 | Insp Repts 50-277/89-07 & 50-278/89-07 on 890130-0210. Violations Noted.Major Areas Inspected:Electrical Power Sys Including Verification of as-built Drawings,Adequacy of Breaker & Fuse Coordination & Plant Mods | Anticipated operational occurrence Probabilistic Risk Assessment Battery sizing Earthquake |
IR 05000277/1989080 | 16 March 1989 | Physical Security Insp Repts 50-277/89-80 & 50-278/89-80 on 890105-27.Major Areas Inspected:Security Program Mgt & Effectiveness,Personnel Experience & Qualifications,Testing & Maint & Licensee self-assessments & Audits | |
IR 05000277/1989081 | 6 March 1989 | Integrated Assessment Team Insp Repts 50-277/89-81 & 50-278/89-81 on 890203-17.Major Areas Inspected: Effectiveness of Restart Plan Corrective Actions & Degree of Readiness of Licensee Mgt Controls | |
IR 05000277/1988041 | 8 November 1988 | Insp Repts 50-277/88-41 & 50-278/88-41 on 881003-07.No Violations Noted.Major Areas Inspected:Fire Protection/ Prevention Program | Safe Shutdown Fire Barrier |
IR 05000277/1988035 | 3 November 1988 | Insp Repts 50-277/88-35 & 50-278/88-35 on 880926-30.No Violations Noted.Major Areas Inspected:Licensee Performance in Areas of Maint Surveillance Procedures & Records That Verify Component Availability,Per Tech Spec Requirements | Safe Shutdown Fire Barrier Scram Discharge Volume |
IR 05000277/1988037 | 3 November 1988 | Insp Repts 50-277/88-37 & 50-278/88-37 on 880926-30.No Violations Noted.Major Areas Inspected:Radiation Safety Program,Including Status of Previously Identified Items & post-project Reviews of Unit 3 Pipe Replacement | |
ML20206L425 | 1 November 1988 | Insp Repts 50-277/88-38 & 50-278/88-38 on 880926-30. Violations Noted.Major Areas Inspected:Licensee Corrective Actions for Previous Environ Qualification (EQ) Findings & Licensee EQ Documentation Re Cable Splices Qualificability | |
ML20206D312 | 27 October 1988 | Insp Repts 50-277/88-32 & 50-278/88-32 on 880831-0929.No Violations or Deviations Noted.Major Areas Inspected: Licensed Operator Requalification Training Program. Weaknesses in Requalification Program Identified | Safe Shutdown Job Performance Measure Earthquake |
IR 05000277/1988034 | 25 October 1988 | Insp Repts 50-277/88-34 & 50-278/88-34 on 880903-1014.No Violations Noted.Major Areas Inspected:Accessible Portions of Units 2 & 3 Operational Safety,Radiation Protection, Physical Security,Control Room Activities & Licensee Events | Fitness for Duty High Radiation Area Fire Barrier Stroke time Anticipated operational occurrence Hydrostatic Earthquake Continuous fire watch Fire Watch Inattentive |
IR 05000277/1988028 | 18 October 1988 | Insp Repts 50-277/88-28 & 50-278/88-28 on 880829-0902.No Violations Noted.Major Areas Inspected:Review of Licensee Operating procedures,non-licensed Operators Training & on Site & Offsite Review Committees | Non-Destructive Examination |
IR 05000277/1988036 | 12 October 1988 | Insp Repts 50-277/88-36 & 50-278/88-36 on 880926-28.No Violations Noted.Major Areas Inspected:Annual full-participation Emergency Exercise Performed on 880927 | Health Physics Network Fuel cladding |
IR 05000277/1988017 | 6 October 1988 | In-Depth Team Insp Repts 50-277/88-17 & 50-278/88-17 on 880711-22.Violations Noted.Major Areas Inspected:Facility Maint Program & Program Implementation | Fitness for Duty Hydrostatic Probabilistic Risk Assessment Systematic Assessment of Licensee Performance |
IR 05000277/1988033 | 4 October 1988 | Insp Repts 50-277/88-33 & 50-278/88-33 on 880906-09.No Violations Noted.Unresolved Item Noted.Major Areas Inspected:Radioactive Effluent Controls Program,Including Releases,Radiation Monitoring Sys Calibr & Surveillances | |
IR 05000277/1988029 | 19 September 1988 | Insp Repts 50-277/88-29 & 50-278/88-29 on 880805 & 08-12.No Violations Noted.Major Areas Inspected:Replacement of Unit 2 & 3 Emergency Water sys,errosion-corrosion Program in Unit 2 & 3 & Radiographic Condition of Unit 3 Recirculation Pump | Liquid penetrant |
IR 05000277/1988024 | 16 September 1988 | Insp Repts 50-277/88-24 & 50-278/88-24 on 880716-0902.No Violations Noted.Major Areas Inspected:Operational Safety, Radiation Protection,Physical Security,Control Room Activities & Surveillance Testing | Fitness for Duty Packing leak High Radiation Area Half scram Fire Barrier Hydrostatic Inattentive |
IR 05000277/1988031 | 8 September 1988 | Partially Deleted Insp Repts 50-277/88-31 & 50-278/88-31 on 880827-29 (Ref 10CFR73.21).Violation Noted.Major Areas Inspected:Mgt Effectiveness,Assessment Aids - Protected Area & Access Control - Personnel | |
