PY-CEI-NRR-2322, Application for Amend to License NPF-58,stipulating That Water Leakage from Feedwater motor-operated CIVs Will Be Added Into Primary Coolant Sources Outside of Containment Program & Valves Need Not Be Included in Test Program

From kanterella
Jump to navigation Jump to search
Application for Amend to License NPF-58,stipulating That Water Leakage from Feedwater motor-operated CIVs Will Be Added Into Primary Coolant Sources Outside of Containment Program & Valves Need Not Be Included in Test Program
ML20151V471
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 09/09/1998
From: Myers L
CENTERIOR ENERGY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20151V475 List:
References
PY-CEI-NRR-2322, NUDOCS 9809140325
Download: ML20151V471 (39)


Text

~ . ~ . _ - - -- ~ -.... ~._ .._.- -..-..... .. - . . . - _ _ _ - . - . ~ . - . . - - . . - . .

k L

gum _ nnum PerryNuclest P6werPlant

-mmBY ' a'te:'M  :

l  :

Lew W. Myere 216-280-5915

i. Vic2 President Fax:216-280-8029 i l  !

l I i l September 9,1998  !

PY-CEl/NRR-2322L i United States Nuclear Regulatory Commission Document Control Desk  ;

L Washington, DC 20555

. Perry Nuclear Power Plant  !

Docket No. 50-440 License Amendment Request: Improved Licensing and l

Design Basis For Isolation of the Feedwater Penetrations l t

~ Ladies and Gentlemen:

l Pursuant to 10 CFR 50.59 and 10 CFR 50.90, Nuclear Regulatory Commiraan (NRC) review and j approval is requested on a license amendment related to hydrostatic (water) testing of -  !

containment isolation valves in the Feedwater System lines. This Technical Specification change L stipulates that water leakage from the Feedwater motor-operated containment isolation valves will i be added into the Primary Coolant Sources Outside of Containment Program (Technical Specification 5.5.2), and therefore the Feedwater check valves do not need to be included in the

,e -

hydrostatic test program addressed by Surveillance Requirement 3.6.1.3.11. The proposed  ;

. testing change is based on design and licensing basis changes being implemented to improve l l functioning of the Feedwater Leakage Control System.

]

The desire is to add dual power supplies to the motor-operated containment isolation valve and L redirect the feedwater leakage control system to this valve. This improves the reliability of the isolation capability of the penetration, and improves the time required to install the water seal. The proposed Updated Safety Analysis Report (USAR) pages summarizing the improved design and i licensing basis are provided for NRC review under the provisions of 10 CFR 50.59, based on initial assessments that have been performed during the design change development process.

NRC approval of this license amendment package is needed to allow installation of the Feedwater penetration improvements during the seventh refueling outage (RFO7). The outage is currently scheduled to begin on April 10,1999. Therefore, a meeting with the NRC staff is being scheduled for September 10,1998, to initiate discussions on the attached license amendment request.

j~ Attachment 1 provides a summary, a description of the proposed Technical Specification (TS) and USAR changes, a safety analysis, and an environmental consideration. Attachment 2 provides

' the significant hazards consideration. Attachment 3 provides the annotated TS page..

Attachment 4 provides annotated USAR pages. Attachment 5 provides the annotated Bases page (for the NRC staffs information, since the Bases are revised by PNPP site procedures).

l 4

PDR mo m ADOCK 05000440 ce ,

t 1

P

[ PDR ,

i L

. 4 . __ ._ . ~ . _ . . _- _. ._.

' PY-CEl/NRR-2322L -

September 9,1998 Pag 2 2 of 2 -

I If you have questions or require additional information, please contact Mr. Henry L. Hegrat, '

Manager - Regulatory Affairs, at (440) 280-5606.  ;

Very truly yours, Attachments cc: NRC Project Manager -

NRC Resident inspector  :

NRC Region lll  !

' State of Ohio l

l-1 t-I. '

i l I L i l

l l

l I, Lew W. Myers, being duly swom state that (1) I am Vice President - Nuclear, of the  !

' Centerior Service Company, (2) I am duly authorized to execute and file this i certification on behalf of The Cleveland Electric Illuminating Company and Toledo Edison Company, and as the duly authorized agent for Duquesne Light Company, Ohio  !

Edison Company, and Pennsylvania Power Company, and (3) the statements set forth -

i herein are true and correct to the best ofmy knowledge, information and belief. l

(/

Lew W. Myers[ s f

Swom to and subscribed before me, the (JA i

7 day of i

,/f98 f

/e6$5DE,*0CTT~%..

t W.!ty i' 2 H. Fis; n 1 0 h b MrCc Muxn ?:gfxs Fsb.20,2000 (ReccrqsJinLakeCounty) l l

l l

ww r

. 2 Attachment 1 PY-CEl/NRR-2322L Page 1 of 26

SUMMARY

Pursuant to 10 CFR 50.59 and 10 CFR 50.90, Nuclear Regulatory Commission (NRC) review and approval is requested on a license amendment related to hydrostatic (water) testing of ,

containment isolation valves in the Feedwater System lines. A Technical Specification change  !

