ML20153B883
| ML20153B883 | |
| Person / Time | |
|---|---|
| Site: | Peach Bottom |
| Issue date: | 04/28/1988 |
| From: | Chaudhary S, Kaplan H, Strosnider J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML20153B872 | List: |
| References | |
| REF-GTECI-A-07, REF-GTECI-CO, TASK-A-07, TASK-A-7, TASK-OR 50-277-88-04, 50-277-88-4, 50-278-88-04, 50-278-88-4, NUDOCS 8805060103 | |
| Download: ML20153B883 (11) | |
See also: IR 05000277/1988004
Text
.
..
-
-
.
__. .
._
,
- '
s
,.
-
.
!
r
U.S. NUCLEAR REGULATORY COMMISSION
!
REGION I
50-277/88-04
,
Report No.
50-278/88-04
[
r
50-277
!
Docket No.
50-278
.
?
License No. OPR-56
Category C
Li::ensee:
Philadelphia Electric Company
j
2301 Market Street
'
Philadelphia, Pennsylvania 19101
j
t
Facility Name:
Peach Bottom Atomic Station, Units 2 and 3
,
,
1
i
j
Inspection At: Delta and Philadelphia, Pennsylvania
l
Inspection Conducted:
February 1-11, 1988
i
Yh88
!
Inspectors:
- v
1
- (/S/ K. Chiudhary, Senior Reactor Engineer
date
-
/MPS; EB; DRS
!
d
a
}
LWTan,SeniorReactorEngineer,MPS;
aff a,p {Q
L0m
H. Kap
date
(
j
1/28//6 _
Approved by:
_/ R. Strosnider, Chief
date
[
h
gNaterialandProcessesSection,EB,DRS
i
,
?
Inspection Summary:
Inspection on February 1-11, 1988 (Combined Inspection
l
Reports Nos. 50-277/88-04, and 50-278/88-04)
Areas Inspected: A special announced inspection by two region-based inspectors
l
4
?
was conducted at the Philadelphia Electric Company's engineering offices in
!
Philadelphia, Pennsylvania and at Peach Bottom Atomic Station, Delta,
l
The inspection covered review of licensee action in response to
!
4
Unresolved Safety Issue (USI A-7), Mark I Containment Program. The inspection
'
included review and examination of design analyses and calculations; design and
l
.
construction / erection drawings and schedule; modification to the torus,
t
!
torus-attached piping; temperature monitoring system instrumentation; and Plant
!
Unique Analysis Report. A visual examination of installed items verified the
!
"as-built" condition of modifications,
l
,
Results: The licensee's actions in response to Mark I Containment Program met
1
the requirements of NUREG-0661 and licensee commitments in PUAR.
No violations
i
l
or durations were identified.
!
I
t
j
]
8805060103 G80502
'
ADOCK 05000277
l
0
00D
f
-
- -
-
- .
.
-
-
?
. _ _ - _ _ - _ _ _ - .
,
'
.,
.
,
.
4
f
a
l
DETAILS
!
l
J
,
1.0 Persons Contacted
'
Philadelphia Electric Company-
- W. T. Baxter, Supervisor, Nuclear Quality Assurance
- W. C. Birely, Senior Licensing Engineer
- C, B. Boyce, Licensing Engineer
i
- A. R. Diederich, Manager, PECO-Nuclear
John Franz, Station Manager
- D. M. O'Rourke, Branch Head, Civil / Structural Engineering
i
- H. W. Vollmer, Manager, Civil-Architecture
U.S. - Nuclear Regulatory Commission
!
T. Johnson, Senior Resident Inspector
R. Urban, Resident Inspector
,
L. Meyers, Resident Inspector
i
!
In addition, the ir.spectors contacted other engineers, techniciar.s, health
physicist and chemists, and quality assurance personnel as their work
i
4
interfaced with the scope of this inspection.
Personnel marked with (*)
i
i
attended the exit meeting at the conclusion of the inspection.
1
i
2.0 Inspection Purpose and Scope
l
-
i
,
'
j
The purpose of the inspection was to determine if the licensee had
i
modified the Peach Bottom Atomic Power Plant, Unit 2 & 3 containments
!
consistent with commitments to NRC concerning Unresolved Safety Issue
f
(USI) A-7, and that these modifications had been performed using
t
,
appropriate procedures and with an acceptable level of quality.
