Press Release-I-17-032: NRC Issues Confirmatory Order Over Security-Related Violations at Millstone Nuclear Power Plant
ML17332A441
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 11/21/2017
From:
Office of Public Affairs Region I
To:
Category:Press Release
References
Press Release-I-17-032
Download: ML17332A441 (1)


Text

No: I-17-032 November 21, 2017

Contact:

Diane Screnci, 610-337-5330 Neil Sheehan, 610-337-5331 NRC Issues Confirmatory Order Over Security-Related Violations at Millstone Nuclear Power Plant The NRC has issued a confirmatory order to Dominion Energy Nuclear Connecticut Inc.

following an Alternative Dispute Resolution mediation session regarding security-related violations at the Millstone nuclear power plant.

Dominion Energy has agreed to carry out a series of corrective actions, which are spelled out in the order and which the NRC will confirm in upcoming inspections.

The actions are intended to address two violations and related performance aspects identified during an NRC investigation at the Waterford, Conn., plant, where NRC determined that a now-former contracted security officer working as an armorer deliberately failed to properly perform required maintenance of weapons at the plant and conduct monthly inventories of weapons not in use, including the deliberate falsification of records related to both issues.

The mediation session was conducted on Sept. 20, 2017. Under the ADR process, mediation is facilitated by a neutral third party who has no decision-making authority but assists the NRC and a licensee in reaching an agreement when differences exist regarding an enforcement action.

A number of actions agreed to by Dominion include an evaluation of security contractor oversight and related training; independent reviews of the safety culture and organizational effectiveness within the sites security organization; and communication about the issue to industry peers.

A copy of the confirmatory order will be made available in the NRCs electronic documents system, ADAMS.