will clarify that water leakage from the Feedwater motor-operated containment isolation valves will be added into the Primary Coolant Sources Outside of Containment Program (Technical Specification 5.5.2), and therefore the Feedwater lines do not also need to be included in the i hydrostatic test program addressed by Surveillance Requirement 3.6.1.3.11. The proposed I testing change is based on design / licensing basis changes being implemented to improve functioning of the Feedwater Leakage Control System. The proposed Updated Safety Analysis l Report (USAR) pages summarizing the improved design and licensing basis are provided for  ;

NRC review under the provisions of 10 CFR 50.59, based on initial assessments that have been  !

performed during the design change development process. I The Feedwater Leakage Control System (FWLCS) became a significant issue late in initial plant licensing (it was resolved in late 1985), due to NRC reopening of a previously (January 1983) ,

approved penetration configuration / test technique. This led to a negotiated agreement on the I licensing basis for the as-built configuration. This licensing basis is described in detail in Section V of the Safety Analysis, below.

Post-accident dose calculation assumptions continue to be met by the excellent as-found leak test results achieved by the motor-operated gate valves installed in the Feedwater penetration for the purpose of providing long-term, high integrity leakage protection. The challenge experienced at the Perry Nuclear Power Plant (PNPP) has been maintaining low enough leak rates on the twin check valves in each feedwater line to ensure that the lines would be filled with FWLCS seat water as quickly as was discussed with the NRC during the licensing process.

The following discussions provide a summary of the issue, followed by more detailed discussions. Specifically, the following information is provided under the heading of SAFETY ANALYSIS:

1. Brief Summary Of The Current Configuration IL Description Of Why The Feedwater Penetration isolation Methods Are Being Improved Ill. Brief Summary of Proposed improved Feedwater Penetration Configuration  !

IV. Summary Of Existing Licensing Basis Versus Proposed Licensing Basis V. Details of Existing Licensing Basis! References VI. Details of The Design Change NRC approval of this license amendment is necessary before the Feedwater penetration i improvements can be implemented during the seventh refueling outage (RFO7). The outage is currently scheduled to begin on April 10,1999. NRC approval on this proposed amendment is requested prior to January 29,1999, to ensure implementation during RFO7. Otherwise, the feedwater check valves may need to be reworked during the outage, in preparation for the next cycle, until final NRC approval of this license amendment can be completed. This would delay implementation of improvements to the Feedwater penetration isolation method for up to two years.

l

Attachment 1 PY-CEl/NRR-2322L Page 2 of 26 l

SUMMARY

DESCRIPTION OF THE PROPOSED TECHNICAL SPECIFICATION A1LD UPDATED SAFETY ANALYSIS REPORT (USAR) CHANGES A note is being added to the Technical Spec 4ication Surveillance Requirement for hydrostatic (water) testing of lines (SR 3.6.1.3.11). The new note states that the Feedwater lines are excluded from this particular hydrostatic testing program (the Bases explain this is because stem, bonnet and seat water leakage from the third, high integrity valve in the Feedwater lines (the gate valves) is controlled by the Primary Coolant Sources Outside Containment Program I (TS 5.5.2)). The annotated Technical Specification page is included in Attachment 3.

[ Note to reviewers: The proposed Bases changes are included in Attachment 5 for information only, since Bases are not a formal part of the Technical Specifications (Bases changes are processed per the Technical Specification Bases Control Program, Specification 5.5.11).]

The proposed testing change described above is based on design and licensing changes for the Feedwater penetrations. USAR pages are included in Attachment 4 which describe the  ;

improved licensing / design basis for the isolation provisions on the Feedwater System lines, to reflect changes from the licensing / design basis that is currently describeo in licensing correspondence end the USAR.

(Attachment 1 continued on page 3) l l

Attachment 1 PY-CEl/NRR-2322L Page 3 of 26 SAFETY ANALYSIS PARTl. Brief Summary of The Current Configuration Drawings of the current configuration are provided in the following Figures.

/ /

jmo l l

Steam Tunnel Drywell Q d l

N /?  % .

A .iN ,

G sN gpy; ,

B21 F065A/B B21-F032A/B N27-F559A/B lMo l L -

l

(, _j RHR/RWCU '

Return, and -

Outboard FWLCS Inboard FWLCS  ;

from LPCS waterleg pump from RHR B/C waterleg pump  ;

Attention:  ;

The following figure is a mirror image of the one above, i.e., the Reactor Pressure Vessel (RPV) is on the left versus the right. Also, it is " typical" of one of the two Feedwater penetrations; Penetrations # P121 (the "A" line) and P414 (the "B" line).

)

INBOARD OUTBOARD w s v li -

. . Feedwater flow f- cf I bb ' - 4 x x h F- -

- _N\l , d N27-F559 ' @ @ Steam B21-F032 B21-F065 I1 Drywell , Containment Outboard (Div.1) FWLCS g, RWCU Return Line G33-F052 /\

inboard (Div. 2) FWLCS %  !

