RA-24-0045, Cycle 29, Revision 0, Core Operating Limits Report (COLR)
From kanterella
Jump to navigation
Jump to search
ML24032A017 | |
Person / Time | |
---|---|
Site: | Mcguire |
Issue date: | 02/01/2024 |
From: | Rollins T Duke Energy Carolinas |
To: | Office of Nuclear Reactor Regulation, Document Control Desk |
References | |
RA-24-0045 MCEl-0400-435, Rev. 000 | |
Download: ML24032A017 (1) | |
Similar Documents at Mcguire | |
---|---|
Category:Fuel Cycle Reload Report
MONTHYEARRA-23-0118, Cycle 29, Revision 1, Core Operating Limits Report (COLR)2023-05-0303 May 2023
[Table view]Cycle 29, Revision 1, Core Operating Limits Report (COLR) RA-20-0313, Cycle 28, Revision 0, Core Operating Limits Report (COLR)2020-09-30030 September 2020 Cycle 28, Revision 0, Core Operating Limits Report (COLR) MNS-18-023, Cycle 26, Revision 1 Core Operating Limits Report2018-03-31031 March 2018 Cycle 26, Revision 1 Core Operating Limits Report MNS-17-042, Cycle 26, Revision 0, Core Operating Limits Report2017-10-0909 October 2017 Cycle 26, Revision 0, Core Operating Limits Report MNS-16-025, Core Operating Limits Report2016-03-23023 March 2016 Core Operating Limits Report ML13270A0872013-09-16016 September 2013 Response to Request for Additional Information Regarding the Core Operating Limits Report for Cycle 23 ML13114A2922013-04-10010 April 2013 Cycle 23, Revision 0, Core Operating Limits Report ML12055A2892012-02-14014 February 2012 Cycle 22, Revision 3, and Unit 2, Cycle 21, Revision 2, Core Operating Limits Report ML1011004612010-04-14014 April 2010 Cycle 21, Revision 0, Core Operating Limits Report ML0930001202009-10-20020 October 2009 Cycle 20, Revision 2, Core Operating Limits Report ML0902201992009-01-0707 January 2009 Submittal of Core Operating Limits Report, Cycle 20, Revision 1 ML0709406842007-03-27027 March 2007 Cycle 19, Revision 30 Core Operating Limits Report (COLR) ML0623401882006-08-14014 August 2006 Cycle 18, Rev. 29, Core Operating Limits Report (COLR) ML0409102582004-03-24024 March 2004 Cycle 17, Revision 27, Core Operating Limits Report (COLR) ML0406506582004-02-23023 February 2004 Cycle 16 Revision 26 Core Operating Limits Report (COLR) and Unit 2, Cycle 16, Revision COLR ML0329404982003-10-0707 October 2003 Cycle 16 Core Operating Limits Report (COLR) ML0302305012002-12-30030 December 2002 Inservice Inspection Report End of Cycle Refueling Outage ML0230304602002-10-21021 October 2002 Core Operating Limits Report (COLR) ML0208703442002-03-20020 March 2002 Core Operating Limits Report (Colr), Revision 21, Cycle 15 2023-05-03 Category:Letter type:RA MONTHYEARRA-23-0242, Proposed Alternative for the Inspection of Reactor Vessel Closure Head Penetrations in Accordance with 10 CFR 50.55a(z)(2)2024-01-10010 January 2024
[Table view]Proposed Alternative for the Inspection of Reactor Vessel Closure Head Penetrations in Accordance with 10 CFR 50.55a(z)(2) RA-23-0325, Submittal of Procedures CSD-EP-HNP-0101-01, 02, CSD-EP-ONS-0101-01, CSD-EP-RNP-0101-01, and EP-RNP-EPLAN-ANNEX2024-01-0808 January 2024 Submittal of Procedures CSD-EP-HNP-0101-01, 02, CSD-EP-ONS-0101-01, CSD-EP-RNP-0101-01, and EP-RNP-EPLAN-ANNEX RA-23-0295, Delay of Planned End Date for Fourth 10-Year Inservice Testing (1ST) Program Interval2024-01-0404 January 2024 Delay of Planned End Date for Fourth 10-Year Inservice Testing (1ST) Program Interval RA-23-0318, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0404 December 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0284, RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0279, Supplement to Application to Adopt Risk-Informed Completion Times TSTF-505, Revision 2 and Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power2023-11-0202 November 2023 Supplement to Application to Adopt Risk-Informed Completion Times TSTF-505, Revision 2 and Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power RA-23-0281, Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes2023-11-0101 November 2023 Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes RA-23-0225, Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes2023-09-20020 September 2023 Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes