Issue date | Title | Topic | |
---|---|---|---|
DD-99-12, Informs That Time Provided by NRC Regulation within Which Commission May Act to Review DD-99-12 Has Expired.With Certificate of Svc.Served on 991028 | 28 October 1999 | Informs That Time Provided by NRC Regulation within Which Commission May Act to Review DD-99-12 Has Expired.With Certificate of Svc.Served on 991028 | |
ML20138H383 | 25 October 1999 | Forwards Draft Model of Renewed License for Calvert Cliffs, Unit 2 to Illustrate How List of Minimum Requirements Could Be Incorporated Into License Condition | |
ML20217M287 | 21 October 1999 | Refers to Rev 5 Submitted in May 1999 for Portions of Byron Nuclear Power Station Generating Stations Emergency Plan Site Annex.Informs That NRC Approval Not Required Based on Determination That Plan Effectiveness Not Decreased | |
ML20217M172 | 19 October 1999 | Forwards NRC Rept Number 17, Requal Tracking Rept Form Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates | |
ML20217M210 | 19 October 1999 | Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates | |
ML20217G949 | 14 October 1999 | Forwards Exemption from Requirements of 1-CFR50,App E, Section IV.F.2.c,re Conduct of full-participation Exercise in Sept 1999,at Plant,Units 1,2 & 3 | Exemption Request |
ML20217D967 | 12 October 1999 | Forwards Copy of Transcript of Public Meeting Held by NRC Staff & NNECO on 990825 at Waterford,Connecticut on Decommissioning Program for Millstone,Unit 1.Without Encl | |
ML20217F617 | 8 October 1999 | Forwards Insp Repts 50-335/99-11 & 50-389/99-11 on 990827 & 990907-09.No Violations Identified.Matl Encl Contained Safeguards Info as Defined by 10CFR73.21 & Disclosed to Unauthorized Individuals Prohibited by Section 147 of AEA | |
ML20217F789 | 8 October 1999 | Forwards Insp Repts 50-454/99-12 & 50-455/99-12 on 990803- 0916.One Violation Occurred Being Treated as NCV | Earthquake |
ML20217G080 | 7 October 1999 | Informs That on 990930,staff Conducted mid-cycle PPR of Farley & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Will Conduct Regional Insps Associated with SG Removal & Installation | |
ML20217D301 | 7 October 1999 | Forwards Request for Addl Info Re Util 990118 Request for Amend to License NPF-49 to Allow full-core Offloads to Spent Fuel Pool During Core Offloads to Spent Fuel Pool During Core Offload Events | |
ML20212L179 | 5 October 1999 | Informs That as Result of Staff Review of Util Responses to GL 92-01,rev 1,suppl 1 & Suppl 1 Rai,Staff Revised Info in Rvid & Is Releasing Rvid Version 2 | |
ML20217B635 | 5 October 1999 | Forwards for Info,Final Accident Sequence Precursor Analysis of Operational Event at Byron Station,Unit 1,reported in LER 454/98-018 & NRC Responses to Util Specific Comments Provided in | Mission time Temporary Modification |
ML20217B471 | 4 October 1999 | Informs That Staff Did Not Identify Any Safety Concerns Re Licensee Proposals to Modify Commitments Made for Action Items 4.2.1,4.2.2,4.5.1 & 4.5.2 of GL 83-28 by Providing Addl Justifications or Safety Bases for Changes | |
ML20212M263 | 4 October 1999 | Informs That Staff Concluded That Licensee Responses to GL 97-06 Provides Reasonable Assurance That Condition of Util SG Internals in Compliance with Current Licensing Bases for Calvert Cliffs Nuclear Power Plant | |
ML20212J245 | 1 October 1999 | Informs That Util 980807 & 990629 Responses to GL 98-01, Y2K Readiness of Computer Sys at NPPs Acceptable.Nrc Considers Subj GL to Be Closed for Units 2 &3 | |
ML20212J305 | 1 October 1999 | Discusses GL 97-06 Re Degradation of SG Internals,Dtd 971230.GL Requested Each PWR Licensee to Submit Info That Will Enable NRC Staff to Verify Whether PWR SG Internals Comply & Conform to Current Licensing Basis for Facilities | |
