Semantic search
Jump to navigation
Jump to search
Issue date | Title | Topic | |
---|---|---|---|
ML20196G673 | 1 July 1997 | Informs Commission That Decommissioning Process Has Been Completed at PSC of Colorado Fsvngs,Unit 1 Located in Town of Platteville in Weld County,Co | |
ML20141K996 | 5 May 1997 | Safety Evaluation Supporting Amend 89 to License DPR-34 | |
ML20140E112 | 10 April 1997 | Confirmatory Survey of Group Effluent Discharge Pathway Areas for Fsv Nuclear Station,Platteville,Co | |
ML20134D166 | 30 January 1997 | Rev 1,Vol 6 to Final Survey Rept,Final Survey of Group E (Book 2A of 2) | |
ML20137S611 | 31 December 1996 | Annual Rept Pursuant to Section 13 or 15(d) of Securities Exchange Act 1934, for Fy Ended Dec 1996 | Incorporated by reference |
ML20134G727 | 29 October 1996 | Rev 0,Volume 11,Book 1 of 1 to Final Survey of Group J | |
ML20134G686 | 29 October 1996 | Rev 0,Volume 8,Books 1 & 2 of 2 to, Final Survey of Group G | |
ML20134G640 | 29 October 1996 | Rev 0,Volume 6,Books 1 & 2 of 2 to Final Survey of Group E | |
ML20134G617 | 29 October 1996 | Rev 2,Volume 1,Books 1 & 2 of 2 to Final Survey Description & Results | |
ML20134G632 | 26 October 1996 | Rev 1,Volume 5,Books 2 & 3 of 3 to Final Survey of Group D | |
ML20133D783 | 22 October 1996 | Preliminary Rept - Orise Support of NRC License Insp at Fsv on 960930-1003 | |
ML20116A466 | 19 July 1996 | Fsv Final Survey Exposure Rate Measurements | |
ML20112J686 | 31 May 1996 | June 1996 Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments for Fsv Decommissioning.Rept Covers Period of 960216-0531 | |
ML20112C153 | 17 May 1996 | Fsv Final Survey Exposure Rate Measurements | |
ML20101G552 | 21 March 1996 | Confirmatory Survey Activities for Fsv Nuclear Station PSC Platteville,Co, Final Rept | |
ML20097E320 | 31 January 1996 | Nonproprietary Fort St Vrain Technical Basis Documents for Piping Survey Instrumentation | |
ML20095K413 | 26 December 1995 | Rev 3 to Decommissioning Plan | High Radiation Area Grab sample Offsite Dose Calculation Manual Tornado Missile Coatings Operating Basis Earthquake Locked High Radiation Area Decommissioning Funding Plan Design basis earthquake Process Control Program Exemption Request Earthquake Scaffolding Exclusive Use |
ML20095H721 | 20 December 1995 | Revs to Fort St Vrain Decommissioning Fire Protection Plan Update | Offsite Dose Calculation Manual Fire Barrier Coatings Emergency Lighting Fire Protection Program Fire Watch |
ML20095K975 | 15 December 1995 | Fort St Vrain Project Update Presentation to NRC, on 951207 & 15 | |
ML20096C167 | 13 December 1995 | Rev 4 to Decommissioning Fire Protection Plan | Offsite Dose Calculation Manual Fire Barrier Coatings Emergency Lighting Fire Watch |
ML20094M165 | 30 November 1995 | Nonproprietary Fsv Technical Basis Documents for Piping Survey Implementation | |
ML20092F346 | 14 September 1995 | Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments for Fsv Decommissioning, Covering Period of 950516-0815.W/ | Offsite Dose Calculation Manual |
ML20137S233 | 31 December 1994 | Rept of Independent Counsel Investigation Concerning Issues at Fort St Vrain Nuclear Generating Station Decommissioning Project, Dec 1994 | Unanalyzed Condition Scaffolding |
ML20137H353 | 31 December 1994 | Partially Withheld, Rept of Independent Counsel Investigation Concerning Issues at Fort St Vrain Nuclear Generating Station Decommissioning Project, App D,Comments by Mkf & Westinghouse Team & Responses | |
ML20029C603 | 31 December 1993 | 1993 Annual Rept Public Svc Co of Colorado. W/940405 Ltr | |
ML20058Q379 | 21 December 1993 | Rev 1 to Decommissioning Plan for Fort St Vrain Nuclear Generating Station | Anticipated operational occurrence Tornado Missile Nondestructive Examination FLEX Decommissioning Funding Plan Design basis earthquake Process Control Program Earthquake |
