Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
ML23158A19530 August 2023R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program ClarificationsFire Protection Program
ML23191A05921 July 2023R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 155 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1Nondestructive Examination
Pressure and Temperature Limits Report
Fire Protection Program
ML23114A25228 April 2023Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XIIncorporated by reference
ML23073A36816 March 2023Authorization and Safety Evaluation for Proposed Alternative I6R-10, Revision 0 Related to the Steam Generators,
ML22364A0241 March 2023R. E. Ginna Nuclear Power Plant Issuance of Amendments Nos. 231, 231, 232, 232, and 154 Regarding Adoption of TSTF-246Fire Protection Program
ML23005A17623 February 2023R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 153 Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative ChangesShutdown Margin
Surveillance Frequency Control Program
Fire Protection Program
ML23005A12222 February 2023R. E. Ginna Nuclear Power Plant - Issuance of Amendment No 152 Adopt TSTF-315-Revise Technical Specification 3.1.8, Physics Tests Exceptions - Mode 2Shutdown Margin
Fire Protection Program
ML22293B80530 November 2022Constellation Energy Generation, Llc_Fleet - Request to Authorize Use Honeywell Mururoa V4F1 R Supplied Air SuitsMururoa
ML22094A10722 June 2022R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 151 Adopt 10 CFR 50.69, 'Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power ReactorsSafe Shutdown
High winds
Ultimate heat sink
Tornado Missile
Internal Flooding
Probabilistic Risk Assessment
Cyber Security
Incorporated by reference
FLEX
Fukushima Dai-Ichi
Large early release frequency
Frazil ice
Preemption Authority
Earthquake
Fire Protection Program
Very Early Warning Fire Detection
ML22119A09421 June 2022R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 150 Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4BSafe Shutdown
High winds
High Radiation Area
Tornado Missile
Probabilistic Risk Assessment
Cyber Security
FLEX
Surveillance Frequency Control Program
Large early release frequency
Flooding Focused Evaluation
Preemption Authority
Maintenance Rule Program
Offsite Circuit
Fire Protection Program
ML22090A08629 April 2022Amendments to Adopt TSTF-541,Rev.2,Add Exceptions to Surveillance Requirements for Valves,Dampers Locked in Actuated PositionSafe Shutdown
Water Inventory Control
Cyber Security
Surveillance Frequency Control Program
Safeguards Contingency Plan
Recently irradiated fuel
Fire Protection Program
ML21347A03813 January 2022Issuance of Amendments to Revise Reactor Coolant Leakage RequirementsPacking leak
Cyber Security
Pressure and Temperature Limits Report
Surveillance Frequency Control Program
Process Control Program
Safeguards Contingency Plan
Pressure Boundary Leakage
Fire Protection Program
Unidentified leakage
ML21277A24816 November 2021Letter with Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (Public Version)Decommissioning Funding Plan
ML21250A38229 September 2021R. E. Ginna Nuclear Power Plant - Issuance of Relief Request I6R-06 Alternate Inspection for Reactor Vessel InternalsSafe Shutdown Earthquake
Operating Basis Earthquake
Incorporated by reference
Earthquake
Flow Induced Vibration
ML21246A10622 September 2021R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Alternative Request GR-03, Valve Position Verification Testing Extension Sixth 10-Year Inservice Testing Program IntervalIncorporated by reference
Grace period
ML21230A2063 September 2021Proposed Alternative to Use ASME OM Code Case OMN-28Incorporated by reference
ML21216A2205 August 2021Proposed Alternative to Eliminate Certain Documentation Requirements for Pressure Retaining BoltingCoatings
Nondestructive Examination
Incorporated by reference
ML21175A00127 July 2021R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 145 Regarding Technical Specifications Change to Make a One-Time Exception to the Steam Generator Tube Inspection RequirementsNondestructive Examination
Foreign Material Exclusion
COVID-19
Fire Protection Program
ML21166A16825 June 2021Incorporated by reference
ML20353A12611 March 2021R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 144 Implementation of WCAP-14333 and WCAP-15376, TSTF-411-A, and TSTF-418-A to Revise Reactor Trip and Engineered Safety Feature Actuation System InstrumentationHigh winds
Anticipated operational occurrence
Tornado Missile
Internal Flooding
Probabilistic Risk Assessment
Tornado-Generated Missile
Tornado Missile Protection
Surveillance Frequency Control Program
Large early release frequency
Flooding Focused Evaluation
Maintenance Rule Program
Fuel cladding
Fire Protection Program
ML21039A63617 February 2021R. E. Ginna - Proposed Alternative to Use the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-885
ML21028A6733 February 2021Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L-2020-LLR-011Incorporated by reference
ML20287A1305 November 2020Review of Quality Assurance Program ChangesGrace period
ML20269A20030 September 2020Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L2020-LLR-0117Incorporated by reference
ML20167A00711 September 2020R. E. Ginna - Issuance of Amendment Nos. 216, 216, 220, 220, and 143 - Adoption of TSTF-567, Rev. 1, Add Containment Sump Technical Specifications to Address GSI-191 IssuesSurveillance Frequency Control Program
Fire Protection Program
ML20232A1711 September 2020Request to Use Alternative Code Case OMN-26Safe Shutdown
Stroke time
Incorporated by reference