ML20212J999 | 1 October 1999 | Responds to Recent Ltr to President Clinton,H Clinton, Chairman Jackson &/Or Wd Travers Expressing Concern Re Millstone Npps.Nrc Continues to Monitor Performance of Plant to Ensure That Public Health & Safety Adequately Protected | |
ML20212K124 | 1 October 1999 | Responds to Recent Ltrs to Chairman Jackson,Commissioners & Wd Travers,Expressing Concern Re Millstone Npps.Nrc Continues to Monitor Performace of Millstone to Ensure That Public Health & Safety,Adequately Protected | |
ML20212L183 | 1 October 1999 | Responds to Recent Ltr to Wd Travers Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Performance of Millstone to Ensure Adequate Protection to Public Health | |
ML20212L197 | 1 October 1999 | Responds to Recent Ltr to Chairman Jackson & Commissioners Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Plant Performance to Ensure Public Health & Safety | |
ML20212L208 | 1 October 1999 | Responds to Recent Ltrs to President Wj Clinton,Chairman Jackson & Commissioners & Wd Travers,Expressing Concerns Re Millstone NPPs & Continued Lack of Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Plant Performance | |
ML20212L217 | 1 October 1999 | Responds to Recent Ltr to President Wj Clinton,Chairman Jackson & Commissioners,Wd Travers & Ferc,Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island | |
ML20217B299 | 1 October 1999 | Forwards Insp Repts 50-454/99-16 & 50-455/99-16 on 990907-10.No Violations Noted.Water Chemisty Program Was Well Implemented,Resulted in Effective Control of Plant Water Chemistry | |
ML20212J880 | 30 September 1999 | Discusses GL 98-01,suppl 1, Y2K Readiness of Computer Sys at Npps. Util 980731,990607 & 03 Ltrs Provided Requested Info in Subj Gl.Nrc Considers Subj GL to Be Closed for Unit 1 | |
ML20212J839 | 30 September 1999 | Forwards RAI Re Request for Amends to Ts.Addl Info Needed to Complete Review to Verify That Proposed TS Are Consistent with & Validate Design Basis Analysis.Request Discussed with H Mahan on 990930.Info Needed within 10 Days of This Ltr | |
ML20212J675 | 30 September 1999 | Forwards Replacement Pages Eight Through Eleven of Insp Repts 50-454/99-15 & 50-455/99-15.Several Inaccuracies with Docket Numbers & Tracking Numbers Occurred in Repts | |
ML20212J662 | 30 September 1999 | Informs of Completion of mid-cycle PPR of Units 2 & 3 on 990916.Identified Several Recent Instances in Which Condition Repts Were Not Initiated,Resulting in Untimely or Inadequate C/As.Historical Listing of Plant Issues Encl | |
ML20217B322 | 30 September 1999 | Refers to Investigation Rept 1-1997-035 Conducted at Millstone Nuclear Power Station by NRC Ofc of Investigation Field Ofc,Region I on 970915 to Determine Whether Former Health Physics Technician Discriminated Against | |
ML20217A927 | 30 September 1999 | Discusses Investigation Conducted at Millstone Nuclear Power Station by NRC OI Region I on 980319 to Determine If Contract Training Instructor Was Terminated for Raising Concerns About Quality of Training Matls | |
ML20212J781 | 30 September 1999 | Requests That Licensee Address Potential Aging Mgt Issue Re Effects of Void Swelling of Rv Internals by Making Plant Specific Commitment to Implement Focused age-related Degradation Insp for Evidence of Void Swelling in Future | Aging Management |
ML20212J561 | 29 September 1999 | Informs That on 990916,NRC Completed mid-cycle Plant Performance Review of Calvert Cliffs.No Areas in Which Util Performance Warranted Addl Insp Beyond Core Insp Program Identified.Historical Listing of Plant Issues,Encl | |
ML20217A582 | 29 September 1999 | Advises of NRC Plans for Future Insp Activities at Facility for Licensee to Have Opportunity to Prepare for Insps & to Provide NRC with Feedback on Any Planned Insps Which May Conflict with Plant Activities | |