The scope
l
'
of this inspection was defined by the instructions contained in the NRC
j
Temporary Instruction (TI) 2515/85.
j
Technical issues in USI A-7 involved suppression pool hydrodynamic loads
on the Mark I containment.
These hydrodynamic loads were not considered
!
a
in the original design of these containments.
The newly identified loads
i
.
'
affected the torus shell, torus support structures, internal structures,
'
and piping attached to torus (torus attached piping, TAP).
The issue was
addressed through a two phased approach consisting of short term and long
term programs.
Licensees with plants having Mark I containments were
i
required to submit a plant-unique analysis report (PUAR) to provide a
basis for the plant specific modifications.
For Peach Bottom the NRC
+
'
staff reviewed the PVAR against acceptance criteria contained in
l
NUREG-0661. The staff issued safety evaluation reports (SERs) for the
i
l
Peach Bottom plants in March 1984.
i
'
!
!
,
,
>
.
-
.,
.
3
As part of the STP, the licensee performed two (2) modifications in each
unit:
1.
Installation of torus support saddles at 16 support locations in
each unit, and,
2.
Installation of supports on the four (4) longest safety relief
valve (SRV) discharge lines in each unit.
As part of the LTP, the licensee scheduled the following modifications
in each unit.
The schedule covered the period from September 1979 to
December 1981. Modifications were:
1.
Vacuum breakers and new supports on SRV Lines in the drywells:
(Mod. 536)
2.
Rerouted, resupported SRV piping in the torus, and installed
quenchers; (Mod. 537)
3.
Installed Downcomer Ties; (Mod. 539)
4.
Installed Vent Header Deflectors; (Mod. 538)
5.
Torus temperature monitoring systems; (Mod. 603)
6.
Installed elbows on RHR lines; (Mod. 605)
7.
Performed MSRV discharge test in Unit-2 only; (Mod. 611)
8,
Modified torus internal structures; (Mod. 649)
9.
Installed torus nozzle stiffners; (Mod. 650)
10.
Installed torus tiedowns; (Mod. 651)
11.
Installed torus shell stiffners; (Mod. 653)
The modifications were implemented on the following schedule:
Modifications
Outage
Unit 2
Unit 1
1980
536
537
538
539
603
605
611
1981
536 & 605
537 & 649
538 & 650
539 & 651
603 & 653
1982
649
650
651
653
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
. ' .
-
.
4
3.0 Review Criter:a
Temporary Instruction (TI) 2515/85 was primarily used to define inspection
requirements.
The NRC staff SERs, licensea's PUAR, and applicable
sections of the Code of Federal Regulations also were used to define
additional inspection requirecents and licensee commitment.
4.0 Documentation Reviewed
Prior to the inspection, the inspectors reviewed the docket files
(50-277/50-278) for pertinent te'chnical information and related licensing
correspondence. The PVAR was revi(wed to identify the licensee
commitments. The inspectors also reviewed NRC staff SERs, previous
inspection reports, NUREG-0408, and NUREG-0661. The above docket search
identified information addressing the methodology, acceptance criteria,
procedures, specifications, schedules and other programmatic details
related to the licensee's response to this issue.
During the inspection at the licensee's engineering / corporate of fices and
at the plant site, the inspectors reviewed modification design calculations,
design and installation / fabrication drawings, engineering specifications,
installation / erection procedures, quality assurance and quality control
records, and additional correspondence.
The inspectors also reviewed the
photographic record of the progress of modifications maintained by the
licensee as a control record.
Based on the above review, the inspectors determined that design
calculations were sufficiently detailed and contained references and
technical assumptions / bases to permit review. Appropriate requirements
from applicable codes and standards were incorporated. There was evidence
of independent checks and design reviews, and design input controls.
The
design drawings were properly checked, reviewed, and approved for
'
constraction; and the drawing had adequate details for proper installation /
erection.
The engineering specification adequately described the technical and
quality assurance requirements for procurement of material and sources,
construction / installation, and inspection / verification with acceptance /
rejection criteria.
The documents reviewed to determine the above findings
are listed in attachment 1 to this report.
No violation or deviation was
identified.
.
-
-
-
- -
- -
_ _ _ _ __ - . _ _ _ _ _ _ _ _ _ _
___ _
_
_ _ _ _ _
_ _ _ _ - _
_ _ _ _
. - _ _ _ _ _ _ - _ _ _ _ _ _ - _ _ _ _ .
'
.
-
.
.
.