I I J RHR Shutdown Cooling Return line E12-F053 I I

i l

Attachment 1 PY-CEl/NRR-2322L Page 4 of 26 PARTl. Brief Summary of Current Configuration (continued)

. There are no automatic isolations of Feedwater lines on accident signals, so that Feedwater can maintain flow to the reactor vessel. As noted in ANSI /ANS-56.2, greater plant safety is assured by maintaining a feedwater supply to the reactor (this makes the Feedwater penetrations a unique case, since remote-manual actions are acceptable for isolation despite the non-safety classification of the system).

. Two piston lift style check valves are in each Feedwater line for isolation of significant flow from a Feedwater line break outside containment. These anti-waterhammer valves are not designed for air tests.

. A third valve (Motor-operated valve (MOV), gate valve) is provided for long-term, high integrity leakage protection when, in the judgment of the operator, continued makeup from Feedwater is unnecessary or is not available. This valve provides a tight water seal against postulated radioactive leakage. As part of the licensing basis discussions, the NRC agreed that the non-safety, non-seismic Feedwater piping outboard of the MOV would remain intact at least until this gate valve can be remote-manually isolated by plant operators.

. FWLCS provides a manually initiated seal water system. The seal water system permits water versus air testing of the valves in the penetration (air tests were only required for the MOV stems and bonnets).

. FWLCS consists of two redundant seal water sources which inject into the Feedwater lines between the valves. The line between the valves is currently assumed to fill with water and pressurize within = 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, based on a 20-minute control room operator manual action.

. The check valves are seat leak tested with water (hydrostatic test) to meet Technical Specification surveillance requirements (19 gallons per minute (gpm) total, distributed amongst the 19 water tested penetrations). Per 10 CFR 50 Appendix J, due to the existence of the water seal system, the leakage past the check valves is not added into the leakage that is included in the licensing basis radiological dose consequence analysis.

. The seats of the third valves (the MOVs) are tested with water; results are added into the Technical Specification 5.5.2

  • Primary Coolant Sources Outside Containment" Program (5 gallons per hour (gph) total field limit for the systems outside containment that could contain raceoactive fluids after an accident. The licensing basis radiological consequence analysis for the design basis loss-of-coolant accident includes the dose contribution from this liquid leakage.

. As noted in the above bullets and explained in greater detail in the remainder of this attachment, the current licensing basis dose analysis places reliance on closure of the third (motor-operated gate) valves. These are the valves that provide the high integrity containment isolation for the Feedwater lines.

PART 11. Description Of Why The Feedwater Penetration isolation Methods Are Being improved e improve the closure provisions for the third (gate) valves. [As noted above, the existing licensing basis places reliance on closure of the third (gate) valves. It is desired to improve the closure capability of these valves.]

. Improve the reliability of the water seal provisions on the Feedwater line. [The current FWLCS is a manually initiated system, which uses the weight of the inboard and/or the outboard piston lift check valve discs to allow water level (and pressure) to build up in the Feedwater line to a level that would cover the seat / preclude containment air leakage. The difficulty experienced over the past several outages has been with the as-found leakage test results for the check valves. Most notably, this has been with the non-Technical Specification required leakage limit imposed by the PNPP USAR. This USAR limit is imposed to ensure the lines would be able to be filled with water within approximately one hour. A change to the USAR, made after NRC approval of the initiallicensing basis, documents this more restrictive limit (more restrictive than the 19 gpm Technical

. . -~ _. - . . - _ - - -

Attachment 1 PY-CEl/NRR-2322L Page 5 of 26 Specification hydrostatic test total). The USAR requires each feedwater valve to leak less than 1 gpm. This was determined appropriate to ensure the line fill-time calculation assumptions would be met. It is desired to implement changes to improve the method used i to obtain the water seal on the Feedwater line.)

. . Reduce the costs and radiological dose incurred in maintaining the water seal method for the Feedwater lines. [ Dismantling of the check valves and polishing of the seats to meet the USAR fill-time" leak requirement of 1 gpm resulted in over 5 Rem of dose to plant workers during the sixth refueling outage, and cost approximately $880,000 to complete.]  ;

The proposed Feedwater Penetration configuration described in Parts ill, IV and Vi below will ensure that the FWLCS would be active and providing a water seal on the penetration within the

=1 hour time frame originally discussed with the NRC.

PART ll1. Brief Summary of Proposed improved Feedwater Penetration Configuration

. The FWLCS would remain a manually initiated system, but rather than attempting to fill the large piping volumes between the valves, the two redundant FWLCS lines would be routed to the bonnet of the existing third motor operated gate valve in each Feedwater line. These valves are already assumed to be successfully closed by the operator after the start of the event. Once the FWLCS is lined up, one of the redundant pumps would be aligned to the valves to provide the water seal to the penetration much faster than using the former technique of filling the entire line. The gate valve bonnet and seat areas would begin to fill and pressurize when the seal water reaches the valve, and the seal would be established within several minutes.

Division 1 FWLCS _i [

INBOARD OUTBOARD  ! ViT~\

cp L map Division 2 g FWLCS Y p~gj: I

.h a

I

\ A \M b s  !