ML20216J134 | 28 September 1999 | Ltr Contract:Task Order 49, Millstone Units 2 & 3 Employee Concerns Program Insp, Under Contract NRC-03-98-021 | |
ML20212M160 | 28 September 1999 | Refers to 990908 Engineering Meeting Conducted at NRC Region II to Discuss Engineering Issues at Lucie & Turkey Point Facilities.List of Attendees & Copy of Presentation Handout Encl | |
IR 05000272/1999007 | 28 September 1999 | Forwards Insp Repts 50-272/99-07 & 50-306/99-07 on 990721- 0831.One Potentially Safety Significant Issue Identified Dealing with Control Room Special Ventilation System.Four Addl Issues of Low Safety Significance Identified | |
ML20212E703 | 23 September 1999 | Responds to GL 98-01, Year 2000 Readiness of Computer Sys at Npps. Util Requested to Submit Plans & Schedules for Resolving Y2K-related Issues | |
ML20212F111 | 21 September 1999 | Discusses Closeout of GL 97-06, Degradation of Steam Generator Internals | |
ML20212F496 | 20 September 1999 | Forwards Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations of NRC Requirements Occurred & Being Treated as Ncvs,Consistent with App C of Enforcement Policy | |
ML20216F805 | 17 September 1999 | Forwards Insp Rept 50-454/99-14 & 50-455/99-14 on 990823-27. Security Program Was Effectively Implemented in Areas Inspected.No Violations Were Identified | |
ML20212D458 | 10 September 1999 | Responds to to D Rathbun,Requesting Review of J Sherman Expressing Concerns That Plant & Other Nuclear Plants Not Yet Y2K Compliant | Safe Shutdown Enforcement Discretion |
ML20212C804 | 10 September 1999 | Responds to to D Rathbun Requesting Review of J Sherman Re Y2K Compliance.Latest NRC Status Rept on Y2K Activities Encl | Safe Shutdown Enforcement Discretion |
ML20212A317 | 10 September 1999 | Discusses Investigation Rept 1-1998-045 Conducted on 981112 to Determine If Former Senior Health Physics Technician Being Denied Employment at Millstone in Retaliation for Having Raised Safety Concerns in Past.Synopsis Encl | |
ML20212A750 | 10 September 1999 | Forwards Staff Requirements Memo Response,Dtd 990525,which Provides Actions NRC Plans for Continued Oversight of safety-conscious Work Environ & Employee Concerns Program | |
ML20212A901 | 10 September 1999 | Forwards Environ Assessment & Finding of No Significant Impact Re Application for Exemption,Dtd 990803.Proposed Exemption Would Provide Relief from Requirement of 10CFR50 | Exemption Request |
ML20212A834 | 9 September 1999 | Requests That Licensees Affected by Kaowool Fire Barriers Take Issue on Voluntary Initiative & Propose Approach for Resolving Subj Issues.Staff Plans to Meet with Licensees to Discuss Listed Topics | Safe Shutdown Fire Barrier Coatings Exemption Request Fire Protection Program Backfit |
ML20212A695 | 9 September 1999 | Requests That Licensees Affected by Kaowool Fire Barriers Take Issue on Voluntary Initiative & Propose Approach for Resolving Subj Issues.Staff Plans to Meet with Licensees to Discuss Listed Topics | Safe Shutdown Fire Barrier Coatings Exemption Request Fire Protection Program Backfit |
ML20211N804 | 8 September 1999 | Informs That on 990930 NRC Issued GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Condition, to Holders of Nuclear Plant Operating Licenses | |
ML20211N430 | 8 September 1999 | Discusses Proposed Meeting to Discuss Kaowool Fire Barriers. Staff Requesting That Affected Licensees Take Issue on Voluntary Initative & Propose Approach for Resolving Issues | Safe Shutdown Fire Barrier Coatings Exemption Request Fire Protection Program Backfit |
ML20211P184 | 8 September 1999 | Forwards Insp Repts 50-454/99-15 & 50-455/99-15 on 990824- 26.No Violations Noted.Objective of Insp to Determine Whether Byron Nuclear Generating Station Emergency Plan Adequate & If Emergency Plan Properly Implemented |