ML20141L63610 July 2020Issuance of Amendments Based on TSTF-427,Allowance for Nontechnical Specification Barrier Degradation on Supported System Operability,Rev 2Time of Discovery
High winds
Fire Barrier
Internal Flooding
Probabilistic Risk Assessment
Cyber Security
Large early release frequency
Safeguards Contingency Plan
Turbine Missile
Fire Protection Program
ML20134H9408 July 2020Issuance of Amendments Revising the High Radiation Area Administrative ControlsHigh Radiation Area
Offsite Dose Calculation Manual
Cyber Security
Annual Radioactive Effluent Release Report
Process Control Program
Safeguards Contingency Plan
Deep Dose Equivalent
Fire Protection Program
Scaffolding
ML20090D2912 June 2020R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Alternative I6R-02 for the Sixth 10-Year Inservice Inspection Interval (EPID L-2019-LLR-0071). Supersedes ML20056D559
ML20113F04130 April 2020Proposed Alternative to the Submittal Schedule for Certain Reports (COVID-19)Incorporated by reference
Pandemic
Coronavirus
COVID-19
ML20021A0706 April 2020Issuance of Amendments to Delete License Conditions for Decommissioning TrustsSafe Shutdown
Internal Flooding
Probabilistic Risk Assessment
Cyber Security
Preemption Authority
Fire Protection Program
ML20057E0913 April 2020R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 139 Add a One-Time Note for Use of Alternative Residual Heat Removal Method
ML20056D55913 March 2020R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Alternative I6R-02 for the Sixth 10-Year Inservice Inspection Interval
ML20055F88613 March 2020R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Alternative I6R-01 for the Sixth 10-Year Inservice Inspection IntervalBoric Acid
ML19325D82423 December 2019R. E. Ginna Nuclear Power Plant Issuance of Amendment No. 136 to Revise Technical Specification 5.5.15, Containment Leakage Rate Testing Program, to Extend Containment Integrated Leak Rate Test FrequencySafe Shutdown
Safe Shutdown Earthquake
Internal Flooding
Probabilistic Risk Assessment
Nondestructive Examination
FLEX
Aging Management
Large early release frequency
Moisture barrier
Earthquake
Fire Protection Program
Grace period
ML19318E0802 December 2019R. E. Ginna Nuclear Power Plant - Safety Evaluation of Alternative Request SR-1 Related to Snubber Program Aligned with Sixth 10-Year Inservice Testing Interval ProgramIncorporated by reference
ML19252A24629 October 2019R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 134 to Revise the Emergency Response Organization Staffing RequirementsCyber Security
Minimum staff
Fire Protection Program
ML19269C53427 September 2019Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination TechniquesIncorporated by reference
ML19205A4535 August 2019R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Alternatives PR-01 and PR-02 for Sixth 10-Year Inservice Testing ProgramIncorporated by reference
ML19205A3535 August 2019R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Alternatives GR-01, VR-01, and VR-02 for the Sixth 10-Year Inservice Testing Program (EPID L-2018-LLR-0382; EPID L-2018-LLR-0383)Stroke time
Incorporated by reference
Surveillance Frequency Control Program
ML19192A24418 July 2019Proposed Alternative to Use ASME Code Cases N-878 and N-880Commercial Grade Dedication
Nondestructive Examination
Incorporated by reference
ML19100A00422 April 2019R. E. Ginna Nuclear Power Plant - Issuance of Relief Request ISI-18 Regarding Fifth 10-Year Inservice Inspection Program IntervalProbabilistic Risk Assessment
ML18309A30115 November 2018R. E. Ginna - Issuance of Amendment Nos. 327, 305, 232, 173, and 133, Respectively, Eliminating the Nuclear Advisory Committee RequirementsCyber Security
Preemption Authority
ML18213A36913 November 2018Issuance of Amendment No. 132 Revise Technical Specifications 3.3.1, Reactor Trip System Instrumentation, and 3.3.2, Engineered Safety Feature Actuation System InstrumentationTest box
Surveillance Frequency Control Program
Fire Protection Program
ML18295A63031 October 2018R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 131 Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF 547, Clarification of Rod Position RequirementsShutdown Margin
Surveillance Frequency Control Program
Fire Protection Program
ML18214A17631 August 2018Issuance of Amendment No. 130, Revise Technical Specification Surveillance Requirement 3.8.4.3, DC (Direct Current) Sources - Modes 1, 2, 3, and 4Anticipated operational occurrence
Fire Protection Program
ML18206A2822 August 2018Issuance of Amendments to Relocate the Staff Qualification RequirementsSafe Shutdown
Cyber Security
Safeguards Contingency Plan
Fire Protection Program
ML18190A47212 July 2018R.E Ginna - Correction to Amendment No. 127 Related to Request to Delete a Modification Associated with the Risk-Informed, Performance Based Fire Protection Program in Accordance with 10 CFR 50.48(c) (CAC No. MF9948; EPID L-2017-LLA-0253)Fire Protection Program
ML18137A61426 June 2018Calvert Cliffs Independent Spent Fuel Storage Installation; Nine Mile Point Nuclear Station; and R. E. Ginna Nuclear Power Plant - Issuance of Amendments Revising Emergency Action Level SchemesHigh winds
Ultimate heat sink
Operating Basis Earthquake
Operator Manual Action
Spent Fuel Pool Instrumentation
Earthquake
Fuel cladding
ML18114A02525 June 2018Issuance of Amendment No. 127, Modify License Condition 2.C.(3) Related to Commitment Associated with Implementation of National Fire Protection Association Standard 805 (CAC MF9948; EPID L-2017-LLA-0253)Safe Shutdown
Probabilistic Risk Assessment
FLEX
Large early release frequency
Fire Protection Program