Press Release-III-14-012, NRC Schedules Public Meeting April 8 to Discuss Performance of Point Beach Nuclear Power Plant

From kanterella
Jump to navigation Jump to search
Press Release-III-14-012: NRC Schedules Public Meeting April 8 to Discuss Performance of Point Beach Nuclear Power Plant
ML14087A349
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 03/28/2014
From:
Office of Public Affairs Region II
To:
Category:Press Release
References
Press Release-III-14-012
Download: ML14087A349 (1)


Text

No: III-14-012 March 28, 2014 CONTACT: Viktoria Mitlyng 630-829-9662 Prema Chandrathil 630-829-9663 NRC Schedules Public Meeting April 8 to Discuss Performance of Point Beach Nuclear Power Plant The Nuclear Regulatory Commission staff will hold a public meeting with representatives of NextEra Energy April 8 to discuss the agencys assessment of safety performance for 2013 at the Point Beach Nuclear Power Plant. The two-unit plant is located in Two Rivers, Wisc., approximately 13 miles northwest of Manitowoc.

The meeting is scheduled for 6-7:30 p.m. CDT at the Two Creeks Town Hall, 5128 East Tapawingo Road, in Two Creeks. The NRC will present its assessment of the plants 2013 performance, talk about agency activities, and be available to respond to questions or comments from the public.

NRC inspectors spend a significant amount of time monitoring a wide range of plant activities to ensure the plant operates safely. Our hands-on approach is a key factor in protecting the public and environment, said NRC Region III Administrator Cynthia D. Pederson. We hold public meetings near the plant every year to make our staff available to answer questions about NRC oversight with those who live near the plant.

The annual assessment letter sent from the NRC Region III office to plant officials addresses the performance of the plant during 2013 and will serve as the basis for the discussion.

The NRCs assessment of Point Beachs performance for the past year has Unit 1 in Column 3 due to two white or low to moderate safety significant findings and Unit 2 in Column 2 because of one white finding. One white finding affected both units and is associated with the plants failure to implement external flooding wave run-up protection design features. The second white finding involved Unit 1 and is associated with the plants failure to ensure alignment of the turbine-driven auxiliary feedwater pump. This would have resulted in a failure of the equipment to work when called upon.

The NRC is currently completing a supplemental team inspection for the white findings to assess the plants understanding of the issues and the effectiveness of the short- and long-term corrective actions to prevent recurrence. The NRC will be issuing an inspection report with conclusions on the plants actions. The outcome of this inspection will determine in which column the units will reside and the level of inspection effort going forward.

The NRCs action matrix reflects overall plant performance and agency response. There are five columns in the matrix with Column 1 requiring a baseline level of inspections. A move to the other columns results in an increased level of NRC oversight and inspections. The NRC uses color-coded inspection findings and performance indicators to assess nuclear plant performance. The colors start with green and then increase to white, yellow, or red, commensurate with the safety significance of the issues involved. Performance indicators are statistical measurements of plant and equipment performance.

Overall, the NRC found that the Point Beach facility operated safely in 2013 but the decline in performance has resulted in increased oversight and additional inspections to ensure effective corrective actions. Routine inspections are performed by two NRC Resident Inspectors assigned to the plant and by inspection specialists from the Region III Office in Lisle, Ill., and the agencys headquarters in Rockville, Md.

The most current performance information for Point Beach Unit 1 and Unit 2 is available on the NRC website.

Page l 2