Issue date | Title | Topic | |
---|---|---|---|
ML20205D705 | 2 April 1999 | Notice of Violation from Insp & Investigation Concluded on 981119.Violation Noted:On 980511,supervisor Employed by Raytheon Corp Contractor at Lasalle,Confirmed Odor of Alcohol on Employee & Failed to Perform for-cause FFD Test | Fitness for Duty |
ML20205D589 | 29 March 1999 | Notice of Violation from Insp & Investigation Concluded on 981119.Violation Noted:On 980511,supervisor Employed by Raytheon Corp Contractor at Lasalle,Confirmed Odor of Alcohol on Employee & Failed to Have Require for-cause Test | Fitness for Duty |
ML20237A590 | 7 August 1998 | Notice of Violation from Insp on 980713-16.Violation Noted: on 980526,two Construction Laborers Permitted to Enter Unit 2 a Reactor Water Cleanup Heat Exchanger Room,W/O Satisfying Provisions of TS 6.1.1.1 | High Radiation Area |
ML20236U384 | 24 July 1998 | Notice of Violation from Insp on 980706-21.Violation Noted: as of 980717,testable Valves 1FP-160A,160B,161,236 & 234 in Fire Protection Sys Lines That Supply Fire Suppression Water to Control Room Not Cycled in Preceding 12 Months | |
ML20236L454 | 2 July 1998 | Notice of Violation from Insp on 980423-0605.Violation Noted:Two Operators,Performing OOS Tag Removal & Positioning of Control Room Ventilation Sys Dampers,Did Not Perform an apart-in-time Independent Verification | |
ML20248M127 | 5 June 1998 | Notice of Violation from Insp on 980319-0421.Violations Noted:As of 980421,licensee Failed to Adequately Perform Combustible Loading Calculations Required by LaSalle Administrative Procedure 240-6,rev 36,dtd 970821 | Fire Protection Program |
ML20217D061 | 23 March 1998 | Notice of Violation from Insp on 971222-980306.Violation Noted:Licensee Failed to Ensure,Through Documentation & Other Activities That Applicable Design Basis & Regulatory Requirements Translated Into Procedures & Instructions | |
IR 07100101/2012018 | 23 January 1998 | Notice of Violation from Insp on 971101-1218.Violation Noted:Activities Affecting Quality Were Not Accomplished IAW Applicable Procedures | Operability Determination |
ML20198T363 | 21 January 1998 | Notice of Violation from Insp on 971215-17.Violation Noted:On 971201 Contract Workers Failed to Contact Radiation Protection Prior to Cutting Grinding & Welding Activities on Reactor Water Cleanup Sys Piping Respectively | |
ML20197A822 | 7 November 1997 | Notice of Violation from Insp on 971010 & 20.Violation Noted:On 970908,SM Jozwiak Reported for Duty at LaSalle County Nuclear Station & Was Found to Have Used an Illegal Drug,Marijuana | |
ML20212B310 | 15 October 1997 | Notice of Violation from Insp on 970628-0808.Violations Noted:Licensee CA for NOV Issued on 970124 Re Inadequate Instructions for Performing Manual Backwash,Were Not Adequate to Preclude Repetition | Offsite Dose Calculation Manual |
ML20212B527 | 10 October 1997 | Notice of Violation from Insp on 970908-12.Violation Noted: on 970904,listed Sys Were Inoperable & Licensee Unable to Restore One Subsysten/Sys within 4 H or Established Secondary Containment Integrity within Following 8 H | |
ML20217B425 | 29 August 1997 | Notice of Violation from Insp on 970510-0627.Violation Noted:Inspectors Identified That Surveillance Test Results Indicated That 1B Rhrp Parameters in Required Action Range & Licensee Did Not Immediately Declare Pump Inoperable | |
ML20151J822 | 22 July 1997 | Notice of Violation from Insp on 970322-0509.Violation Noted:Procedures Recommended in App a of RG.133,Rev 2 Were Not Implemented | |
ML20149F022 | 17 July 1997 | Notice of Violation from Insp on 970428-0620.Violation Noted:Test Engineer Conducting Residual Heat Removal SWS post-mod Testing,Safety Related Function Returned to Work W/O Break of 8 H Between Work Periods | |
ML20140B673 | 20 May 1997 | Notice of Violation from Insp on 970207-0321.Violation Noted:Applicable Procedures Recommended in App a of RG 1.33,Rev 2,Feb 1978,were Not Correctly Implemented | |