Mh#l_

s_i II d 5 E _BQ{ h[_h/ Steam N27-F559 B21-F032 B21E065 ,

b Tunnel 4 41 L Drywell Containment f[ RWCU Return line (break-excluded, leads back to Containment) i G33-F052 - 5 .

i RHR Shutdown Cooling Return line

. t e L _k E15-F050

_x____r E12-F053 e Although the current licensing basis already assumes that the third valve will be remote-manually closed by the control room operator following a loss-of-coolant-accident (LOCA) to provide the long term, high integrity leakage protection, an even higher confidence level on closure of these valves will be provided by a design change and revisions to plant emergency procedures. The procedures will direct operators to implement an alternate

!- division of electrical power to the gate valves, in the event that the valves normal power l

Attachment 1 PY-CEl/NRR-2322L Page 6 of 26 supply is lost. An alternate division of power such as this is not a new concept; the operators already receive training on a similar arrangement that is utilized in the PNPP licensing basis for the Station Blackout event. The capability to provide power from Division 3 will be a permanent design modification, but physical and electrical separation between Divisions 1 and 3 will be maintained by employing two features:

1 Normally open, fused disconnect switches at both ends of the circuit, and '

2 Fuses normally stored out of the circuit.

. The water seal provided to the disc / seat of the third (gate) valve would provide for a water test on these seats, at 21.1 P.. One method would be to initiate FWLCS to the bonnet, and measure leakage past the seat by collecting the leakage in the line outboard of the gate valves. Water leakage past the gate valve seats would continue to be added into the Primary Coolant Sources Outside of Containment Program. This Program is in place to protect the assumptions of the radiological dose calculations for PNPP. This is how the water leakage from the Feedwater penetrations is currently addressed in the PNPP dose ,

calculations.

  • Due to the injection of the seal water into the stem / bonnet area of the gate valves, the appropriate test for stem / bonnet leakage is to identify any water leakage outside of the piping system, and eliminate it. This test will be performed during the system walkdowns performed per the Technicti Specification 5.5.2 Primary Coolant Sources Outside Containment Program, at pressures > 1000 psig. This water test approach for the stem / bonnet will ensure post-accident leakage outside of this Class 2 Feedwater piping is eliminated, and will not adversely affect the PNPP radiological dose calculations.

. The check valves would no longer need to maintain a 1 gpm leakage limit, since the lines would no longer need to be filled with water to make the FWLCS function. It would still be necessary to ensure that the check valves are exercised closed so that significant flow from a Feedwater line break outside of the containment could be prevented. This is the ASME (American Society of Mechanical Engineers) Code Class 1 function of the valves. As noted in Generic Letter (GL) 89-04 Position 3 "Back Flow Testing of Check Valves", many plants were not performing back flow testing of any kind prior to 1989 on check valves that perform a safety function in the closed position to prevent reversed flow. Main Feedwater check valves were listed as an example of such valves. The GL noted that tests on check valves that perform a safety function in the closed position to prevent reversed flow should be performed. " Category C" tests on such " safety function check valves" were described as '

proving that the disc closes on its seat. An example method discussed for such safety function Category C tests is a visual observation. Upon implementation of this amendment, the PNPP Feedwater check valve closure function will be verified by an inspection of the valve internals at an appropriate frequency as determined by the Inservice Testing Program (ISTP). The design change will incorporate new taps off of the line adjacent to the check valves so that this necessary inspection can be completed (for example, by using boroscopic inspections). The check valves would be removed from the hydrostatic testing program, as such additional testing is not necessary to ensure their closure capabilities to prevent significant flow following a postulated Feedwater line break outside containment.

Hydrostatic leak tests of the check valves are also not necessary to address the radiological dose calculations (since the feedwater line high integrity le 'kage barrier is provided by the gate valves). This is addressed in more detail in Section it , oelow.

. Testing of the Reactor Water Cleanup Return line and the RHR Shutdown Cooling Return Line, which both return water to the reactor vessel through the Feedwater process line, is also addressed in detail in Section IV, below.

--_-. ___ - - - _. -. . ~ .

Attachment 1 PY-CEl/NRR-2322L Page 7 of 26 PART IV. Summary of Existing Licensing Basis versus Proposed Licensing Basis in summary, the Feedwater lines (and the branch lines that return back into the Feedwater lines) connect back to the Reactor Coolant Pressure Boundary (RCPB), and therefore the applicable General Design Criterion is GDC 55 for the valves in Penetrations P121 and P414.

Feedwater penetrations are considered unioue, and they comply with GDC 55 using the "other defined basis" words in the GDC ("unless it can be demonstrated that the containment isolation provisions . . are acceptable on some other defined basis"). The " degree of conformance" positions which describe the "other defined basis" for PNPP are described below and in the USAR markups in Attachment 4 to this letter.

Additional details and references to docketed letters /the NRC Safety Evaluation Report (SER)/Supplementa! SERs (SSERs)/ applicable industry guidelines for the following items are provided in Section V below, for reviewers information.

Summary of Existina Licensina Basis Summary of Proposed Licensina Basis (see Section V for details) (see UsAR markups in Att. 4 for addt'l details

1. FWLCS is manually initiated. 1. Remains unchanged.
2. FWLCS is effective within approximately one 2. Remains unchanged.

hour after the onset of a LOCA.

3. Check Valve design: 3. Remains unchanged.

. Slow close to prevent waterhammer.

