Issue date | Title | Topic | |
---|---|---|---|
ML20206P150 | 5 January 1999 | LER 98-S03-00:on 981207,security Officer Discovered Uncontrolled Safeguards Info Drawing.Caused by Failure to Follow Established Procedures & Policies.Drawing Was Controlled by Site Security.With | Time of Discovery |
ML20216F993 | 31 December 1998 | Piedmont Municipal Power Agency 1998 Annual Rept | |
ML20198E638 | 17 December 1998 | LER 98-S02-00:on 981130,security Access Was Revoked Due to Falsification of Criminal Record.Individual Was Escorted from Protected Area & Unescorted Access Was Restricted. with | |
ML20153G460 | 30 September 1998 | USI A-46 Seismic Evaluation Rept, Vols 1-2 | Safe Shutdown High Radiation Area Safe Shutdown Earthquake Probabilistic Risk Assessment Emergency Lighting Design basis earthquake Earthquake Scaffolding |
ML17354B097 | 9 September 1998 | Part 21 Rept Re Possible Machining Defect in Certain One Inch Stainless Steel Swagelok Front Ferrules,Part Number SS-1613-1.Caused by Tubing Slipping Out of Fitting at Three Times Working Pressure of Tubing.Notified Affected Utils | |
ML15261A468 | 4 September 1998 | Safety Evaluation Supporting Amends 232,232 & 231 to Licenses DPR-38,DPR-47 & DPR-55,respectively | Safe Shutdown Probabilistic Risk Assessment Maintenance Rule Program |
ML20248F744 | 31 May 1998 | Reactor Vessel Working Group,Response to RAI Regarding Reactor Pressure Vessel Integrity | |
ML20247L904 | 31 December 1997 | 1997 Annual Rept for Duke Energy Corporation & Saluda River Electric Cooperative,Inc,Financial Statements as of Dec 1997 & 1996 Together W/Auditors Rept | |
ML20198J765 | 15 October 1997 | Safety Evaluation Accepting 10-yr Interval Insp Program Plan Alternatives for Listed Plants Units | VT-2 Incorporated by reference |
ML20148S314 | 30 June 1997 | Ro:On 970422,Oconee Unit 2 Was Shut Down Due to Leak in Rcs. Leak Was Caused by Crack in Pipe to safe-end Weld Connection at RCS Nozzle for HPI Sys A1 Injection Line.Unit 1 Was Shut Down to Inspect Hpis Injection Lines & Implement Ldst Mods | |
ML20148H250 | 5 June 1997 | Safety Evaluation Accepting Proposed Restructuring of Util Through Acquisition Of,& Merger W/Panenergy Corp | |
ML20210E359 | 27 March 1997 | Part 21 Rept Re Sorrento Electronics Inc Has Determined Operation & Maint Manual May Not Adequately Define Requirements for Performing Periodic Surveillance of SR Applications.Caused by Hardware Failures.Revised RM-23A | |
ML20134N712 | 20 February 1997 | Safety Evaluation Accepting Relief Request 96-04 for Plant | Hydrostatic |
ML20138L215 | 31 January 1997 | Monthly Operating Repts for Jan 1997 for Oconee Nuclear Station,Units 1,2 & 3 | |
ML20138L228 | 31 December 1996 | Revised Monthly Operating Repts for Dec 1996 for Oconee Nuclear Station,Units 1,2 & 3 | |
ML20133C123 | 23 December 1996 | Informs Commission of Staff Review of Request for License Amends from DPC to Perform Emergency Power Engineered Safeguards Functional Test on Three Oconee Nuclear Units | Shutdown Margin Time to boil |
ML20115F247 | 3 July 1996 | Part 21 Rept Re Piping (Small Portion of Unmelted Matl Drawn Lengthwise Into Bar During Drawing Process) Defect That Existed in Bar as Received from Mill.Addl Insp Procedure for Raw Matl Instituted | |
ML17353A434 | 31 October 1995 | Rev 1 to BAW-2245, Initial Rt of Linde 80 Welds Based on Fracture Toughness in Transition Range. | |
ML20107M893 | 31 October 1995 | Nonproprietary DPC Fuel Reconstitution Analysis Methodology | Anticipated operational occurrence Safe Shutdown Earthquake Earthquake Fuel cladding Affidavit Depleted uranium |
ML17264A118 | 31 July 1995 | Response to Part (1) of GL 92-01,Rev 1,Suppl 1. | |
ML20086M085 | 29 June 1995 | DPC TR QA Program | Fitness for Duty Non-Destructive Examination Coatings Nondestructive Examination License Renewal Commercial Grade |
ML20077R363 | 31 December 1994 | Monthly Operating Repts for Dec 1994 for Bfnpp | |
ML20236L597 | 29 December 1994 | SER in Response to 940314 TIA 94-012 Requesting NRR Staff to Determine Specific Mod to Keowee Emergency Power Supply Logic Must Be Reviewed by Staff Prior to Implementation of Mod | Backfit |
ML20064L200 | 31 January 1994 | Final Rept EPRI TR-103591, Burnup Verification Measurements on Spent-Fuel Assemblies at Oconee Nuclear Station | |
ML20062K748 | 1 December 1993 | ISI Rept for Unit 2 McGuire 1993 Refueling Outage 8 | |
ML20056E517 | 31 August 1993 | Technical Review Rept, Tardy Licensee Actions | |
ML20046C129 | 2 August 1993 | LER 93-007-00:on 930701,determined That Unit 1 Ssf Rc Makeup Sys Inoperable in Past Due to Design Deficiency.Operations Procedures Revised to Reflect Newly Calculated Operating Limits for Rc Makeup Pump,Rcps & RCS.W/930802 Ltr | |
