IR 05000445/202300523 August 2023Updated Inspection Plan for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2023005 and 05000446/2023005)- Mid Cycle Letter 2023
ML23068A3789 March 2023Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000445/2023011 and 05000446/2023011) and Request for InformationSafe Shutdown
Fitness for Duty
Commercial Grade Dedication
Hydrostatic
Probabilistic Risk Assessment
Temporary Modification
Aging Management
Job Performance Measure
Fire Protection Program
IR 05000445/20220061 March 2023Annual Assessment Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2022006 and 05000446/2022006)Fitness for Duty
Commercial Grade Dedication
License Renewal
Exemption Request
COVID-19
IR 05000445/202200522 August 2022Updated Inspection Plan for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2022005 and 05000446/2022005)Fitness for Duty
Commercial Grade Dedication
Cyber Security
License Renewal
Exemption Request
COVID-19
ML22179A30328 June 2022Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000445/2022401; 05000446/2022401Cyber Security
ML22124A3045 May 2022Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000445/2022003 and 05000446/2022003) and Request for InformationUltimate heat sink
Coatings
Nondestructive Examination
Aging Management
Frazil ice
IR 05000445/20210062 March 2022Annual Assessment Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2021006 and 05000446/2021006)Fitness for Duty
Commercial Grade Dedication
Cyber Security
Exemption Request
Coronavirus
ML21253A2339 September 2021Request for Information: Comanche Peak Nuclear Power Plant, Units 1 and 2 (05000445 and 05000446); Occupation Radiation Safety (71124.01, 71124.02, 7511)High Radiation Area
ML21245A3072 September 2021Request for Information ML21245A307Boric Acid
Nondestructive Examination
Scaffolding
IR 05000445/20210051 September 2021Mid-Cycle Inspection Plan Transmittal Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2021005 and 05000446/2021005)Fitness for Duty
Operator Manual Action
Cyber Security
Open Phase Condition
Exemption Request
Power-Operated Valves
COVID-19
ML21176A12925 June 2021CPNPP FFD Inspection Doc Request 2021Fitness for Duty
ML21103A39813 April 2021CP Security Inspection Information Request 2021403
ML21027A43227 January 2021Information Request, Security IR 2021401
ML20309A3604 November 2020Notification of NRC Design Bases Assurance Inspection (Teams) (Inspection Report 05000445/2021011 and 05000446/2021011) and Initial Request for InformationUltimate heat sink
Probabilistic Risk Assessment
Temporary Modification
Large early release frequency
IR 05000445/20200051 September 2020Updated Inspection Plan for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2020005 and 05000446/2020005)Fitness for Duty
Operator Manual Action
Cyber Security
Open Phase Condition
Exemption Request
Power-Operated Valves
COVID-19
ML20139A14518 May 2020Notification of NRC Design Bases Assurance Inspection (Programs) (05000445/2020010 and 05000446/2020010) and Initial Request for InformationPower-Operated Valves
ML20055E1053 March 2020CP2019006 Annual Assessment LetterFitness for Duty
Operator Manual Action
Cyber Security
Open Phase Condition
Power-Operated Valves
ML20045E35113 February 2020Information Request February 13, 2020 Notification of Inspection and Request for Information Comanche Peak Unit 2 NRC Inspection Report 05000446/2020002Boric Acid
Nondestructive Examination
Scaffolding
IR 05000445/201900530 August 2019Updated Inspection Plan for Comanche Peak, Units 1 and 2, Reports 05000445/2019005 and 05000446/2019005Fitness for Duty
Cyber Security
IR 05000445/20180064 March 2019Annual Assessment Letter for Comanche Peak, Units 1 and 2 (Report 05000445/2018006 and 05000446/2018006)Cyber Security
ML19043A94420 February 20192019 CP Brq RFI LetterTime Critical Operator Action
IR 05000445/201800531 August 2018Updated Inspection Plan for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2018005 and 05000446/2018005)Cyber Security
Open Phase Condition
IR 05000445/20170061 March 2018Annual Assessment Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2017006 and 05000446/2017006)Open Phase Condition
IR 05000445/201700528 August 2017Updated Inspection Plan for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2017005 and 05000446/2017005)B.5.b
IR 05000445/20160061 March 2017Annual Assessment Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2016006 and 05000446/2016006)B.5.b
Spent Fuel Pool Instrumentation
ML16302A10027 October 2016Notification of Inspection (NRC Inspection Report 05000445/2017002 and 05000446/2017002) and Request for Information
