No. I-08-035

Contact: Diane Screnci, 610/337-5330

Neil Sheehan, 610/337-5331

May 24, 2008

NRC MONITORING UNUSUAL EVENT AT MILLSTONE 2 NUCLEAR PLANT

The Nuclear Regulatory Commission (NRC) is monitoring an Unusual Event declared

this morning at the Millstone 2 nuclear power plant in Waterford, Conn. An Unusual Event is the

lowest of four levels of emergency classification used by the NRC.

At 9:38 a.m. today, Millstone 2 lost off-site power for reasons that are still being

investigated. (Nuclear power plants, besides sending electricity to the grid, also use a small

percentage of their electrical output to power certain operational equipment.) In response, plant

owner and operator Dominion declared an Unusual Event at 9:54 a.m. due to a loss of off-site

power for greater than 15 minutes.

As designed, the pressurized-water reactor shut down and the plants two emergency

diesel generators, which provide back-up power when off-site power is lost, started to provide

electricity to key safety systems. One of two required off-site power sources has been restored to

the plants electrical distribution system. That occurred at approximately 11:06 a.m.

Millstone 2 was in the process of being restarted and was at a low power level at the time

of the event. The unit had been shut down on May 22 in response to a turbine trip, or shutdown,

believed to be caused by a lightning strike at a substation located about 2 1/2 miles from the plant.

Dominion continues to evaluate the root cause of the May 22 shutdown and whether there is any

connection between the electrical problem that caused that event and the loss of off-site power

earlier today.

The NRC began formally monitoring the event at 10:24 a.m. today. A Resident Inspector

assigned to the plant was already on-site at the time of the event to monitor the plant start-up

from the May 22nd shutdown and immediately began monitoring the companys actions in

response to the shutdown. In addition, the Incident Response Center at the NRCs Region I

Office in King of Prussia, Pa., was activated to track developments at the plant, maintain close

communications, and determine if any additional actions were needed.

NRC NEWS

U.S. NUCLEAR REGULATORY COMMISSION

Office of Public Affairs, Region I

475 Allendale Road, King of Prussia, Pa. 19406

E-mail: opa1@nrc.gov

Site: http://www.nrc.gov

Millstone 3, an adjoining pressurized-water reactor owned and operated by Dominion,

was not affected by the event and continues to operate at 100-percent power.

Federal and state officials have been notified regarding the event.