ML20137J746 | 26 March 1997 | Notice of Violation from Insp on 961207-970206.Violations Noted:Applicable Procedures Recommended in App a of RG 1.33 Rev 2,Feb 1978 Were Not Correctly Implemented | Fire Barrier Fire impairment Fire Protection Program |
ML20140C390 | 24 March 1997 | Notice of Violation from Insp on 970224-28.Violation Noted: as of 970223,technician Did Not Ensure Reasonable Efforts Made to Prevent Spread of Contamination from Contaminated Areas in Unit 1 a & B Heater Drain Pump Rooms | |
ML20134N117 | 14 February 1997 | Notice of Violation from Insp on 961106-07,1204,970103 & 0203.Violation Noted:Minor Mod Was Performed on Components & Sys Using Nuclear Design Info Transmittal Form Rather than Process in Lap 1300-14 from Late 1995 to Oct 1996 | |
ML20134M529 | 13 February 1997 | Notice of Violation from Insp on 961026-1213.Violation Noted:Operator Performing LaSalle Operation Surveillance DG-Q2 Did Not Have Copy of Surveillance Procedure | |
ML20134G487 | 29 January 1997 | Notice of Violation from Insp on 960914-1025 & 1213. Violation Noted:Applicable Procedures Recommended in App a of RG 1.33,Rev 2,dtd Feb 1978,were Not Correctly Implemented in Listed Instances | Fire Protection Program |
ML20132E894 | 9 December 1996 | Notice of Violation from Insp on 961001-08.Violation Noted: Licensee Staff Performed Bench Tests & Determined AOV Actuators in RCIC & PCIS Did Not Exhibit Preloaded Spring Closing Forces Specified in Written Specifications | |
ML20135A432 | 26 November 1996 | Notice of Violation from Insp on 960803-0913.Violation Noted:Failure to Use Appropriate Root Cause Analysis procedure,LTP-500-1,to Troubleshoot & Determine Failure Mechanism When Output Breaker O DG Failed | |
ML20134N264 | 20 November 1996 | Notice of Violation from Insp on 961015-18.Violation Noted:Licensee Did Not Make Surveys to Assure Compliance w/10CFR20.1201(a) Which Limits Radiation Exposure to 5 Rem Total Effective Dose Equivalent | |
ML20134M986 | 15 November 1996 | Notice of Violation from Insp on 960903-24.Violations Noted: on 960331,for Unit 1 & on 960531,for Unit 2,fuel Pool Emergency Makeup Pumps Removed from Svc to Be Modified by Adding SS Weld Overlay to CS Pump Casing | Weld Overlay |
ML20129D566 | 23 September 1996 | Notice of Violation from Insp on 960622-0802.Violation Noted:C/As for 941224,MSIV Closure & C/As for Problem Identification Form Written on 950306,not Effective in Preventing Recurrence of MSIV Closure & Reactor Scram | Condition Adverse to Quality Fire Watch |
ML20134C697 | 17 September 1996 | Notice of Violation from Insp on 960525-0622.Violation Noted:Hydrogen & Oxygen Monitoring Systems for Units 1 & 2 Were Being Operated in Continuous Mode for More than 1 Yr | |
ML20149H287 | 9 November 1994 | Notice of Violation from Insp on 940820-1007.Violation Noted:Licensee Did Not Promptly Identify,Nor Take Proper Actions to Correct Flow Measuring Orifices,Which Were Installed Backwards | |
ML20058H381 | 6 December 1993 | Notice of Violation from Radiation Insp on 931102-09. Violations Noted:On 931031,operator Did Not Immediately Leave Area as Required When Dosimeter Alarm Went Off. Operator Entered Contaminated Area W/Required Clothing | |
ML20058B824 | 18 November 1993 | Notice of Violation from Insp on 930927-1001,06-08,18-20 & 25-29.Violation Noted:Radiation Protection Procedures Not Adhered to & During Concument Work Activities on Refuel Floor.Licensee Failed to Peform Adquate Surveys | |
ML20058A898 | 17 November 1993 | Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $112,500 from Insp on 930908-14.Violation Noted:Surveys to Determine That Individual Exposures to Airborne Concentrations Do Not Exceed Limits Not Made | |
ML20059K651 | 3 November 1993 | Notice of Violation from Insp on 930827-1015.Violation Noted:Hoses & Electrical Cord Which Breached Contaminated Area Boundaries Were Not Taped as Required to Avoid Spread of Contamination from Controlled Area | |