5
,
5.0 Erection / Installation Procedures and Practices
The inspector reviewed portions of documents on microfilm that were
!
generated by Chicago Bridge and Iron (CB&I), the subcontractor for the
-
"
Unit 2 & 3 containment suppression chamber (Torus) modifications .
The
microfilm reels reviewed were identified as 1-83-0255 and 1-83-0258, for
Unit 2 and 1-83-0209 and 1-83-0210 for Unit 3.
The microfilm reels
'
contained engineering specifications, welding procedures, NDE procedures,
inspection records, certified material test reports and engineering
calculations.
The quality of the film was acceptable and retained records
were comprehensive in scope and readily retrievable.
The Unit 2 work was
performed under CB&I contract 94410; the Unit 3 work under CB&I contract
99412.
Installation of the new quencher assembly was performed in
accordance with the applicable portions of the ASME Code,Section III and
j
XI (1977 edition & Summer 1978 Addenda) as specified by Code Case N-236.
!
,
Classification of assemblies included subsection NF-Class 3 component
'
'
supports, subsection ND-class 3 piping, and subsection NE-Class MC.
The
)
CBI documents consisted of certified material test reports, visual,
radiographic and magnetic particle test reports, welding procedure
specifications, and welding procedure and welder qualification records.
.
Also included were shop release reports, job site receiving and inspection
check lists, material heat number (traceability) sheets, nonconformance
,
!
reports, master check (traveller) lists covering operations inspections
,
t
and eu minations, welding and coating records and repair check lists.
The
r
principal materials employed in the modification were SA 516 Grade 70
4
steel plate, SA 36, structural steel plate and shapes, and SFA 5.1-E7018
weld filler metal.
The inspector verified that the material certifications for these materials
conformed to the applicable SA and SFA mate * 'al specifications including
satisfactory impact test results obtained at temperatures between -15*F
'
i
and -50*F.
The minimum specifieJ test temperatures were -10*F for
component supports and 0 F for materials welded to the existing containment
'
vessels. The principal welding procedure employed was WPS-W1-7018-1,
4
using the manual metal are process with E7018 filler metal. The inspector
verified that WPS-W1-7018-1 was qualified in accordance with ASME IX and
!
III requirements.
Documentation included ample evidence of welder
'
qualification and NDE personnel qualification records along with detailed
visual and magnetic particle test reports of structural welds required for
modification.
Radiographic reports were also available for the safety
,
relief valve piping butt welds.
The inspector reviewed both shop and
'
field weld history records that included part identifications, weld
,
procedure specifications, weld fit up inspections, and welder identifications.
1
The inspector noted the absence of preheat entries.
Preheat was required
l
.
l
for thicknesses greater than 1" since welding was performed without stress
'
l
relief.
The licensee '.mmediately contacted CB&I who stated that preheat
,
was employed when required and that the QA sign off indicated that it had
!
,
been performed.
l
I
'
!
'
,
i
---n__,,,
..v
.
_ _
_
. _
_
_ - _ .
_
_
_ _ _ _
_ _ _ .
._
l
.,
'
-
.
,
.
6
I
P
It should be noted that unlike the initial modification in 1978 all
welding by CB&I was performed when the torus in both units was dry.
In
l
1978, with the torus partially filled with water, CB&I utlizied specially
devloped welding procedures featuring preheat and electrode control to
minimize moisture. No rejectable magnetic particle indications were
i
.
reported after welding.
[
1
The inspector reviewed non-conformance reports and found no significant
deficiencies or problems
The vast majority of the reports addressed
,
dimensional problems and were satisfactorily dispositioned.
4
>
l
The inspector reviewed the licensee's audit reports OP-176, OP-133, OP-150
and CP-84 covering Bechtel and CB&I activities.
-
-
The audits were found to cover a wide spectrum of activities including
i
!
purchasing, design control and QA and welding.
The inspector verified
through review of OP-84 that all fifteen findings from these audits were
,
j
resolved satisfactorily.
In summary the inspector concluded that the modifications in the Unit 2
and 3 containment suppression chambers had been accomplished under an
!
,
acceptable QA program.
!
6.0, Physical Verification and Visual Examination
.
The inspector visually examined a sample of modifications made in response
-
!..
to USI A-7.
The physical inspection and examination were performed to
verify that the "as-built" modifications matched those shown on plant
i
design drawings and in design documents.
Examples of the items visually
i
examined included saddle support, column tie downs, torus attached piping
'
i
nozzle reinforcements, and reinforcements to pump supports in core spray
i
line.
