ML20211C331 | 30 April 1999 | Rev 2.0 to Generic ODCM for Dresden,Quad Cities,Zion, Lasalle,Byron & Braidwood | Offsite Dose Calculation Manual Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report Process Control Program Deep Dose Equivalent |
ML20205A087 | 22 March 1999 | Revs to Odcm,Including Rev 2.0 to Chapter 10, Radioactive Effluent Treatment & Monitoring & Rev 1.9 to Chapter 12, Radiological Effluent Technical Stds (Rets) | Grab sample Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report Process Control Program Power change |
ML20199E036 | 12 January 1999 | Proposed Tech Specs Section 3.10, Fuel Handling & Storage, Eliminating Reference to Initiation of Generating Station EP Action That Is Incorrect & Not Part of Reason for Min FSP Water Level TS | |
ML20196F645 | 30 November 1998 | Proposed Tech Specs 3/4.1.A,3/4.10.B & 3/4.12.B,proposing Changes to Relocate Requirement to Remove RPS Shorting Links Which Enable non-coincident Scram for Neutron Instrumentation,To Licensee Controlled Document | Shutdown Margin Fuel cladding |
ML20237A865 | 7 August 1998 | Qualified Unit 1 Supervisor Initial & Continuing Training Program | Job Performance Measure |
ML20151S269 | 31 July 1998 | Rev 1.8 to Chapter 12 of Dresden Station Odcm | Grab sample Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report Power change |
ML20217N933 | 30 April 1998 | Rev 1.7 to Chapter 12 of Dresden Station Odcm | Grab sample Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report Power change |
ML20216H432 | 31 December 1997 | Revs to OCDM for Braidwood,Including Rev 1.8 to Chapter 10, Rev 1.9 to Chapter 11,rev 2 to Chapter 12 & Rev 2 to App F | Grab sample Offsite Dose Calculation Manual Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report Process Control Program Power change |
ML20216H855 | 31 December 1997 | Revs to OCDM for Dresden Station,Including Rev 1.9 to Chapter 10,rev 1.3 to Chapter 11,rev 1.6 to Chapter 12 & Rev 1.1 to App F | Grab sample Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report Process Control Program Power change |
ML20198M249 | 18 December 1997 | Revs to Ocdm,Including Rev 1.3 to Chapter 11, Radiologicial Environ Monitoring Program & Rev 1.6 to Chapter 12, Radiological Effluent Technical Stds (Rets) | Grab sample Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report Power change |
ML20216H824 | 31 October 1997 | Revs to OCDM for Byron Station,Including Rev 1.3 to Chapter 10,rev 1.5 to Chapters 11 & 12 & Rev 1.3 to App F | Grab sample Offsite Dose Calculation Manual Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report Process Control Program Deep Dose Equivalent Power change |
ML20216H904 | 31 October 1997 | Revs to OCDM for Zion Station,Including Rev 1.9 to Chapter 10,rev 1.1 to Chapter 11,rev 1.9 to Chapter 12 & Rev 1.1 to App F | |
ML20198P160 | 20 October 1997 | Rev 1.5 to Odcm,Chapter 12 | Grab sample Offsite Dose Calculation Manual |
ML20212A294 | 2 October 1997 | Rev 56 to Dresden Nuclear Power Plant for Insertion in NRC Security Plan.Rev Withheld | |
ML20216C638 | 29 August 1997 | Proposed Tech Specs,Incorporating New Siemens' Methodologies That Will Enhance Operational Flexibility & Reducing Likelihood of Future Plant Derates | Shutdown Margin Offsite Dose Calculation Manual Anticipated operational occurrence Fuel cladding |
ML20196G878 | 18 July 1997 | Proposed Tech Specs,Meeting Administrative Commitment Resulting from from Plant TS Improvement Program | |
ML20148K614 | 5 June 1997 | Proposed Tech Specs,Updating Revised TS to Format Consistent W/Recently Approved TS Upgrade for DNP & Proposed Other Miscellaneous Changes Re Decommissioning Status of Unit 1 | High Radiation Area Offsite Dose Calculation Manual Process Control Program Fire Protection Program |
ML20141A641 | 31 May 1997 | Rev 1.4,Chapter 12 to Radiological Effluent Technical Stds (RETS) of ODCM | Grab sample Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report |
ML20216H869 | 31 March 1997 | Revs to OCDM for LaSalle Station,Including Rev 1.8 to Chapter 10,rev 1.9 to Chapter 11,rev 1.8 to Chapter 12 & Rev 1.7 to App F | |
ML17187A799 | 17 February 1997 | Proposed Tech Specs 3/4.7.K & 3/4.8.C Re Issues Resulting from Comeds Efforts to Reconstitute Design Basis of Chrs | |
ML20137C001 | 31 January 1997 | Odcm,Dresden Annex Revs 1.9 to Chapter 10, Radioactive Effluent Treatment & Monitoring, 1.2 to Chapter 11, Radiological Environ Monitoring Program & 1.3 to Chapter 12, Radiological Effluent Technical Standards | Grab sample Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report Process Control Program |
ML20135B058 | 25 November 1996 | Proposed Tech Specs,Submitting Update to Administrative Controls Section of TS Which Reflects Transition of Overall Corporate Responsibility for Storage of Spent Nuclear Fuel | |