IR 05000445/201600512 September 2016Errata for Mid-Cycle Assessment Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2016005 and 05000446/2016005)B.5.b
Spent Fuel Pool Instrumentation
ML16239A25231 August 2016Mid-Cycle Assessment Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2016005 and 05000446/2016005)Spent Fuel Pool Instrumentation
B.5.b Mitigating Strategies
IR 05000445/201640131 August 2016Non-Public Security Inspection Plan for Comanche Peak Nuclear Power Plant (NRC Physical Security Inspection Report Numbers 05000445/2016401 and 05000446/2016401)
IR 05000445/20150062 March 2016Annual Assessment Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2015006 and 05000446/2015006)B.5.b
Spent Fuel Pool Instrumentation
IR 05000445/20154011 September 2015Non-Public Security Inspection Plan for Comanche Peak Nuclear Power Plant (NRC Physical Security Inspection Report Numbers 05000445/2015401 and 05000446/2015401)
IR 05000445/20150051 September 2015Mid-Cycle Assessment Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2015005 and 05000446/2015005)B.5.b
Spent Fuel Pool Instrumentation
IR 05000445/20140062 September 2014Mid-Cycle Assessment Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2014006 and 05000446/2014006)B.5.b
Spent Fuel Pool Instrumentation
IR 05000445/20144022 September 2014Non-Public Security Inspection Plan for Comanche Peak Nuclear Power Plant (NRC Physical Security Inspection Report Numbers 05000445/2014402 and 05000446/2014402)
IR 05000445/20130014 March 2014IR 05000445-13-001 & 05000446-13-001, 02/12/2014, Comanche Peak, Units 1 & 2, Annual Assessment Inspection Plan
ML13282A5009 October 2013Notification of NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000445-14-008 and 05000446-14-008) and Request for InformationHot Short
Safe Shutdown
Fire Barrier
Probabilistic Risk Assessment
Multiple Spurious Operation
Emergency Lighting
B.5.b Mitigating Strategies
Maintenance Rule Program
Fire Protection Program
IR 05000445/20130063 September 2013(Report 05000445/2013006 and 05000446/2013006)
IR 05000445/20128014 March 2013Annual Assessment Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2012801 and 05000446/2012801)
ML13060A4351 March 2013Notification of NRC Component Design Bases Inspection IR 05000445-13-007 and 05000446-13-007, and Initial Request for InformationProbabilistic Risk Assessment
Temporary Modification
IR 05000445/20120064 September 2012Mid-Cycle Letter for Comanche Peak Nuclear Power Plant Units 1 and 2 (Reports 05000445/2012006 and 05000446/2012006)
IR 05000445/20120015 March 2012Annual Assessment Letter for Comanche Peak Nuclear Power Plant Units 1 and 2 (Report 05000445/2012001 and 05000446/2012001)
ML1124306441 September 2011Mid-Cycle Performance Review and Inspection Plan - Comanche Peak Nuclear Power Plant - Units 1 and 2
CP-201101030, Transmittal of Unit 1 Inservice Inspection Program Plan, Revision 6, (Unit 1: ASME Code XI 1998 Edition, 1999 and 2000 Addenda, Interval Start - August 13, 2000, Second Interval)2 August 2011Transmittal of Unit 1 Inservice Inspection Program Plan, Revision 6, (Unit 1: ASME Code XI 1998 Edition, 1999 and 2000 Addenda, Interval Start - August 13, 2000, Second Interval)Non-Destructive Examination
Weld Overlay
Hydrostatic
VT-2
Liquid penetrant
Through-Wall Leak
Dissimilar Metal Weld
CP-201101031, Transmittal of Unit 1 Inservice Inspection Program Plan, Revision 0 (Unit 1: ASME Code XI 1998 Edition, 1999 and 2000 Addenda, Interval Start - August 13, 2010, Third Interval)2 August 2011Transmittal of Unit 1 Inservice Inspection Program Plan, Revision 0 (Unit 1: ASME Code XI 1998 Edition, 1999 and 2000 Addenda, Interval Start - August 13, 2010, Third Interval)Weld Overlay
Internal Flooding
Hydrostatic
Probabilistic Risk Assessment
Nondestructive Examination
VT-2
Incorporated by reference
Large early release frequency
Liquid penetrant
IR 05000445/20110014 March 2011IR 05000445-11-001, 05000446-11-001, 03/01/2011 - 02/29/2012, Comanche Peak Nuclear Power Plant, Units 1 and 2, Annual Assessment Letter
ML1024403971 September 2010Mid-Cycle Performance Review and Inspection Plant - Comanche Peak Nuclear Power Plant
IR 05000445/20100013 March 2010Annual Assessment Letter - Comanche Peak Nuclear Power Plant (Reports 05000445-10-001 and 05000446-10-001)
CP-200900848, Submittal of Unit 2 Inservice Inspection Plan for Refueling Outage No .1130 July 2009Submittal of Unit 2 Inservice Inspection Plan for Refueling Outage No .11
IR 05000445/20090014 March 2009Annual Assessment Letter - Comanche Peak Steam Electric Station (Reports 05000445/2009001 and 05000446/2009001)
ML0824606392 September 20082008 Midcycle Assessment Letter Comanche Peak and Inspection Plan