. Designed to check reverse flow of water,  !

while not impeding normal flow. *

4. Check Valve safety-related functions: 4. Check Valve safety-related function:

e isolation of significant flow from a . Isolation of significant flow from a Feedwater line break outside containment. Feedwater line break outside

. Provide barrier to allow FWLCS to fill containment.

Feedwater line within approximately one hour after a LOCA. >

5. Third (gate) Valve design: 5. Third (gate) Valve design remains unchanged, except:

. Borg Warner Co. Motor-opere'ed gate . FWLCS seal water would be injected valve. into the valve bonnet through an

. Flexible wedge disc design, which has a existing stem leakoff line to seal the groove around the circumference of the stem, bonnet, and flex-wedge seat with wedge, between the two seating surfaces. water. The water flows into the groove  ;

between the seats and seals the pipe.  !

. Limitorque Company Actuator, powered . Third (gate) Valve actuator could be i from Division 1 powered from Division 3 if Division 1 is i not available. This is similar to the

. ASME Class 2 approach used in the event of a Station Blackout (SBO), where Division 2 is j backed up by Division 3 (already proceduralized)). Following this design change, these Feedwater gate valves could also be closed after an SBO, if

determined necessary by the operators.

i

Attachment 1 PY-CEl/NRR-2322L Page 8 of 26 Summary of Existina Licensina Basis Summary of Proposed Licensina Basis (See Section V for details) (See uSAR markups in Att. 4 for addt'l details

6. Third (gate) Valve safety-related functions: 6. Third (gate) Valve safety-related functions:

. Long-term low water leakage (high integrity) . Long-term low water leakage (high containment isolation valve, closed to integrity) containment isolation valve, i maintain the radiological dose calculation closed to maintain the radiological dose assumptions. calculation assumptions.

. Provide barrier to allow FWLCS to fill . Provide barrier to allow FWLCS to Feedwater lines within approximately one provide a water seat on the gate valve's hour after a LOCA. flex-wedge seat within approximately one hour after a LOCA.

7. As noted in Supplement 7 to the PNPP Safety 7. Conclusions remain unchanged.

Evaluation Report (SSER 7), the Feedwater piping outboard (away from containment) of the third (gate) valve is assumed to remain intact for at least the first hour post-LOCA. The piping is assumed to remain intact for a sufficient length of time for the operator to remotely close the third (gate) valve. The intact Feedwater piping prevents leakage from containment due to

. Operation of Feedwater it it remains available following the event.

. High temperature and pressures in the Feedwater piping, for at least the first hour post-LOCA, if Feedwater is not available following the event. This is supported by RETRAN analysis.

The acknowledgment in the approval of the Feedwater penetration as-built configuration (SSER 7) that the Feedwater piping would remain intact until the third (gate) valve can be successfully closed by the operator is important, since the gate valves are the long-term, high integrity Feedwater line containment isolation valves which are assumed closed in the radiological dose calculations.

8. The FWLCS consists of two redundant pumps 8. Remains the same, except that:

and piping runs, supplying water to seal the e injection for both subsystems is into the Feedwater lines for at least 30 days post- bonnets / seats of the existing Third LOCA. Injection is into the Feedwater pipe (gate) Valves on both lines. Both between the inboard check and the outboard FWLCS subsystems would be hard-gate valve. The Division 1 system (outboard) piped to the gate valve on each line.

injects between the outboard check valve and . The operator could remote manually the Third Valve, and the Division 2 system initiate either subsystem to provide the (inboard) injects between the two check valves. water seal on both gate valves.

The Residual Heat Removal (RHR) and Low

, Pressure Core Spray (LPCS) waterleg pumps [ Note: Consideration is being given to a are used to provide the water for FWLCS. future design change to supply a non-radiologically contaminated water source to

Attachment 1 PY-CEl/NRR-2322L Page 9 of 26 Summary of Existina Licensina Basis Summary of Proposed Licensina Basis

[s,eo Section V for details) (see UsAR markups in Att. 4 for addt'l details the bonnets of the valves. This would preclude the need to add the leakage past the Third Valves into the " Primary Coolant Sources Outside Containment Program"

, (further discussion of this test program for the Third (gate) Valves is provided in severalitems below). Such a future change is anticipated to be able to be implemented under the prc. Dions of 10 CFR 50.59.]