ML20129F323 | 23 October 1996 | Proposed Tech Specs Replacing All Existing Pages of Unit 1 TS | High Radiation Area Grab sample Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report Process Control Program Fire Protection Program |
ML20129C239 | 16 October 1996 | Proposed Tech Specs for Dresden 2 & 3 & Quad Cities 1 & 2, marked-up to Show Transition Verbiage | Offsite Dose Calculation Manual Process Control Program Fire Protection Program |
ML20129D398 | 20 September 1996 | Proposed Tech Specs 3/4.6.K,updating Pressure-Temp Curves to 22 Effective Full Power Yrs & TS Bases | Shutdown Margin Hydrostatic Power change |
ML20216H884 | 30 June 1996 | Revs to ODCM for Quad Cities,Including Rev 1.8 to Chapters 10,11,12 & App F | Grab sample Offsite Dose Calculation Manual Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report Process Control Program |
ML20113B600 | 20 June 1996 | Proposed Tech Specs,Incorporating New NRC Approved Thermal Limit Licensing Methodology in List of Approved Methodologies Used in Establishing Thermal Limits in Cycle Specific COLR & Change to Fuel Assembly Design Features | Shutdown Margin Reactor Vessel Water Level Anticipated operational occurrence Nondestructive Examination Abnormal operational transient Scram Discharge Volume Annual Radiological Environmental Operating Report Fuel cladding |
ML20112E634 | 22 May 1996 | Proposed Tech Specs Requesting Emergency Amend to License DPR-25 Temporarily Modifying Description of Certain Corner Room Steel Supports to Match Current Configuration Until Mod During Next Refueling Outage | Safe Shutdown Unanalyzed Condition Safe Shutdown Earthquake Hydrostatic Operating Basis Earthquake Earthquake |
ML20086D474 | 30 June 1995 | Proposed Tech Specs Re TS Upgrade Program for Dresden Units 2 & 3 & Quad Cities Units 1 & 2 | Grab sample Hydrostatic Pressure Boundary Leakage |
ML20092C809 | 12 May 1995 | Rev 2, Shroud Repairs Program for Dresden Units 2 & 3, Back-up Calculations for RPV Stress Rept Number 25A5691, May 1995 | Finite Element Analysis |
ML20087H865 | 2 May 1995 | Proposed Tech Specs Re TS Upgrade Program Section 3/4.10 | Shutdown Margin Reactor Vessel Water Level |
ML20085M617 | 31 July 1994 | Rev 1.1 to Chapter 12, Radioactive Effluent Technical Stds of Dresden ODCM | |
ML20063F901 | 31 January 1994 | Rev 1.0 to Chapters 10,11,12 & App F to Odcm,Dresden Station Units 2 & 3 | Grab sample Offsite Dose Calculation Manual Process Control Program Hardened vent |
ML17179B093 | 10 September 1993 | Rev 2 to Dresden Station 3rd Interval IST Plan, Sections 2,13 & 14,pages 2-1,13-1 to 13-4 & 14-40,respectively | Cold shutdown justification |
ML20058E875 | 3 September 1993 | Revised AOP-6.3, Loss of RHR Shutdown Cooling | |
ML20058E835 | 10 June 1993 | Revised AOP-7.4, Control Room Inaccessibility | |
ML20127D069 | 30 December 1992 | Corporate Emergency Response Organization Required Reading Package 92-11 | |
ML20125D638 | 8 December 1992 | Proposed Tech Specs 3/4.1 Re Reactor Protection Sys | Shutdown Margin Reactor Vessel Water Level Scram Discharge Volume Fuel cladding |
ML20058E868 | 29 September 1992 | Rev 56A to AOP 1BOA PRI-5, Control Room Inaccessibility Unit 1 | |
ML20106A622 | 15 September 1992 | Proposed TS 2.0, Safety Limits & Limiting Safety Sys Settings & 3/4.11, Power Distribution Limits | Shutdown Margin Reactor Vessel Water Level Anticipated operational occurrence Abnormal operational transient Scram Discharge Volume Fuel cladding |
ML20081M125 | 31 August 1992 | Rev 17 to Procedure Dgp 03-04 Control Rod Movements | Overtravel Power change |
ML20099D779 | 29 July 1992 | Proposed Tech Specs Sections 1.0, Definitions, 3/4.0, Applicability & 3/4.3, Reactivity | Safe Shutdown Shutdown Margin Packing leak Offsite Dose Calculation Manual Nondestructive Examination Annual Radioactive Effluent Release Report Scram Discharge Volume Process Control Program Overtravel Fuel cladding Pressure Boundary Leakage Grace period |
ML20096F116 | 24 April 1992 | Proposed Ts,Changing OL Section 2.G Re Reporting Requirements | Fire Protection Program |
ML20081M185 | 31 January 1992 | Rev 17 to Procedure DAP 07-02, Conduct of Shift Operations | Fire Watch |
ML20081M161 | 20 November 1991 | Rev 0 to Procedure DAP 14-4, Control Rod Sequences | |
ML20058E876 | 18 November 1991 | Rev 56 to AOP Bwoa PRI-10, Loss of Rh Cooling Unit 1 | |
ML20081M031 | 15 November 1991 | Rev 2 to Procedure Doa 0300-12, Mispositioned Control Rod (W-2,W-3) | Unanalyzed Condition Time of Discovery Power change |
ML20081M172 | 31 August 1991 | Rev 15 to Procedure DAP 07-01, Operations Dept Organization | |
ML20081M140 | 17 May 1991 | Rev 6 to Procedure DOP 0400-02, Control Rod Minimizer | |