ML20059D959 | 26 October 1993 | Notice of Violation from Insp on 930923-25.Violations Noted: Failure to Follow Procedures Re Mispositioning of Spent Fuel Assembly in Unit 2 Spent Fuel Pool on 930913 & Inadequate Corrective Actions to Prevent Similiar May 1993 Event | |
ML20059D090 | 22 October 1993 | Notice of Violation from Insp on 930823-0930.Violation Noted:Written Safety Evaluation Not Performed for Changes to Facility in Listed Cases | |
ML20059A121 | 15 October 1993 | Notice of Violation from Insp on 920603-0720.Violation Noted:Licensee Records Required to Be Maintained by NRC Regulations Not Complete or Accurate in All Matl Respects | |
ML20057G074 | 7 October 1993 | Notice of Violation from Insp on 930729-0916.Violation Noted:Maint Procedures Used to Repair O DG Cooling Water Pump Oil Fill Line Did Not Include Critical Tolerances Necessary to Adequately Reset Oil Levels | |
ML20057D263 | 27 September 1993 | Notice of Violation from Insp on 930811-18.Violation Noted: Hose Storage Area on 754' Elevation of Turbine Building Contained Smearable Levels of Contamination in Excess of 1,00dpm/100cm2 & Not Posted W/Caution.. | |
ML20057B874 | 17 September 1993 | Notice of Violation from Insp on 930713-0827.Violation Noted:Relay Was Miswired While Performing Mod on 2B Diesel Generator Cooling Water Pump & Hoses & Electrical Cords Which Breached Contaminated Area Boundaries Were Not Taped | |
ML20127A640 | 5 January 1993 | Notice of Violation from Insp on 921126-1228.Violation Noted:Incorrect Fuse Removed During Performance of LaSalle Electrical Surveillance (LES)-PC-101 | Fire Protection Program Fire Watch Hourly Fire Watch |
ML20126C081 | 16 December 1992 | Notice of Violation from Insp on 9211102-1214.Violation Noted:As of 921120,inappropriate Equation Was Used to Evaluate Design Basis Capability of safety-related MOVs | |
ML20125C828 | 4 December 1992 | Notice of Violation from Insp on 921014-1125.Violation Noted:Procedures for Preparation for Refueling & Refueling Equipment Operation,Rwcu Sys & Liquid Radioactive Waste Not Adhered to | |
ML20128B616 | 25 November 1992 | Notice of Violation from Insp on Stated Dates.Violation: Operator Not Fully Familiar W/Requirements of RWP Under Which He Worked,Observed Climbing While Wearing Minimal Protective Clothing (Booties & Gloves) | |
ML20127D819 | 9 September 1992 | Notice of Violation from Insp on 920824-28.Violation Noted: Package of Radioactive Spent Resins Transported W/O Required Info of Content,Activity & Transport Index | |
ML20062E032 | 9 November 1990 | Notice of Violation from Insp on 900902-1020.Violation Noted:Failure to Specifically Address 10CFR50.59 Reviews, Activities & Updated FSAR Changes in Util Annual Rept | |
ML20055D975 | 28 June 1990 | Notice of Violation from Insp on 900530.Violation Noted: Licensee Failed to Conduct Adequate Evaluation to Determine Radiological Conditions Associated W/Floor Contamination Before Allowing Worker Entry Onto Contaminated Floor | |
ML20248A227 | 22 September 1989 | Notice of Violation from Insp on 890725-0911.Violations Noted:Licensee Attempted to Lineup Common Reactor Bldg Closed Cooling Water HX from Unit 2 to 1 W/O Approved Procedure | |
ML20245E883 | 3 August 1989 | Notice of Violation from Insp on 890610-0724.Violation Noted:Equipment Contaminated W/Byproduct Matl Transferred to Unauthorized Offsite Equipment Repair Vendor | |
ML20246D622 | 30 June 1989 | Notice of Violation from Insp on 890523-0616.Violations Noted:Licensee Failed to Include Appropriate Quantitative & Qualitative Acceptance Criteria Specified by Tech Specs for Aforementioned Ventilation Sys Into Implementing Procedure | |
ML20245K801 | 28 June 1989 | Notice of Violation from Insp on 890501-05,15-19 & 25. Violations Noted:Failure to Demonstrate That Diesel Generator Automatic Trips Automatically Bypassed as Stated & Failure to Review Listed Procedures for Adequacy | |
ML20245E601 | 20 June 1989 | Notice of Violation from Insp on 890425-0609.Violation Noted:On 890405 & 19,util Failed to Identify Cause of Failure & Corrective Action Re Reactor Bldg Ventilation Isolation Damper |