These items were inspected for general location and geometry,
i
!
member ditnensions, boundary conditions, and general quality of workmanship
l
and corrosion protection. The items examined are listed in Table 1.0 in
i
-
,
the attachment 1 to this report.
!
'
7.0 Review of Licensee Administrative Controls, Quality Assurance,
and Quality Control
'
J
!
The inspectors reviewed documentation, and held discussions with cognizant
,
j
licensee engineers and management personnel to evaluate the licensee's
QA/QC efforts and administrative controls.
The pertinent documents that
,
i
were examined are listed in Paragraph 9.0 of this report.
These documents
I
are maintained by the licensee on microfilm in the plants record
management / control system.
Records reviewed in this effort provided a
sample of the licensee's QA/QC effort,
The licensee's efforts were
i
directed toward assuring the effective implementation of designers and
contractor's quality assurance program.
These records provided evidence
of licensee's efforts in surveillances and audit of contractor's program
i
and workmanship. The audits were performed annually and were
I
comprehensive in scope.
The quality of the contractor's work was evident
i
!
!
_ _ _ _ _ _ _ _
'
.
7
by the lack of any technical and/or QA adverse finding.
The audit team
included at least one technical specialist / Engineer in the audited area.
The inspector reviewed three audits covering the areas of Welding /NDE, QC
inspection coverage, and procedural compliance of the contractor.
There
were some minor findings which were resolved in timely manner with adequate
dispositions.
The audits reviewed are listed in attachment 1.
The engineering services were provided by the licensee's approved
Architect / Engineer Bechtel Power Corporation, and erection / construction
services were provided by Chicago Bridge & Iron Company (CBI).
Both of
these contractorswere on the licensee's approved vendor list for their
services, and were audited by the licensee's QA department for their
effective implementation of the QA/QC program.
The inspectors verified
that the procurement documents issued by the licensee and/or the A/E
contained detailed requirements for QA/QC and applicable codes and
standards for the purchased materials and services.
8.0 Suppression Pool Temperature Monitoring System Modification
The inspector reviewed the modifications to the suppression pool
temperature monitoring system, including the technical specifications to
confirm the following:
The placement and number of temperature monitoring devices were in
accordance with the PUAR commitments.
Suppression pool temperatures were indicated in the control room.
Instrumentation alarm set points had been established consistent with
TS pool temperature limits.
Control room instrumentation was adequate to assure that requirements
could be met.
The inspector also reviewed drawing No. 6280-E-2394-3, Rev. 3, and
engineering specifications to determine the technical basis of design, and
adequacy of modification / installation.
Based on the above review and visual examination of completed work, the
inspector determined the following:
The controlled drawings indicated that two independent channels of
temperature indicators have been placed at their ten locations in the
suppression pool.
The suppression pool temperature is indicated and recorded in control
room by digital indicators and strip chart recorders.
The low alarm set point was 95 F for the vital-bus powered
instrumentation; the high alarm set point was 120 F.
.
.
.
.
8
The above instrumentation and temperature set points were consistent
with PUAR commitments, and TS requirements.
The inspector determined that the design and installation of the
temperature monitoring system in the suppression pool met the licensee
commitments and the requirements of NUREG.0661.
No deviation or violation was identified.
9.0 Exit Interview
An exit meeting was conducted on February 11, 1988, at the corporate
engineering officers by the inspector.
Attendees at the meeting are
listed in paragraph 1 of this report.
The inspector summarized the
purpose, scope and findings of the inspection.
No written material was
provided to the licensee during this inspection. The licensee
representatives did not indicate that this inspection involved any
proprietary information.
. -
-
-
. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
'
.
,
4
ATTACHMENT 1
TABLE 1.0
ITEMS FIELD VERIFIED
COMP 0NENT
LOCATION
COMMENTS
Torus Support Saddles
Torus Room
Verified Dwgs. 300, and
(except # 8, 9 and 10)
350 Revisions 3 and
Ring Girders
Torus Room
Orawing 300. Rev. 3
- 3, 6 and 14
Shell Stiffners
Torus Room
Orawing 300. Rev. 3
(except #8, 9 and 10)
Torus Attached Pipes
Torus Room
Drawing 8 Rev. 3
(Penetration Stiffners)
- N 205A, E-B; N-209; N-210:
N 211A; N-214
N 226C&D; N-228A&B;
ORAWINGS/ DOCUMENTS REVIEWED
Design (Bechtel).
