Issue date | Title | Topic | |
---|---|---|---|
IR 05000293/2018006 | 4 March 2019 | Annual Assessment Letter for Pilgrim Nuclear Power Station (Report 05000293/2018006) and Confirmatory Action Letter Closure | |
IR 05000293/2018013 | 23 January 2019 | Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2018013 | Foreign Material Exclusion Operability Determination |
ML19017A035 | 17 January 2019 | Revision to Confirmatory Action Letter - Pilgrim Nuclear Power Station | |
IR 05000293/2018012 | 1 November 2018 | Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2018012 | Operability Determination Power change |
ML18284A054 | 11 October 2018 | Revision to Confirmatory Action Letter - Pilgrim Nuclear Power Station | |
IR 05000293/2018011 | 9 October 2018 | Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2018011 | Operability Determination |
ML18235A028 | 23 August 2018 | Revision to Confirmatory Action Letter - Pilgrim Nuclear Power Station | |
IR 05000313/2018013 | 18 June 2018 | NRC Confirmatory Action Letter (EA-16-124) Follow-Up Inspection Report 05000313/2018013 and 05000368/2018013 and Assessment Follow-Up Letter | Boric Acid Tornado Missile Internal Flooding Coatings Fire impairment Temporary Modification Biofouling Through-Wall Leak |
IR 05000293/2018010 | 13 June 2018 | Confirmatory Action Letter (EA-17-086) Follow-Up Inspection Report 05000293/2018010 | Functionality Assessment Condition Adverse to Quality Operability Determination |
ML18158A134 | 7 June 2018 | Revision to Confirmatory Action Letter - Pilgrim Nuclear Power Station | |
IR 05000416/2017014 | 12 March 2018 | Confirmatory Order, NRC Inspection Report 05000416/2017014, and NRC Investigation Reports 4-2016-004 and 4-2014-021 | Enforcement Discretion Exemption Request |
IR 05000313/2017013 | 24 January 2018 | NRC Confirmatory Action Letter (EA-16-124) Follow-Up Inspection Report 05000313/2017013 and 05000368/2017013 | Coatings Aging Management |
IR 05000313/2017012 | 6 October 2017 | NRC Confirmatory Action Letter (EA-16-124) Follow-Up Inspection Report 05000313/2017012 and 05000368/2017012 | Internal Flooding Coatings Functionality Assessment Operability Determination |
ML17214A088 | 2 August 2017 | Confirmatory Action Letter - Pilgrim Nuclear Power Station | Functionality Assessment Condition Adverse to Quality |
IR 05000313/2017011 | 14 July 2017 | NRC Confirmatory Action Letter (EA-16-124) Follow-Up Inspection Report 05000313/2017011 and 05000368/2017011 | Non-Destructive Examination Internal Flooding Functionality Assessment Operability Determination |
ML17088A289 | 29 March 2017 | Revision to Confirmatory Action Letter for Arkansas Nuclear One, Units 1 and 2 | |
ML16169A193 | 17 June 2016 | Confirmatory Action Letter | Boric Acid Internal Flooding Probabilistic Risk Assessment Coatings Fire impairment Temporary Modification Functionality Assessment Aging Management |
ML13177A280 | 26 June 2013 | Confirmatory Action Letter (CAL) Revision 1 - Palisades Nuclear Plant Commitments to Address Safety Injection Refueling Water Tank (SIRWT) and Control Room Concrete Support Structure Leakage | Temporary Modification |
ML082800455 | 2 October 2008 | Withdrawal of Revision to Commitment of Examination Frequency for Pressurizer Butt Welds | |
ML082680182 | 22 September 2008 | Revision to Commitment of Examination Frequency for Pressurizer Butt Welds | |
ML082630145 | 18 September 2008 | Confirmatory Action Letter: Commitments to Address Degraded Spent Fuel Pool Storage Rack Neutron Absorber | |
ML082410180 | 16 September 2008 | Closure of Confirmatory Action Letter NRR-07-006 | Weld Overlay Nondestructive Examination Dissimilar Metal Weld |
ML082350676 | 22 August 2008 | Confirmatory Action Letter (1-08-005) | |
ML081150243 | 15 May 2008 | Completion of Actions for Confirmatory Action Letter NRR-07-023 (Tac No. MD4168) | Dissimilar Metal Weld |
ML080740353 | 14 March 2008 | Evaluation of New Information Related to Alloy 82/182 Pressurizer Butt Weld Inspections Confirmatory Action Letter NRR-07-006 | Nondestructive Examination Dissimilar Metal Weld |
ML080320153 | 31 January 2008 | Supplement to 60-Day Post-Outage Report Per Cal No. NRR-07-023 Pressurizer Butt Weld Inspection | Boric Acid Weld Overlay |
ML073461017 | 12 December 2007 | Day Post-Outage Report Per CAL No. NRR-07-023 Pressurizer Butt Weld Inspection | Boric Acid |
ML072490169 | 7 September 2007 | Evaluation of Finite Element Analysis in Support of Alloy 82/182 Pressurizer Butt Weld Inspections in 2008 as Provided by Confirmatory Action Letter NRR-07-006 | Finite Element Analysis Dissimilar Metal Weld |
ML070800449 | 29 March 2007 | Confirmatory Action Letter (CAL No. NRR-07-023) Palisades Nuclear Plant | Dissimilar Metal Weld |
ML070780094 | 29 March 2007 | Confirmatory Action Letter CAL No. NRR-07-010 Alloy 82/182 Pressurizer Butt Welds | DM weld |
ML070710563 | 20 March 2007 | Confirmatory Action Letter Alloy 82/182 Pressurizer Butt Welds | DM weld |
ML060620420 | 22 July 1998 | Confirmatory Action Letter 97-7-001 Technical Evaluation | Non-Destructive Examination Nondestructive Examination Liquid penetrant |