ML20056G013 | 27 July 1993 | Rev 0 to ISI Rept Unit 2 Oconee 1993 Refueling Outage 13 | |
ML20044G531 | 26 May 1993 | Suppl to 921207 Part 21 Rept Re Declutch Sys Anomaly in Certain Types of Valve Actuators Supplied by Limitorque Corp.Limitorque Designed New Declutch Lever Which Will Be Available in First Quarter 1993 | Stroke time |
ML20126J596 | 31 December 1992 | Part 21 Rept Re Potential Loss of RHR Cooling During Nozzle Dam Removal.Nozzle Dams May Create Trapped Air Column Behind Cold Leg Nozzle Dam.Mod to Nozzle Dams Currently Underway. Ltrs to Affected Utils Encl | Hydrostatic |
ML20117A598 | 23 November 1992 | Special Rept:On 921119,ability of Control Battery Racks to Withstand Seismic Event Could Not Be Confirmed & Batteries Declared Inoperable.Batteries Expected to Be Restored in TS Required Time | |
ML20097G042 | 31 May 1992 | Analysis of Capsule OCIII-D Duke Power Company Oconee Nuclear Station Unit-3 | Anticipated operational occurrence Hydrostatic Fuel cladding |
ML20077D067 | 15 November 1991 | Nonproprietary Version of Rev 0 to Boric Acid Corrosion of Oconee Unit 1 Upper Tubesheet | Boric Acid |
ML20067A524 | 31 December 1990 | Final Submittal in Response to NRC Bulletin 88-011, 'Pressurizer Surge Line Thermal Stratification.' | Operating Basis Earthquake Finite Element Analysis Code Reconciliation Commercial Grade Power change |
ML20042F354 | 30 April 1990 | Special Rept Re Failure to Prevent Performance Degradation of Reactor Bldg Cooling Units.Caused by Mgt Deficiency & Inadequate Program.Cooling Unit Declared Inoperable & Removed from Svc for Cleaning & Placed Back in Operation | Temporary Modification Operability Determination |
ML17348A162 | 27 March 1990 | Part 21 Rept Re Matls W/Programmatic Defects Supplied by Dubose Steel,Inc.Customers,Purchase Order,Items & Affected Heat Numbers Listed | |
ML18094B321 | 28 February 1990 | Annual Operating Repts for 1989 for Salem & Hope Creek Generating Stations | |
ML20012A901 | 27 February 1990 | Suppls 900213 10CFR21 Rept Re Chilled Water Sys Operation. Evaluation of Crystal River Determined That Postulated High Energy Line Break in Intermediate Bldg May Be Subj to Steam Loads Higher than Normal Loads,Causing Rising Water Temp | |
ML20011F194 | 22 February 1990 | Part 21 Rept Re Abb 27/59 Relay Catalog Series 211L.Solder Connections to Printed Wiring Runs on Bottom of Circuit Board Deteriorated Due to Thermal Stress.No Actual Failure Occurred & Relays to Be Changed at Next Outage | |
ML20011F597 | 22 February 1990 | Part 21 Rept Re Solder Connections in Abb 27/59 Relays Deteriorated Due to Thermal Stress,Causing Bonding of Printed Wiring Pattern to Glass Epoxy Circuit Board.Interim Circuit Board W/Larger Pads & Higher Wattage Will Be Used | |
ML18153C101 | 2 February 1990 | Part 21 Rept Re Two of Three Pc Cards in GE Type SLV11A1 Over/Undervoltage Relays Failing to Produce Output.Short Between Leads Would Result in Damage to Component 1C5. Sketch of Threshold Detection Board Encl | |
ML17223A745 | 26 January 1990 | Part 21 Rept Re Backup Rings Furnished in Spare Parts Seal Kits & in 25 Gpm 4 Way Valves as Part of Actuators Made of Incorrect Matl.Rings Should Be Viton & Have Been Identified as Buna N | |
ML20006A823 | 10 January 1990 | Errata to Rev 3 to BAW-1543, Master Integrated Reactor Vessel Surveillance Program Consisting of Revised Tables 3-20 & E-1 | |
ML20005G683 | 5 January 1990 | Part 21 Rept Re Installation Instructions for Grommet Use Range for Patel Conduit Seal P/N 841206.Conduit Seals in Environ Qualification Applications Inspected for Proper Wire Use Range & Grommets Replaced | |
ML17347B462 | 31 December 1989 | App a to USI A-46 & Generic Ltr 87-02. | Safe Shutdown Safe Shutdown Earthquake Probabilistic Risk Assessment Operating Basis Earthquake Earthquake Backfit |
ML19332D539 | 31 October 1989 | Core Thermal-Hydraulic Methodology Using VIPRE-01. | Power change Affidavit |
ML18094B147 | 25 October 1989 | Emergency Plan Annual Exercise 1989 for Artificial Island on 891025. W/One Oversize Drawing | |
ML19325E086 | 16 October 1989 | Followup Part 21 Rept Re Class 1E Battery Chargers W/ Transformers Running at Temps Exceeding Those Used in Qualification Rept When Operating at or Near Full Load Rating of Equipment.Listed Corrective Actions Underway | |
ML19351A294 | 9 October 1989 | Part 21 Rept Re Potential of Ambient Compensated Molded Case Circuit Breakers to Deviate from Published Info. Instantaneous Trip Check Will Be Instituted on All Class 1E Thermal/Magnetic Ambient Breakers Prior to Shipment | |
ML20248G829 | 2 October 1989 | Rev 19 to YOQAP-I-A, Operational QA Program | Boric Acid Probabilistic Risk Assessment Nondestructive Examination Condition Adverse to Quality Liquid penetrant Fire Protection Program |