RS-09-011, Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.

From kanterella
Jump to navigation Jump to search

Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.
ML090210304
Person / Time
Site: Dresden, Oyster Creek, Byron
Issue date: 01/20/2009
From: Simpson P
Exelon Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-08-001, RS-09-011
Download: ML090210304 (2)


Text

Exel6n .

Nuclear Exelon Nuclear www,exeloncorp .com 4300 Winfield Road Warrenville, I L 6o555 RS-09-011 10 CFR 50.54(f)

January 20, 2009 U . S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852 Byron Station, Unit 2 Facility Operating License No. NPF-66 NRC Docket No. STN 50-455 Dresden Nuclear Power Station, Unit 3 Renewed Facility Operating License No. DPR-25 NRC Docket No. 50-249 Oyster Creek Nuclear Generating Station Facility Operating License No. DPR-16 NRC Docket No. 50-219

Subject:

Supplemental Response to Generic Letter 2008-01

References:

1 . NRC Generic Letter 2008-01, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems,"

dated January 11, 2008

2. Letter from K. R. Jury (Exelon Generation Company, LLC/AmerGen Energy Company, LLC) to U. S . NRC, "Three Month Response to Generic Letter 2008-01," dated April 11, 2008
3. Letter from K. R. Jury (Exelon Generation Company, LLC/AmerGen Energy Company, LLC) to U . S. NRC, "Nine-Month Response to Generic Letter 2008-01," dated October 14, 2008 The NRC issued Generic Letter (GL) 2008-01 (i .e., Reference 1) to request that each licensee evaluate the licensing basis, design, testing, and corrective action programs for the Emergency Core Cooling, Decay Heat Removal, and Containment Spray systems, to ensure that gas accumulation is maintained less than the amount that challenges operability of these systems, and that appropriate action is taken when conditions adverse to quality are identified .

January 20, 2009 U . S . Nuclear Regulatory Commission Page 2 References 2 and 3 provided the Exelon Generation Company, LLC (EGC), and AmerGen Energy Company, LLC (AmerGen), responses to NRC GL 2008-01 . In Reference 2, EGC/AmerGen described an alternative course of action since the GL 2008-01 requested evaluations would not be fully complete in accordance with the timeframe required by the GL for several of the EGC/AmerGen units . The remaining actions (i.e., walkdowns of inaccessible piping sections and evaluations using results of the walkdowns) have now been completed for Byron Station Unit 2, Dresden Nuclear Power Station Unit 3, and Oyster Creek Nuclear Generating Station.

As committed in Reference 2, this supplemental response is being submitted for the units listed above to document completion of the walkdowns and any impact upon the GL 2008-01 nine-month response submitted in Reference 3. Walkdowns of inaccessible piping sections for these units were completed during fall 2008 refueling outages for each unit. Evaluation of the walkdown results for each unit did not identify any unexpected vulnerabilities that impact the information in Reference 3, and no new corrective actions were determined necessary. In summary, based on reviews and changes discussed in Reference 3, the GL 2008-01 subject systems are in compliance with the current licensing and design bases and applicable regulatory requirements, and suitable design, operational, and testing control measures are in place for maintaining this compliance.

There are no regulatory commitments contained in this letter. Should you have any questions concerning this letter, please contact Mr. Kenneth M. Nicely at (630) 657-2803 .

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 20th day of January 2009 .

Patrick R. Simpson Manager - Licensing cc: NRC Regional Administrator - Region I NRC Regional Administrator - Region III Senior Resident Inspector - Byron Station Senior Resident Inspector - Dresden Nuclear Power Station Senior Resident Inspector - Oyster Creek Nuclear Generating Station

Text

Exel6n .

Nuclear Exelon Nuclear www,exeloncorp .com 4300 Winfield Road Warrenville, I L 6o555 RS-09-011 10 CFR 50.54(f)

January 20, 2009 U . S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852 Byron Station, Unit 2 Facility Operating License No. NPF-66 NRC Docket No. STN 50-455 Dresden Nuclear Power Station, Unit 3 Renewed Facility Operating License No. DPR-25 NRC Docket No. 50-249 Oyster Creek Nuclear Generating Station Facility Operating License No. DPR-16 NRC Docket No. 50-219

Subject:

Supplemental Response to Generic Letter 2008-01

References:

1 . NRC Generic Letter 2008-01, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems,"

dated January 11, 2008

2. Letter from K. R. Jury (Exelon Generation Company, LLC/AmerGen Energy Company, LLC) to U. S . NRC, "Three Month Response to Generic Letter 2008-01," dated April 11, 2008
3. Letter from K. R. Jury (Exelon Generation Company, LLC/AmerGen Energy Company, LLC) to U . S. NRC, "Nine-Month Response to Generic Letter 2008-01," dated October 14, 2008 The NRC issued Generic Letter (GL) 2008-01 (i .e., Reference 1) to request that each licensee evaluate the licensing basis, design, testing, and corrective action programs for the Emergency Core Cooling, Decay Heat Removal, and Containment Spray systems, to ensure that gas accumulation is maintained less than the amount that challenges operability of these systems, and that appropriate action is taken when conditions adverse to quality are identified .

January 20, 2009 U . S . Nuclear Regulatory Commission Page 2 References 2 and 3 provided the Exelon Generation Company, LLC (EGC), and AmerGen Energy Company, LLC (AmerGen), responses to NRC GL 2008-01 . In Reference 2, EGC/AmerGen described an alternative course of action since the GL 2008-01 requested evaluations would not be fully complete in accordance with the timeframe required by the GL for several of the EGC/AmerGen units . The remaining actions (i.e., walkdowns of inaccessible piping sections and evaluations using results of the walkdowns) have now been completed for Byron Station Unit 2, Dresden Nuclear Power Station Unit 3, and Oyster Creek Nuclear Generating Station.

As committed in Reference 2, this supplemental response is being submitted for the units listed above to document completion of the walkdowns and any impact upon the GL 2008-01 nine-month response submitted in Reference 3. Walkdowns of inaccessible piping sections for these units were completed during fall 2008 refueling outages for each unit. Evaluation of the walkdown results for each unit did not identify any unexpected vulnerabilities that impact the information in Reference 3, and no new corrective actions were determined necessary. In summary, based on reviews and changes discussed in Reference 3, the GL 2008-01 subject systems are in compliance with the current licensing and design bases and applicable regulatory requirements, and suitable design, operational, and testing control measures are in place for maintaining this compliance.

There are no regulatory commitments contained in this letter. Should you have any questions concerning this letter, please contact Mr. Kenneth M. Nicely at (630) 657-2803 .

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 20th day of January 2009 .

Patrick R. Simpson Manager - Licensing cc: NRC Regional Administrator - Region I NRC Regional Administrator - Region III Senior Resident Inspector - Byron Station Senior Resident Inspector - Dresden Nuclear Power Station Senior Resident Inspector - Oyster Creek Nuclear Generating Station