11187-015
S-816 -
Vent Header Deflectors and Supports and Downcomer Ties; Plans and
Sections, Rev. 4
S-817 -
Vent Header Deflectors - Sections and Details, Rev. 3
S-818 -
SRV Quencher Supports - Plans, Rev. 3
,
S-819 -
SRV Quencher Supports - Plans, Sections, and Details, Rev 6
S-820 -
MSRV Discharge Line - Quencher and Ram's Head Details, Rev. 3
S-821 -
RHR G scharge Elbow Modification and Support Details, Rev. 4
S-822 -
Telescoping Struts for the SE/ Discharge Line in the Torus, Rev. 3
S-823 -
SRV Line Piping Modification in the Torus, Rev. 6
S-826 -
Vent System Modification - Plans, Sections and Details, Rev. 3
S-827 -
Monorail & Spray Header - Plans and Sections, Rev. 4
S-828 -
Torus Stiffeners - Plan, Sections and Details, Rev. 2
S-829 -
External Torus Nozzel Reinforcement (6" and above) Plan and
Sections, Rev. 3
S-830 -
External Torus Nozzel Reinforcement, Rev. 3
-
-
-
_ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ __ __ _ _- _ . ____ _ _ ___ ___ - ____-_ - __ - _ - _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ - _ _ _ _ _ _ - _ _
b
. , -
,
.,.
L
ATTACHMENT 1
-2
!
DRAWINGS
!
S-831
Torus Internal Piping Supports - Plans Sections, and Details,
-
.
Rev. 3.
j
i
S-832
Torus Tiedowns - Plan and Typical details for Columns, Rev. 4.
-
.
S-833
Torus Tiedowns - Sections and Miscellaneous Details, Rev. 4.
-
HPCI and RCIC Turbine Exhaust Support Plans, Sections and
h
'
S-834
-
Details, Rev. 4.
.
S-835
Vent System Modification - Plans,. Sections & Details, Rev. 3.
-
S-836
Torus Tiedowns - Plans, Sections and Details, Rev. 4.
-
External Torus Nozzel Reinforcement (6" and above) Plans and
!
S-837
-
Sections, Rev. 3.
5-838
External Torus Nozzel Reinforcement (6" and above Details),
-
Rev. 2.
S-839
Torus Tridowns.- Plan and Typical Details for Columns, Rev. 6.
-
,
3
Torus Tridowns - Sections and Miscellaneous Details, Rev. 4.
5-840
-
,
!
r
CALCULATIONS REVIEWE0
i
PBM-007
PBAPS - CSC Modification - Analysis & Design of Deflectors,
'
-
Rev. 2
.
t
PBM-008-PBAPS - CSC Modification - Downcomer Ties, Rev.2-
l
!
PBM-005
3-PBAPS-CSC Modifications - SRV Quecher Support, Rev. 2
I
f
PBAPS - Containment. STRUTS for SRV Lines 1n Torus, Rev. 2
PBM-010
-
P
PBAPS - SRV pipe supports, Rev. 1
[
PBM-001
-
!
t
PBM-026
PBAPS - CSC - Modifications - External Torus Nozzels
f
-
Reinforcements, Rev. 0
<
OTHER DOCUMENTS
Mark I Containment Short Term Program Safety Evaluation Report.
!
Safety Evaluation Report - Mark I Containment Long-Term Program.
i
A Technical Update on Pressure suppression Type Containments
!
in use in US, Light Water Reactor Nuclear Power Plant.
[
l
'
l
1
!
.'
,
.
ATTACHMENT 1
3
6280-E-120-2
Vsers; Manual, Suppression Pool Temp. Monitoring System
(SPOTMOS)
Spec for Installation Containment Suppression Chamber CSC Modification for
PB Atomic Power Station Specification Number 11187-P-3Q Rev. 7.
Spec for Purchase of Components for Containment Suppression Chamber
Modification for Beach Bottom Atomic Power Station spec. 1187-P-1Q Rev. 7
Design Specific for Containment Suppression Chamber Modification for
PB-2&3 Spec 1187-P-2Q Rev. 3.
General Project Requirement for Purchase Order for PB 2&3 attachment C to
MR 11187-P-1Q Rev. A Spec. 11187-G1, Rev. A.
General Project Requirement for Supplier QA for P.B. - 2&3 attachment D to
MR11187-P-1Q specific 1187-G-13 Rev. O.
I