9. Operator action from the Control Room to close 9. Operator acts,. irom the Control Room to the third (gate) valve and initiate FWLCS close the third valve and initiate FWLCS injection needs to begin within =20 minutes, in injection is still assumed to begin within =20 order to fill the line within "approximately one minutes, but it can be delayed to the hour" post-LOCA (since initiation is estimated at = 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> point without adverse impact if approximately the 20 minute point, and fill times Division 1 power is available, since the were estimated to range from 36 to 44 water seal on the gate valve bonnet / seat is minutes). obtained within several minutes of initiating the FWLCS. This improves the probability of completion of the action (" operator error" probability is reduced - further information on this is provided in Section VI). If Division 1 power is not available, Division 3 power to the gate valves can be established, which will enable FWLCS to still be established within the "approximately one hour" time frame in the current licensing basis. An evaluation of the operator action per ANSl/ANS 58.8-1984 guidelines is being performed to determine the actual time and dose that would be involved with this action. This will be submitted to the NRC when completed.
10. Third (gate) valve was determined to have 10. Due to the injection of the seal water into potential for stem and bonnet air leakage. A the bonnet of the valve, air leakage will not requirement was added into the original be a concern. Stem and bonnet water Technical Specifications requiring the gate leakage will be checked and any leakage valve stem and bonnet to be Type C pneumatic will be eliminated (this will be controlled by (air) tested and the results added into the TS 5.5.2 " Primary Coolant Sources secondary containment bypass leakage totals. Outside Containment Program" (see further discussion below.)). This leakage elimination will be ensured through system walkdowns per the Program at > 1000 psig, with the gate valves in the close'd position.
11. Third (gate) valve through-seat leakage is not 11. Due to the water seal provided by the high considered to be part of the secondary integrity Third Valves, the gate valve seat containment bypass leakage, but at PNPP, leakage will continue to be checked by a gate valve through-seat leakage is addressed, water test conducted at 21.1 P., and the as part of the NUREG-0737 Ill.D.1.1 Primary results will continue to be added into the

Attachment 1 l PY-CEl/NRR-2322L l Page 10 of 26 Summary of Existina Licensina Basis Summary of Proposed Licensina Basis (See usAR markups in Att. 4 for addt'l details

[see Section V for details) l Coolant Leakage Outside Containment Primary Coolant Sources Outside Program. This program is currently included in Containment Program totals (Technical i

Technical Specifications as TS 5.5.2 " Primary Specification 5.5.2). A ten (10) gallon per Coolant Sources Outside Containment hour leakage rate assumption is already Program". included in the current licensing basis LOCA radiological dose calculations for this Based on the requirements of 10 CFR 50 type of leakage, while the field limit is still Appendix J, Options A and B, valves such as set at 5 gph. This doubling (10 gph in the ,

the check valves and the gate valves, which are calculations, 5 gph in the field) is consistent current!y licensed to be sealed with fluid from a with Standard Review Plan guid.ince (SRP seal system, may be excluded when 15.6.5 Appendix B " Radiological determining combined leakage rates, i.e., their Consequences of a Design Basis Loss-of-leakage is not added into the radiological dose Coolant Accident: Leakage From calculations. However, since FWLCS uses Engineered Safety Feature [ESF) potentially contaminated suppression pool Components Outside Containment"). The water, it was considered prudent to address 5 pph and 10 gph limits are specified in through-seat leakage, at least for the high P;PP USAR Section 15.6.5.5.1.2.b "ESF integrity Third Valves (the gate valves), in the Leakage".

calculations. The gate valves leakage was specifically addressed in several stages during (Note: the Revised Accident Source Term the licensing process. The original commitment radiological calculations submitted to the in an August 30,1985 letter was to include seat NRC in support of another pending license leakage through the motor operated gate amendment request assumed a 15 gallon valves into the NUREG-0737 Ill.D.1.1 Primary per hour primary coolant outside Coolant Leakage Outside Containment containment leakage rate.)

Program, and ensure it remained less than the water bypass allowable limit (5 gallons per Although the Feedwater lines would still be hour (gph) field limit for PNPP). This ensured considered to be "hydrostatically tested the water leakage would be limited to within the lines" because water tests are being LOCA radiological calculations. Due solely to pe; armed on the Third (gate) valves, the an NRC concern on the gate valve stem and leakage past these containment isolation bonnet air leakage (see item 10 above), and vWves need not be double counted in two the inability at that point in time (initial plant separate hydrostatic test programs.

licensing) to air test the stem / bonnet separately The efore, a Note is being added to the from the seat, a subsequent letter noted that Technical Specification Surveillance l the gate valves would be tested with air, and Requirement for hydrostatic testing of lines the leakage for these gate vales would be (SR 3.6.1.3.11). The Note explains that the included in the secondary cor nment air Feedwater lines are excluded from this bypass totals. This ensured the stem / bonnet particular program, and the Bases explain air leakage would be limited to within the LOCA that this is because the gate valve water radiological calculations. Subsequently, a leakage is controlled by the Primary I

method was developed for completing the air Coolant Sources Outside Containment test on the gate valve stem and bonnet Program (TS 5.5.2). Also, as part of the separately from the valve seat, and now, as implementation of this amendment, the field originally committed, the seats of the gate limit for leakage will be added into the valves on each line are tested with water and Bases discussion for the new Note. This is the measured leakage is added into the being done to literally comply with Section 6 Primary Coolant Sources Outside Containment " General Requirements" of the Nuclear

Attachment 1 PY-CEl/NRR-2322L I Page 11 of 26 {

i l

Summary of Existina Licensina Basis Summary of Proposed Licensina Basis (See USAR markups in Att. 4 for addt'l details [

{See Section V for details)

Program totals (see Technical Specification Energy institute (NEI) guideline on  ;

5.5.2). Appendix J Option B leak rate testing, NEl e 94-01 " Industry Guideline For implementing i Performance-Based Option of l

10 CFR Part 50, Appendix J".

12. The Inservice Testing Program for valves 12. Remains unchanged.

' (Technical Specification 5.5.6) includes stroke

. time testing of the Third (gate) Valves on a Cold Shutdown frequency to help ensure their reliability.

