Semantic search
Jump to navigation
Jump to search
Issue date | Title | Topic | |
---|---|---|---|
ML20092C433 | 1 September 1995 | Startup Test Rept for Pilgrim Nuclear Power Station Cycle 11 | Shutdown Margin |
ML20078N842 | 18 November 1994 | Rev 32 to Procedure 8.7.3, Secondary Containment Leak Rate Test | |
ML20056E222 | 19 May 1993 | Final Pilgrim Nuclear Power Station Unit 1 Reactor Containment Bldg Integrated Leakage Rate Test Rept | |
ML20045H538 | 29 January 1993 | Procedure 8.7.3,Secondary Containment Leak Rate Test. | |
BECO-91-148, Reactor Containment Bldg Integrated Leakage Rate Test Rept | 5 August 1991 | Reactor Containment Bldg Integrated Leakage Rate Test Rept | Reactor Vessel Water Level Anchor Darling |
ML20076D489 | 22 July 1991 | Procedure 8.7.3, Secondary Containment Leak Rate Test, Containment Results of Leak Rate Tests Performed on 910505 & 0620 | |
ML20204H350 | 26 September 1988 | Restart Readiness Assessment Rept for Pilgrim Nuclear Power Station | Safe Shutdown High Radiation Area Half scram Offsite Dose Calculation Manual Fire Barrier Hydrostatic Temporary Modification Squib Locked High Radiation Area Condition Adverse to Quality Missed surveillance Process Control Program Systematic Assessment of Licensee Performance Safeguards Contingency Plan Exemption Request Pressure boundary leak Fire Protection Program Fire Watch Grace period |
BECO-88-049, Reactor Containment Bldg Integrated Leakage Rate Test Types A,B & C Periodic Test | 31 December 1987 | Reactor Containment Bldg Integrated Leakage Rate Test Types A,B & C Periodic Test | |
ML20209D472 | 23 April 1987 | Secondary Containment Leak Rate Test Rept | |
ML20236M111 | 4 March 1987 | Flooring Radiant Panel Test | |
ML20236M102 | 4 March 1987 | Flooring Radiant Panel Test | |
ML20236M100 | 4 March 1987 | Flooring Radiant Panel Test | |
ML20236M091 | 4 March 1987 | Smoke Density Test (Nbs) | |
ML20236M121 | 4 March 1987 | Flooring Radiant Panel Test | |
ML20236M128 | 4 March 1987 | Flooring Radiant Panel Test | |
ML20236M081 | 4 March 1987 | Smoke Density Test (Nbs) | |
ML20112F838 | 8 January 1985 | Rev 15 to Secondary Containment Leak Rate Signoff | |
ML20100F603 | 31 December 1984 | Reactor Containment Bldg Integrated Leakage Rate Test,Type A,B & C Periodic Test,Pilgrim Nuclear Power Station,Unit 1 | |
ML20107A186 | 30 September 1984 | Rev 1 to Statistical Analysis of Boundary Strengths for Masonry Walls from Field Test Data | |
ML20064B892 | 27 October 1982 | Mark I Containment Program:Plant-Unique Analysis Rept of Torus Suppression Chamber for Pilgrim Station - Unit 1 | Earthquake |
ML19331D134 | 18 August 1980 | Results of Startup Physics Testing Program Conducted for Cycle V Operation. | Shutdown Margin Overtravel |
ML19344B327 | 31 May 1980 | Primary Containment Integrated Leak Rate Test,Second Periodic Test & Local Leak Rate Tests Results,Jan-May,1980. | |
ML19312E001 | 30 April 1980 | Test of Cable Penetration Fire Stops for Pilgrim 1 Nuclear Power Generating Station, Final Rept for 790907 Testing | |
ML19320C989 | 23 April 1980 | Secondary Containment Leak Rate Test Data.Includes Test Conditions,Base Reading & Standby Gas Treatment Sys a & B Performance | |
ML19312D997 | 31 March 1980 | Test of Cable Penetration Fire Stops for Pilgrim 1 Nuclear Generating Station, Final Rept for 790829 Testing | Coatings |
ML19305D259 | 20 March 1980 | Secondary Containment Leak Rate Test Data. | |
ML20126B369 | 3 March 1980 | Secondary Containment Leak Rate Test Data | |
ML19312D995 | 31 January 1980 | Test of Cable Penetration Fire Stops for Pilgrim 1 Nuclear Power Generating Station, for 790531 Testing | Coatings |
ML20236Q882 | 5 November 1976 | Friction Coefficients of Water-Lubricated Stainless Steels for Spent Fuel Rack Facility |