ML20045B364 | 30 June 1993 | June 1993 Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments for Fsv Decommissioning. | |
ML20045A429 | 3 June 1993 | LER 93-003-00:on 930505,new Source of Natural Gas Introduced within 0.5 Miles of ISFSI & Reactor Bldg W/O Prior NRC Approval.Caused by Field Routing of Natural Gas Pipe.Well Isolated by Well operator.W/930603 Ltr | |
ML20077D163 | 10 May 1993 | Enforcement Conference, in Arlington,Tx | Fitness for Duty Stolen |
ML20125C716 | 7 December 1992 | Part 21 Rept Re Possibility for Malfunction of Declutching Mechanisms in SMB/SB-000 & SMB/SB/SBD-00 Actuators. Malfunction Only Occurs During Seismic Event.Balanced Levers May Be Purchased from Vendor.List of Affected Utils Encl | Stroke time Anchor Darling |
ML20128D719 | 1 December 1992 | Safety Evaluation Approving Exemption from Requirement of 10CFR50.54(q) to Change to Biennial Emergency Plan Exercise Rather than Annual Following Completion of Next Scheduled Exercise at Plant | |
ML20127P586 | 23 November 1992 | Followup to 921005 Part 21 Rept Re Potential Defect in SB/SBD-1 Housing Cover Screws.Procedure Re Replacement of SBD-1 Spring Cover Bolts Encl.All Fasteners Should Be Loosened & Removed.List of Affected Utils Encl | |
ML20127F569 | 3 November 1992 | Informs Commission of Intent to Issue Order Approving Plant Decommissioning Plan & Corresponding Amend to License DPR-34 | High Radiation Area Offsite Dose Calculation Manual Process Control Program |
ML20101E576 | 31 May 1992 | Monthly Defueling Operations Rept for May 1992 for Fort St Vrain | |
ML20096E822 | 30 April 1992 | Monthly Operating Rept for Apr 1992 for Fort St Vrain.W/ | |
ML20095E960 | 17 April 1992 | Rev to Fort St Vrain Proposed Decommissioning Plan | Offsite Dose Calculation Manual Anticipated operational occurrence Tornado Missile Coatings Nondestructive Examination Decommissioning Funding Plan Design basis earthquake Process Control Program Earthquake Chernobyl Fire Watch Scaffolding |
ML20100R743 | 31 March 1992 | Monthly Operating Rept for Mar 1992 for Fort St Vrain.W/ | |
ML20090L062 | 29 February 1992 | Monthly Operating Rept for Feb 1992 for Fort St Vrain Unit 1 | |
ML20092D008 | 31 January 1992 | Monthly Operating Rept for Jan 1992 for Fort St Vrain Nuclear Generating Station | |
ML20102B224 | 22 January 1992 | Fort St Vrain Station Annual Rept of Changes,Tests & Experiments Not Requiring Prior Commission Approval Per 10CFR50.59, for Period 910123-920122 | Safe Shutdown Fire Protection Program |
ML20094N670 | 31 December 1991 | Public Svc Co Annual Financial Rept for 1991 | |
ML20091J625 | 31 December 1991 | Monthly Operating Rept for Dec 1991 for Fort St Vrain.W/ | |
ML20094D671 | 30 November 1991 | Monthly Operating Rept for Nov 1991 for Fort St Vrain Unit 1 | |
ML20090M187 | 20 November 1991 | FOSAVEX-91 Scenario for 1991 Plant Exercise of Defueling Emergency Response Plan | |
ML20086D689 | 15 November 1991 | Proposed Decommissioning Plan for Fort St Vrain Nuclear Generating Station | Anticipated operational occurrence Nondestructive Examination Decommissioning Funding Plan Process Control Program Earthquake |
ML20085N145 | 5 November 1991 | Revised Ro:Operability Date of 910830 for Electric Motor Driven Fire Water Pump P-4501 Not Met.Pump Not Actually Declared Operable Until 911025.Caused by Unforseen Matl & Testing Problems.Equivalent Pump Available | Safe Shutdown |
ML20086C545 | 31 October 1991 | Monthly Operating Rept for Oct 1991 for Fort St Vrain.W/ | |
ML20085H661 | 10 October 1991 | Assessment of Mgt Modes for Graphite from Reactor Decommissioning | Hydrostatic |
ML20091D767 | 1 October 1991 | Rev B to Engineering Evaluation of Prestressed Concrete Reactor Vessel & Core Support Floor Structures for Proposed Sys 46 Temp Change | |
ML20085D986 | 30 September 1991 | Monthly Operating Rept for Sept 1991 for Fort St Vrain.W/ |