Non-Public Security Inspection Plan for Comanche Peak Nuclear Power Plant (NRC Physical Security Inspection Report Numbers 05000445/2014402 and 05000446/2014402)
ML14245A421
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 09/02/2014
From: Mark Haire
Plant Support Branch-1
To: Flores R
Luminant Generation Co
References
IR-2014-402
Download: ML14245A421 (4)


Text

tember 2, 2014

SUBJECT:

NON-PUBLIC SECURITY INSPECTION PLAN FOR COMANCHE PEAK NUCLEAR POWER PLANT (NRC PHYSICAL SECURITY INSPECTION REPORT NUMBERS 05000445/2014402 AND 05000446/2014402)

Dear Mr. Flores:

On August 12, 2014, the NRC completed its mid-cycle performance review of Comanche Peak Nuclear Power Plant. The results of that review have been transmitted to you separately in publicly available assessment letter. This letter informs you of the NRCs plans for future security-related inspections at your facility.

The enclosed inspection plan lists the security-related inspections scheduled through December 31, 2015. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the next semiannual performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. Routine force-on-force inspections are conducted approximately every 3 years. You will be notified by separate correspondence 8 to 10 weeks in advance of any force-on-force inspections scheduled for your facility.

While we are fully committed to our goal of ensuring openness in our regulatory process, we must balance that goal with the more immediate need of ensuring the continued safety and secure operation of nuclear facilities and the protection of nuclear materials in our country.

Thus due to the security-related information contained in this correspondence, and in accordance with NRC Policy For Handling, Marking and Protecting Sensitive Unclassified Non-Safeguards Information, a copy of this letter and its enclosure will not be available for public inspection in either the NRC Public Document Room or the Publicly Available Records (PARS) component of NRC's document system (ADAMS).

Please contact me at (817) 200-1527 with any questions you have regarding this letter.

Sincerely,

/RA/

Mark S. Haire, Chief Plant Support Branch 1 Division of Reactor Safety Docket Nos.: 50-445; 50-446 License Nos.: NPF-87; NPF-89 Enclosure:

Inspection Plan cc w/enclosure:

Mr. Neil Harris (interim)

Manager, Nuclear Security Luminant Generation Company, LLC Comanche Peak Nuclear Power Plant Mail Code X02 6322 North FM 56 Glen Rose, TX 76043 ML14245A421 SUNSI Review ADAMS Publicly Available Non-Sensitive Keyword: RGN-002 By: MHaire Yes No Non-Publicly Available Sensitive OFFICE C:PSB1 NAME MHaire/dch SIGNATURE /RA/

DATE 8/29/2014 Letter to Rafael Flores from Mark Haire, dated September 2, 2014 SUBJECT: NON-PUBLIC SECURITY INSPECTION PLAN FOR COMANCHE PEAK NUCLEAR POWER PLANT (NRC PHYSICAL SECURITY INSPECTION REPORT NUMBERS 05000445/2014402 AND 05000446/2014402)

Electronic Distribution by RIV w/enclosure:

Security Specialist/NSIR (Eric.Wharton@nrc.gov)

Security Specialist/NSIR (Niry.Simonian@nrc.gov)

Senior Resident Inspector (John.Kramer@nrc.gov)

Electronic Distribution by RIV w/o enclosure:

Regional Administrator (Marc.Dapas@nrc.gov)

Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)

Acting DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Michael.Hay@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Resident Inspector (Rayomand.Kumana@nrc.gov)

Branch Chief, DRP/A (Wayne.Walker@nrc.gov)

Senior Project Engineer, DRP/A (Ryan.Alexander@nrc.gov)

Acting Senior Project Engineer, DRP/A (Theresa.Buchanan@nrc.gov)

Project Engineer, DRP/A (Brian.Cummings@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Balwant.Singal@nrc.gov)

Branch Chief, DRS/TSB (Geoffrey.Miller@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV/ETA: OEDO (Anthony.Bowers@nrc.gov)

ROPreports