ML20154L175 | 8 September 1988 | Partially Deleted Insp Repts 50-277/88-26 & 50-278/88-26 on 880725-29 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Assessment Aids - Protected Area & Access Control - Personnel & Mgt Effectiveness | Fitness for Duty |
ML20153D074 | 25 August 1988 | Insp Repts 50-277/88-30 & 50-278/88-30 on 880815-19. Violations Noted.Major Areas Inspected:Adequacy of Licensee Actions in Response to IE Bulletin 80-11 & Adequacy of Corrective Actions in Response to Violation 87-16-01 | |
IR 05000277/1988023 | 23 August 1988 | Physical Security Insp Repts 50-277/88-23 & 50-278/88-23 on 880627-30.No Violations Observed.Major Areas Inspected: Followup on Licensee Implementation of Commitments Identified in Util 880603,13,17 & 24 Ltrs | Fitness for Duty Safeguards Contingency Plan Inattentive |
IR 05000277/1988027 | 15 August 1988 | Insp Repts 50-277/88-27 & 50-278/88-27 on 880802-04.No Violations Noted.Major Areas Inspected:Emergency Response Facilities,Public Info Program,Changes to Emergency Prearedness Program & Followup of Previously Noted Issues | |
IR 05000277/1988025 | 11 August 1988 | Insp Repts 50-277/88-25 & 50-278/88-25 on 880718-22.No Violations or Deviations Noted.Major Areas Inspected:Util Licensed Operator Requalification Program W/Respect to Program Effectiveness | |
IR 05000277/1988018 | 26 July 1988 | Insp Repts 50-277/88-18 & 50-278/88-18 on 880604-0715.No Violations Noted.Major Areas Inspected:Accessible Portions of Unit 2 & 3,operational Safety,Radiation Protection, Physical Security,Control Room Activities & Maint | Unanalyzed Condition Fitness for Duty Fire Barrier Contraband Nondestructive Examination Locked High Radiation Area |
IR 05000277/1988021 | 21 July 1988 | Mgt Meeting Insp Repts 50-277/88-21 & 50-278/88-21 on 880609 Re Security Concerns at Plant Reported in Annual Security Audit & Findings of Util Investigation Into Allegations by Members of Plant Security Force | |
IR 05000278/1988014 | 20 July 1988 | Insp Rept 50-278/88-14 on 880509-20.Unresolved Items & Concerns Noted.Major Areas inspected:safety-related Piping Weldments Selected from Plant Replacement Piping Program Insp Plan,Including Welding & Preservice Insp | Nondestructive Examination Liquid penetrant Dissimilar Metal Weld |
IR 05000277/1988019 | 18 July 1988 | Insp Repts 50-277/88-19 & 50-278/88-19 on 880606-10.No Violations Noted.Major Areas Inspected:Implementation & Effectiveness of Corrective Actions in QA Program for Procurement of Commercial Grade Items | |
IR 05000277/1988020 | 12 July 1988 | Insp Repts 50-277/88-20 & 50-278/88-20 on 880613-17.No Violations Noted.Major Areas Inspected:Nonradiological Chemistry Program in Measurement Control & Analytical Procedure Evaluations | |
IR 05000277/1988022 | 7 July 1988 | Insp Repts 50-277/88-22 & 50-278/88-22 on 880623.No Violations Noted.Major Areas Inspected:Emergency Preparedness Annual Emergency Drill & Followup of Corrective Actions on Previously Identified Issues | |
IR 05000277/1988013 | 8 June 1988 | Insp Repts 50-277/88-13 & 50-278/88-13 on 880423-0603.Four Violations Noted by Licensee.Major Areas Inspected: Operational Safety,Radiation Protection,Physical Security, Refueling Activities,Maint,Outstanding Items & Events | Fitness for Duty High Radiation Area Fire Barrier Hydrostatic Scram Discharge Volume Fire Protection Program Scaffolding Inattentive |
IR 05000277/1987035 | 1 June 1988 | Insp Repts 50-277/87-35 & 50-277/87-35 on 871113-880114.No Violations Noted.Major Areas Inspected:Overall Crew Interaction,Knowledge & Use of Plant Procedures,Knowledge & Use of Tech Specs & Crew Communication | |
IR 05000277/1988011 | 18 May 1988 | Insp Repts 50-277/88-11 & 50-278/88-11 on 880411-15.No Violations Noted.Major Areas Inspected:Status of Previously Identified Items,Air Sampling Program,Alara,Worker Allegation & Pipe Replacement Project Changes | |
IR 05000277/1988012 | 11 May 1988 | Safety Insp Repts 50-277/88-12 & 50-278/88-12 on 880419-20. No Violations Noted.Deficiencies Found in Emergency Action Level Scheme & Personnel Response.Major Areas Inspected: Emergency Preparedness Training Program | Earthquake |
ML20153B883 | 28 April 1988 | Insp Repts 50-277/88-04 & 50-278/88-04 on 880201-11.No Violations Noted.Major Areas Inspected:Review of Licensee Action in Response to USI A-7, Mark I Containment Program | |
IR 05000277/1988008 | 21 April 1988 | Insp Repts 50-277/88-08 & 50-278/88-08 on 880314-18. Violations Noted.Major Areas Inspected:Replacement of Recirculation Sys Piping on Unit 3 & Detection of IGSCC in Shroud Support Access Cover Plates of Unit 3 | Nondestructive Examination Liquid penetrant |