13. The ongoing Motor-Operated Valve (MOV) test 13. Remains unchanged.

program conducted per commitmen's to  !

~

Generic Letter 96-05 " Periodic Verification Of Design-Basis Capability Of Safety-Related Power-Operated Valves" includes the Third l Valves. It includes checks of dynamic thrust l

, and torque requirements and trending of results to help ensure the reliability of the Third Valves.

14. The Check Valve stem is internal to the bonnet, 14. Remains unchanged. l and the bonnet is not considered to be an air leakage pathway and does not require  :

t Appendix J Type C testing.

15. Testing of the seats of the Check Valves in 15. Generic Letter (GL) 89-04 Position 3 "Back - '

each of the lines is currently performed by a Flow Testing of Check Valves" noted that reverse flow hydrostatic (water) leak rate test. tests on check valves that perform a safety '

The results of these tests are then added into function in the closed position to prevent .

i

. the Technicat Specification hydrostatic leak test reversed flow should be performed. _

total, and compared to an acceptance criteria of " Category C" tests on such " safety function 19 gallons per minute (There are more than 19 check valves" were described as neeaing to l

- valves in the program, but the PNPP _ prove that the disc closes on its seat. An

acceptance criterion is conservatively based on example method discussed for such safety a total equal to "the number of penetration - function Category C tests is a visual

' pathways in the program" (multiplied by observation. It is proposed that the "1 gpm") rather than multiplying by the number Feedwater Check Valves be Category C of valves - see Tech Spec SR 3.6.1.3.11.) The tested for their safety function by -

reason that the check valves are included in performance of a visualinspection of the

. this Technical Specifict' ion hydrostatic test valve intemals at an appropriate frequency

' program, with its limit c,. :9 gpm for the valves as determined by the inservice Testing in the program, is because of Appendix J Program (ISTP). A tap would be added requirements. Appendix J (and the more recent adjacent to each check valve to permit '

_ guidance endorsed by Option B to App. J, i.e., visualinspections of the valves to verify NEl 94-01) requires that valves that are sealed proper closure. This inspection would o

with fluid from a seal system should have constitute the " exercise closed (EC)" test in  !

l' the ISTP. The " exercise open (EO)" testing l leakage rates that do not exceed those specified in the technical specifications or ' would remain the same, i.e., the valves associated bases". These seal water system pass proper flow during plant operation. l leakage rates however, are not required to be l i -

I

Attachment 1 i

PY-CEl/NRR-2322L

( Page 12 of 26 i

I Summary of Existina Licensina Basis Summary of Proposed Licensina Basis (see USAR markups in Att. 4 for addt'l details LSee Section V for details) added into the containment leakage rate totals Hydrostatic leak rate testing would not be  ;

' which factor into the radiological dose required on these check valves since:

calculations. . The check valves Class 1 function would be verified through the " exercise in addition to the 19 gpm leakage limit closed" test method (the internal visual discussed above, a more restrictive USAR limit inspection). Hydrostatic leak testing is

'is placed on the leak rate of each check valve not considered necessary to ensure the in the feedwater line, to support the check valves closure capabilities to assumptions of the FWLCS line " fill-time" prevent significant flow following a calculations. This USAR limit is 1 gpm. This postulated Feedwater line break outside limit was added into the USAR after NRC containment. ,

approval of the initial licensing basis. . The FWLCS function would be provided  !

by closure of the Third Valves and These leakage acceptance criteria are the initiation of FWLCS to the gate valve values that have proven challenging to meet discs within ~ one hour following a during as-found testing of the check valves over LOCA inside the containment. During  ;

the last several refueling outages. the first hour, until the Third Valves are closed, leakage past the Check Valves is assumed not to occur, since the NRC has accepted that the Feedwater piping remains intact until the operator remotely isolates the Third Valve, and  ;

I that the Feedwater piping would preclude leakage during that period.  !

. The FWLCS function would no longer require the check valves to be leak tight to within 1 gpm, since the Feedwater lines would no longer have to be filled with water, i.e., the rerouting of the FWLCS water to the gate valve bonnets l makes the "line fill-time" moot (fill-time was the basis for the 1 gpm limit).

. The radiological dose calculations already depend on successful closure of the third (gate) valves to limit releases following a postulated LOCA severe enough to damage fuel. This is specified in the existing licensing basis.

The check valves previou. " seal water" function will no longer exist. Therefore, the third (gate) valves will continue to be classified as " containment isolation valves", but the check valves will not.

For the above reasons, a new Note is added to Technical Specification SR 3.6.1.3.11 to clarify that the hydrostatic test program does not apply to the Feedwater lines.