RA-23-0136, Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0154, Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0142, Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require2023-07-0707 July 2023 Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require RA-23-0127, 10 CFR 50.55a(g)(4)(iv) Request to Use a Subsequent Edition of ASME Section XI Referenced in 10 CFR 50.SSa(a) for ISI Code of Record2023-06-28028 June 2023 10 CFR 50.55a(g)(4)(iv) Request to Use a Subsequent Edition of ASME Section XI Referenced in 10 CFR 50.SSa(a) for ISI Code of Record RA-23-0135, Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory2023-06-0707 June 2023 Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory RA-23-0041, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-30030 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations RA-23-0118, Cycle 29, Revision 1, Core Operating Limits Report (COLR)2023-05-0303 May 2023 Cycle 29, Revision 1, Core Operating Limits Report (COLR) RA-23-0117, Report of Changes to Duke Energy McGuire Emergency Plan Annex2023-05-0101 May 2023 Report of Changes to Duke Energy McGuire Emergency Plan Annex RA-23-0044, Aduke Energy Annual Report of Changes Pursuant to 10 CFR 50.462023-04-26026 April 2023 Aduke Energy Annual Report of Changes Pursuant to 10 CFR 50.46 RA-23-0047, Duke Energy Annual Radiological Environmental Operating Report - 20222023-04-26026 April 2023 Duke Energy Annual Radiological Environmental Operating Report - 2022 RA-23-0046, Annual Radioactive Effluent Release Report - 20222023-04-24024 April 2023 Annual Radioactive Effluent Release Report - 2022 RA-23-0037, Duke Energy - Decommissioning Funding Plan for Independent Spent Fuel Storage Installations (Isfsis)2023-03-30030 March 2023 Duke Energy - Decommissioning Funding Plan for Independent Spent Fuel Storage Installations (Isfsis) RA-23-0039, 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2023-03-30030 March 2023 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums RA-23-0040, Onsite Property Insurance Coverage2023-03-30030 March 2023 Onsite Property Insurance Coverage RA-23-0036, Biennial Decommissioning Financial Assurance Reports2023-03-30030 March 2023 Biennial Decommissioning Financial Assurance Reports RA-23-0076, Supplement to Response to Request for Additional Information (RAI) Regarding McGuire Nuclear Station Unit 1 Spring, 2022 Outage Steam Generator Tube Inspection Report2023-03-16016 March 2023 Supplement to Response to Request for Additional Information (RAI) Regarding McGuire Nuclear Station Unit 1 Spring, 2022 Outage Steam Generator Tube Inspection Report RA-23-0024, Response to Request for Additional Information (RAI) for Relief Request for RPV Reactor Coolant System Welds2023-02-28028 February 2023 Response to Request for Additional Information (RAI) for Relief Request for RPV Reactor Coolant System Welds RA-23-0065, Report of Changes to McGuire EAL Technical Basis Document2023-02-23023 February 2023 Report of Changes to McGuire EAL Technical Basis Document RA-18-0090, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-02-17017 February 2023 Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors RA-22-0257, Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-02-17017 February 2023 Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) RA-22-0091, Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2023-02-16016 February 2023 Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RA-18-0190, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-02-16016 February 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b RA-23-0025, End of Cycle 28 (M1R28) Steam Generator Tube Inspection Report Response to Request for Additional Information (RAI)2023-02-15015 February 2023 End of Cycle 28 (M1R28) Steam Generator Tube Inspection Report Response to Request for Additional Information (RAI) RA-23-0001, Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI2023-02-0202 February 2023 Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI RA-22-0118, License Amendment Request to Revise Restrictive Technical Specification Surveillance Requirement Frequencies2023-02-0101 February 2023 License Amendment Request to Revise Restrictive Technical Specification Surveillance Requirement