MONTHYEARML23166A0212023-03-10010 March 2023 News Release-I-23-002: NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss Millstone Nuclear Power Plant 2022 Performance ML22083A0522022-03-18018 March 2022 News Release-I-22-004: NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss Millstone Nuclear Power Plant 2021 Performance Press Release-21-050, NRC Approves Power Uprate for Millstone Power Station, Unit 32021-11-18018 November 2021 Press Release-21-050: NRC Approves Power Uprate for Millstone Power Station, Unit 3 Press Release-I-21-003, NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss Millstone Nuclear Power Plant Performance2021-03-11011 March 2021 Press Release-I-21-003: NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss Millstone Nuclear Power Plant Performance Press Release-I-20-023, NRC Names New Resident Inspector at Millstone Station2020-12-0707 December 2020 Press Release-I-20-023: NRC Names New Resident Inspector at Millstone Station Press Release-I-20-003, NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss Millstone Nuclear Power Plant Performance2020-04-0808 April 2020 Press Release-I-20-003: NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss Millstone Nuclear Power Plant Performance Press Release-I-19-021, New NRC Resident Inspector Assigned to Millstone Nuclear Power Plant2019-07-29029 July 2019 Press Release-I-19-021: New NRC Resident Inspector Assigned to Millstone Nuclear Power Plant Press Release-I-19-009, NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss 2018 Millstone Station Performance2019-04-15015 April 2019 Press Release-I-19-009: NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss 2018 Millstone Station Performance Press Release-I-18-006, NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss 2017 Millstone Station Performance2018-03-27027 March 2018 Press Release-I-18-006: NRC to Meet with Connecticut Nuclear Energy Advisory Council to Discuss 2017 Millstone Station Performance Press Release-I-17-032, NRC Issues Confirmatory Order Over Security-Related Violations at Millstone Nuclear Power Plant2017-11-21021 November 2017 Press Release-I-17-032: NRC Issues Confirmatory Order Over Security-Related Violations at Millstone Nuclear Power Plant Press Release-I-17-031, NRC Names New Resident Inspector at Millstone Nuclear Power Plant2017-10-0202 October 2017 Press Release-I-17-031: NRC Names New Resident Inspector at Millstone Nuclear Power Plant Press Release-I-17-007, NRC to Discuss 2016 Performance at Millstone Station Meeting with Connecticut Nuclear Energy Advisory Council2017-03-20020 March 2017 Press Release-I-17-007: NRC to Discuss 2016 Performance at Millstone Station Meeting with Connecticut Nuclear Energy Advisory Council Press Release-I-16-006, *Corrected - Meeting Start Time* NRC to Discuss Millstone Nuclear Plant Annual Assessment During March 29th Meeting with Conn. Nuclear Energy Advisory Council2016-03-28028 March 2016 Press Release-I-16-006: *Corrected - Meeting Start Time* NRC to Discuss Millstone Nuclear Plant Annual Assessment During March 29th Meeting with Conn. Nuclear Energy Advisory Council ML16082A2322016-03-22022 March 2016 Press Release-I-16-006: NRC to Discuss Millstone Nuclear Plant Annual Assessment During March 29th Meeting with Conn. Nuclear Energy Advisory Council Press Release-I-16-006, NRC to Discuss Millstone Nuclear Plant Annual Assessment During March 29th Meeting with Conn. Nuclear Energy Advisory Council2016-03-22022 March 2016 Press Release-I-16-006: NRC to Discuss Millstone Nuclear Plant Annual Assessment During March 29th Meeting with Conn. Nuclear Energy Advisory Council Press Release-16-011, NRC Issues Annual Assessments for Nation'S Nuclear Plants2016-03-0404 March 2016 Press Release-16-011: NRC Issues Annual Assessments for Nation'S Nuclear Plants Press Release-I-15-040, New NRC Resident Inspector Assigned to Millstone Nuclear Plant2015-12-18018 December 2015 Press Release-I-15-040: New NRC Resident Inspector Assigned to Millstone Nuclear Plant Press Release-I-15-039, New NRC Senior Resident Inspector Assigned to Indian Point Nuclear Plant2015-11-20020 November 2015 Press Release-I-15-039: New NRC Senior Resident Inspector Assigned to Indian Point Nuclear Plant Press Release-I-15-037, NRC