Frequencies RA-22-0256, Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2023-01-23023 January 2023 Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) RA-22-0335, Submittal of 30-Day Report Per 10CFR26.719(c)(1) - Unsatisfactory Performance of a Health & Human Services Certified Lab2022-12-0505 December 2022 Submittal of 30-Day Report Per 10CFR26.719(c)(1) - Unsatisfactory Performance of a Health & Human Services Certified Lab RA-22-0312, Report of Changes to McGuire Emergency Plan Annex2022-10-26026 October 2022 Report of Changes to McGuire Emergency Plan Annex RA-22-0303, End of Cycle 28 (M1 R28) Steam Generator Tube Inspection Report2022-10-25025 October 2022 End of Cycle 28 (M1 R28) Steam Generator Tube Inspection Report RA-22-0291, Report of Changes to Emergency Plan Implementing Procedures2022-10-17017 October 2022 Report of Changes to Emergency Plan Implementing Procedures RA-22-0024, Relief Requested in Accordance with 10 CFR 50.55a(g)(5)(iii) for Volumetric Examination of Class 1 Components2022-09-21021 September 2022 Relief Requested in Accordance with 10 CFR 50.55a(g)(5)(iii) for Volumetric Examination of Class 1 Components RA-22-0253, Independent Spent Fuel Storage Installation (Isfsi), Register Use of Casks2022-08-25025 August 2022 Independent Spent Fuel Storage Installation (Isfsi), Register Use of Casks RA-22-0178, End of Cycle 28 (M1R28) Inservice Inspection Summary Report2022-08-0808 August 2022 End of Cycle 28 (M1R28) Inservice Inspection Summary Report RA-22-0151, Duke Energy Common Emergency Plan, Revision 2, Summary of Changes2022-05-24024 May 2022 Duke Energy Common Emergency Plan, Revision 2, Summary of Changes RA-22-0148, 10 CFR 26.719(c)(1) Report - Unsatisfactory Performance of a Health and Human Services Certified Laboratory2022-05-16016 May 2022 10 CFR 26.719(c)(1) Report - Unsatisfactory Performance of a Health and Human Services Certified Laboratory RA-22-0147, Duke Energy Carolinas, LLC, and Duke Energy Progress, LLC, Response to Request for Additional Information (RAI) Regarding License Amendment Request for Relocating the Duke Energy Emergency Operations Facility2022-05-13013 May 2022 Duke Energy Carolinas, LLC, and Duke Energy Progress, LLC, Response to Request for Additional Information (RAI) Regarding License Amendment Request for Relocating the Duke Energy Emergency Operations Facility RA-22-0149, Supplement to the Request for an Exemption to the Requirements of Certificate of Compliance No. 1031 for the NAC Magnastor Storage System2022-04-28028 April 2022 Supplement to the Request for an Exemption to the Requirements of Certificate of Compliance No. 1031 for the NAC Magnastor Storage System RA-22-0028, Annual Report of Changes Pursuant to 10 CFR 50.462022-04-27027 April 2022 Annual Report of Changes Pursuant to 10 CFR 50.46 RA-22-0029, Shearon Harris Power Plant, McGuire Nuclear Station, Oconee Nuclear Station, H. B. Robinson Steam Electric Plant - Annual Radioactive Effluent Release Report - 20212022-04-27027 April 2022 Shearon Harris Power Plant, McGuire Nuclear Station, Oconee Nuclear Station, H. B. Robinson Steam Electric Plant - Annual Radioactive Effluent Release Report - 2021 RA-22-0127, Interim Part 21 Report of a Deviation or Failure to Comply for Cutler-Hammer Relay2022-04-0808 April 2022 Interim Part 21 Report of a Deviation or Failure to Comply for Cutler-Hammer Relay RA-22-0102, Response to Request for Additional Information (RAI) Regarding Revision 1 of DPC-NE-1007-P, Conditional Exemption of the EOC Mtc Measurement Methodology2022-04-0707 April 2022 Response to Request for Additional Information (RAI) Regarding Revision 1 of DPC-NE-1007-P, Conditional Exemption of the EOC Mtc Measurement Methodology RA-22-0080, Independent Spent Fuel Storage Installation, McGuire, Units 1 & 2, Independent Spent Fuel Storage Installation, Request for an Exemption to the Requirements of Certificate of Compliance No. 1031 for the NAC Magnastor Storage System2022-04-0707 April 2022 Independent Spent Fuel Storage Installation, McGuire, Units 1 & 2, Independent Spent Fuel Storage Installation, Request for an Exemption to the Requirements of Certificate of Compliance No. 1031 for the NAC Magnastor Storage System 2024-01-08 |