Initiates Special Inspection at Millstone Unit 2 Nuclear Power Plant2015-10-13013 October 2015 Press Release-I-15-037: NRC Initiates Special Inspection at Millstone Unit 2 Nuclear Power Plant Press Release-15-054, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2015-09-0303 September 2015 Press Release-15-054: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-I-15-034, Dominion Institutes Corrective Actions at Millstone Nuclear Plant Under Settlement Agreement with NRC2015-08-27027 August 2015 Press Release-I-15-034: Dominion Institutes Corrective Actions at Millstone Nuclear Plant Under Settlement Agreement with NRC Press Release-I-15-013, NRC Staff to Meet with Connecticut Nuclear Energy Advisory Council April 14 to Discuss Millstone Nuclear Plant Annual Assessment2015-04-0707 April 2015 Press Release-I-15-013: NRC Staff to Meet with Connecticut Nuclear Energy Advisory Council April 14 to Discuss Millstone Nuclear Plant Annual Assessment Press Release-I-15-012, NRC Finalizes Security-Related Inspection Finding for Millstone Nuclear Power Plant, Resulting in Additional Oversight2015-04-0202 April 2015 Press Release-I-15-012: NRC Finalizes Security-Related Inspection Finding for Millstone Nuclear Power Plant, Resulting in Additional Oversight ML14294A5902014-10-21021 October 2014 Press Release-I-14-039: NRC Issues 'White' Inspection Finding for Millstone 3 Nuclear Plant; Level of Oversight to Be Increased Press Release-I-14-039, NRC Issues 'White' Inspection Finding for Millstone 3 Nuclear Plant; Level of Oversight to Be Increased2014-10-21021 October 2014 Press Release-I-14-039: NRC Issues 'White' Inspection Finding for Millstone 3 Nuclear Plant; Level of Oversight to Be Increased Press Release-I-14-036, NRC Assigns New Resident Inspector to Millstone Nuclear Plant2014-09-25025 September 2014 Press Release-I-14-036: NRC Assigns New Resident Inspector to Millstone Nuclear Plant Press Release-I-14-034, NRC Launches Special Inspection at Millstone 3 Nuclear Power Plant in Response to Continuing Problems with Pump2014-09-15015 September 2014 Press Release-I-14-034: NRC Launches Special Inspection at Millstone 3 Nuclear Power Plant in Response to Continuing Problems with Pump Press Release-I-14-026, NRC Special Inspection to Review Issues During Unplanned Outage on May 25th at Millstone Nuclear Power Plant2014-06-0202 June 2014 Press Release-I-14-026: NRC Special Inspection to Review Issues During Unplanned Outage on May 25th at Millstone Nuclear Power Plant Press Release-I-14-012, NRC to Discuss Millstone Nuclear Plant Annual Assessment During March 31st Meeting with Nuclear Energy Advisory Council2014-03-26026 March 2014 Press Release-I-14-012: NRC to Discuss Millstone Nuclear Plant Annual Assessment During March 31st Meeting with Nuclear Energy Advisory Council Press Release-I-14-004, NRC Begins Special Inspection at Millstone Unit 3 Nuclear Power Plant2014-02-0303 February 2014 Press Release-I-14-004: NRC Begins Special Inspection at Millstone Unit 3 Nuclear Power Plant Press Release-I-13-012, NRC to Discuss Millstone Nuclear Plant Annual Assessment During April 9th Meeting with Nuclear Energy Advisory Council2013-04-0101 April 2013 Press Release-I-13-012: NRC to Discuss Millstone Nuclear Plant Annual Assessment During April 9th Meeting with Nuclear Energy Advisory Council Press Release-12-117, NRC Sponsoring National Academy of Sciences Effort to Carry Out Pilot of Cancer Risk Study2012-10-23023 October 2012 Press Release-12-117: NRC Sponsoring National Academy of Sciences Effort to Carry Out Pilot of Cancer Risk Study Press Release-12-099, NRC Issues Mid-Cycle Assessments for Nation? Nuclear Plants2012-09-0606 September 2012 Press Release-12-099: NRC Issues Mid-Cycle Assessments for Nation? Nuclear Plants Press Release-I-12-030, NRC Names New Senior Resident Inspector at Millstone Nuclear Plant2012-07-0303 July 2012 Press Release-I-12-030: NRC Names New Senior Resident Inspector at Millstone Nuclear Plant Press Release-I-12-016, NRC to Discuss Millstone Nuclear Power Plant Annual Assessment at Open House, Meeting with Nuclear Energy Advisory Council2012-04-0909 April 2012 Press Release-I-12-016: NRC to Discuss Millstone Nuclear Power Plant Annual Assessment at Open House, Meeting with Nuclear Energy Advisory Council Press Release-12-016, NRC Approves Exelon-Constellation Merger, Indirect Transfer of Five Nuclear Power Plant Licenses2012-02-16016 February 2012 Press Release-12-016: NRC Approves Exelon-Constellation Merger, Indirect Transfer of Five Nuclear Power Plant Licenses Press Release-11-166, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2011-09-0606 September 2011 Press Release-11-166: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-11-159, NRC Makes Preparations for Approach of Hurricane Irene; Dispatches Additional Inspectors to Nuclear Plants2011-08-26026 August 2011 Press Release-11-159: NRC Makes Preparations for Approach of Hurricane Irene; Dispatches Additional Inspectors to Nuclear Plants Press Release-I-11-027, NRC Cites Millstone Unit 2 Nuclear Plant for Inspection Finding of Low to Moderate Safety Significance2011-08-0808 August 2011 Press Release-I-11-027: NRC Cites Millstone Unit 2 Nuclear Plant for Inspection Finding of Low to Moderate Safety Significance Press Release-I-11-024, Millstone Regulatory Conference Postponed; Now Scheduled for July 19th2011-06-24024 June 2011 Press Release-I-11-024: Millstone Regulatory Conference Postponed; Now Scheduled for July 19th Press Release-I-11-023, NRC to Hold Regulatory Conference on June 30 Regarding Preliminary White Finding Issued to Millstone 2 Nuclear Plant2011-06-21021 June 2011 Press Release-I-11-023: NRC to Hold Regulatory Conference on June 30 Regarding Preliminary White Finding Issued to Millstone 2 Nuclear Plant Press Release-I-11-015, NRC to Hold Two Public Meetings on May 25th in Waterford, Conn., to Discuss Annual Assessment of Millstone Nuclear Power Plant2011-05-16016 May 2011 Press Release-I-11-015: NRC to Hold Two Public Meetings on May 25th in Waterford, Conn., to Discuss Annual Assessment of Millstone Nuclear Power Plant Press Release-I-11-003, NRC Begins Special Inspection at Millstone Unit 2 Nuclear Plant2011-02-22022 February 2011 Press Release-I-11-003: NRC Begins Special Inspection at Millstone Unit 2 Nuclear Plant Press Release-I-10-021, NRC to Hold Open House, Public Meeting on April 22 in Waterford, Conn. to Discuss Annual Assessment of Millstone Nuclear Power Plant2010-04-19019 April 2010 Press Release-I-10-021: NRC to Hold Open House, Public Meeting on April 22 in Waterford, Conn. to Discuss Annual Assessment of Millstone Nuclear Power Plant Press Release-I-09-022, NRC to Discuss Annual Assessment for Millstone Nuclear Plant at Two Public Meetings Set for April 23 in Waterford, Conn2009-04-17017 April 2009 Press Release-I-09-022: NRC to Discuss Annual Assessment for Millstone Nuclear Plant at Two Public Meetings Set for April 23 in Waterford, Conn Press Release-I-08-063, New NRC Resident Inspector Assigned to Millstone Station2008-12-15015 December 2008 Press Release-I-08-063: New NRC Resident Inspector Assigned to Millstone Station Press Release-I-08-064, NRC Begins Special Inspection at Millstone 3 Nuclear Power Plant2008-12-15015 December 2008 Press Release-I-08-064: NRC Begins Special Inspection at Millstone 3 Nuclear Power Plant Press Release-08-149, NRC Approves Power Uprate for Millstone Nuclear Power Plant2008-08-12012 August 2008 Press Release-08-149: NRC Approves Power Uprate for Millstone Nuclear Power Plant Press Release-08-118, NRC Advisory Committee on Reactor Safeguards to Meet July 9-11 in Rockville, MD2008-06-24024 June 2008 Press Release-08-118: NRC Advisory Committee on Reactor Safeguards to Meet July 9-11 in Rockville, MD ML0814803262008-05-27027 May 2008 Press Release-I-08-035: NRC Monitoring Unusual Event at Millstone 2 Nuclear Plant 2023-03-10
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs, Region I 475 Allendale Road, King of Prussia, Pa. 19406 E-mail: opa1@nrc.gov Site: www.nrc.gov Blog: http://public-blog.nrc-gateway.gov No. I-11-015 May 16, 2011
Contact:
Diane Screnci, (610) 337-5330 Email: OPA1.RESOURCE@nrc.gov Neil Sheehan, (610) 337-5331 NRC TO HOLD TWO PUBLIC MEETINGS ON MAY 25TH IN WATERFORD, CONN.,
TO DISCUSS ANNUAL ASSESSMENT OF MILLSTONE NUCLEAR POWER PLANT The results of the Nuclear Regulatory Commissions annual safety performance assessment for the Millstone nuclear power plant will be the subject of two public meetings on Wednesday, May 25, in Waterford, Conn.
At 2 p.m., the NRC staff will meet with the public at Waterford Town Hall, at 15 Rope Ferry Road in Waterford, to discuss the agencys assessment. Then, at 6:30 p.m., agency staff will discuss the assessment with Connecticuts Nuclear Energy Advisory Council (NEAC) during a public meeting at the same location.
Prior to the conclusion of both sessions, there will be an opportunity for members of the public to ask questions of the NRC staff regarding the plants performance, as well as the agencys oversight of the facility.
Millstone, which is the site of two operating pressurized-water reactors, is located in Waterford. It is operated by Dominion Nuclear Connecticut, Inc.
Our Annual Assessment reviews allow us to step back and gauge whether the nuclear power plants we regulate are on the right track in terms of performance and adhering to the highest levels of safety, NRC Region I Administrator Bill Dean said. Once weve completed these evaluations, we reach out to the public to share that information and to receive their feedback at a location near each plant. We welcome and value these exchanges.
The NRC utilizes a combination of color-coded inspection findings and performance indicators to measure plant performance. The colors start with green, representing very low safety significance, and increase to white, yellow or red, commensurate with the significance of the issues involved.
Overall, the Millstone Unit 2 and 3 reactors operated safely during 2010. At the conclusion of last year, as assessed through the NRCs Reactor Oversight Process, there were no inspection findings that were Greater than Green (rising to the level requiring additional NRC oversight) or any performance indicators that were other than Green (exceeding the threshold
for the indicator and requiring additional NRC oversight) for the units. Therefore, for the remainder of 2011, Millstone will continue to receive the very detailed inspection regime used by the NRC for plants that are operating well.
Recently, an NRC Special Inspection was conducted to review an operational occurrence at Millstone on Feb. 12, 2011. Specifically, a three-member team was sent to the plant to evaluate operator actions and events surrounding an unplanned increase in reactor power, from 88 percent to 96 percent, during main turbine control valve testing. The results of that inspection are currently being evaluated to determine the significance of any conclusions.
Routine inspections are carried out at Millstone by the three NRC Resident Inspectors assigned to the plant and by inspection specialists from the agencys Region I Office in King of Prussia, Pa. In 2010, the NRC devoted about 8,260 hours0.00301 days <br />0.0722 hours <br />4.298942e-4 weeks <br />9.893e-5 months <br /> to inspection of Millstone, including three major team inspections. Among the areas at Millstone being inspected this year are radiological safety, emergency preparedness and radioactive effluents treatment.
The agency issues its review of performance at specific plants twice a year. Inspection findings and performance indicators are also updated on the NRCs website, www.nrc.gov, each quarter. Following the release of the annual performance reviews every March, the public is provided with an opportunity to discuss the results. The meetings, which are held in the vicinity of the plant, are in keeping with the NRCs commitment to transparency and openness with regard to its activities.
The annual assessment letter for Millstone is available on the NRC website at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/mill_2010q4.pdf. The notice for the public meeting is available in the NRCs Agencywide Documents Access and Management System (ADAMS) under accession number ML111250122. ADAMS is available at: http://www.nrc.gov/reading-rm/adams.html. Help in using ADAMS can be obtained via the NRCs Public Document Room at 1-800-397-4209 or 301-415-4737, or by e-mail at PDR.Resources@NRC.GOV.
Current performance information for Millstone Unit 2 is available on the NRC website at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/MILL2/mill2_chart.html. Current performance information for Millstone Unit 3 is available on the NRC website at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/MILL3/mill3_chart.html.
News releases are available through a free listserv subscription at the following Web address:
http://www.nrc.gov/public-involve/listserver.html. The NRC homepage at www.nrc.gov also offers a SUBSCRIBE link. E-mail notifications are sent to subscribers when news releases are posted to NRCs website.