Attachment 1 PY-CEl/NRR-2322L Page 13 of 26 i Summary of Existina Licensina Basis Summary of Proposed Licensina Basis (See Section V for details) (see UsAR markups in Att. 4 for addt'l details

16. The American Society of Mechanical Engineers 16. It is proposed that the Code Class (ASME ) Code Class 1 boundary extends out to boundaries would remain the same.

and includes the second (outboard) check valve, consistent with the guidance in Regulatory Guide 1.26 " Quality Group

~ Classifications And Standards For Water ,

Steam , And Radioactive-Waste-Containing Components Of Nuclear Power Plants",

including Position C.1.c. This constitutes the Reactor Coolant Pressure Boundary (RCPB) for the Feedwater penetrations. The RCPB is addressed by General Design Criterion (GDC) 14 " Reactor Coolant Pressure Boundary".

l Since the Feedwater lines at PNPP have the third shutoff valves (the gate valves), the ASME 1 Code Class 2 boundary extends out from the second check valve to and including the third  ;

valve in each Feedwater line, as discussed in

. Position C.1.c of Regulatory Guide 1.26. This .

constitutes the " Reactor Coolant System boundary (RCS)" for the Feedwater lines, as ,

described in the 10 CFR 50.2 definition of the RCPB. The RCS is addressed by GDC 15 l

" Reactor Coolant System Design". l The Reactor Water Cleanup (RWCU) and RHR l branch lines that tie in to the main process pipe _l (the Feedwater line) are also Code Class 2, as j

explained in USAR Table 3.2-1 " Equipment '

Classification" and the associated Note 8 to the table.

17. There is a branch line off of the Feedwater line 17. Once the FWLCS is rerouted to the that taps in between the outboard check valve stem / bonnets of the third valve rather than and the Third Valve (see Figure 1). This line into the Feedwater pipe, the branch lines off provides the retum pathway for RWCU and of the Feedwater line will need a different RHR shutdown cooling water to the reactor licensing basis for leakage' mitigation.

vessel. These branch lines currently get sealed

- due to operation of one of the Feedwater The RHR branch line off of the Feedwater Leakage Control subsystems. line will be treated as a closed system outside of containment, similar to the lines discussed in Note 4 to USAR Table 6.2-33 and Note 7 to Table 6.2-40. These Notes explain why leakage is not considered to be i i l bypass leakage. A safety-related globe valve (1E12-F053A/B) in this branch line  :

will be treated as a high integrity i containment isolation valve, similar to the

Attachment 1 PY-CEl/NRR-2322L Page 14 of 26 -

Summary of Existina Licensina Basis Summary of Proposed Licensina Basis (See Section V for details) (See USAR markups in Att. 4 for addt'l details Feedwater gate valves. The 1E12-F053A/B ,

valves will be added to the containment isolation valve listings. These valves meet the qualifications of a containment isolation valve. An air test will be performed on 1E12-F053A/B, and the air leakage will be added into the Type C totals and limited by 0.60 L.. Also, the leakage from the F053 valves will be added into the Type A Integrated Leak Rate Test (ILRT), since the Feedwater penetrations will not be drained during the ILRT. Leakage from the systems listed in USAR Notes 4 and 7 as " closed" are controlled by the Primary Coolant Sources Outside of Containment Program, as described in the Notes. Thus, this RHR branch pathyray would consist of an airleak rate tested containment isolation valve and a closed system outside of containment. In addition, a high-to-low-pressure interface water test is performed on the E12-F053 globe valve and the check valve inboard of the F053 (E12-F050A/B) (see the Figures) in accordance with ASME Section XI.

These valves are tested to water leakage limits of s 5 gpm. Although these valves will continue to receive this high-to-low pressure test, they do not meet the literal i definition of Pressure isolation Valves (PlVs) since they connect to the Reactor Coolant System (GDC 15) versus the Reactor Coolant Pressure Boundary (GDC 14), and therefore they will not be added to the PlV listing currently contained in Operational Requirements Manual (ORM)

Attachment 3.

A Reactor Water Cleanup (RWCU) branch line also exists. This line returns the filtered RWCU water to the Reactor Vessel via the Feedwater lines. The piping " outboard" of I the RWCU branch line check valve (1G33-F052A/B) leads directly back to containment penetration P132, and is ASME Code Class 2, Seismic Category 1,- .

I protected from pipe whip, missiles and jet forces, and analyzed for " break exclusion".

This closed system outside containment m

_ _ _ - __. .- _ m _ .-. _._._ _..- _ _

Attachment 1 PY-CEl/NRR-2322L.

Page 15 cf 26 I i Summary of Existina Licensina Basis Summary of Proposed Licensina Basis i (See Section V for details) (See UsAR markups in Att. 4 for addt'l details [

contains only mechanical joints, including

the packing on the outboard containment  :

isolation valve (1G33-F039) for Penetration  :

P132. This outboard valve, including the ~

stem and bonnet, is already part of the air t

leak rate test program. The remainder of  !

the RWCU line between the Feedwater line  ;

! and Penetration P132 will be added to the i l Technical Specification 5.5.2 Primary  ;

Coolant Sources Outside Containment i Program, with a specific leakage .

acceptance limit of zero (0) leakage when i tested at RWCU operating pressures

(>1000 psig). .This obviates the need to  :

add the RWCU branch line check valves l (1G33-F052A/B) into a leak rate testing program, since zero water leakage outside  ;

the lines when operating at over 1000 psig ensures that there will be no air leakage l from those mechanical joints at P. (7.8 psig i for PNPP). This approach meets Branch  :

Technical Position CSB 6-3 " Determination -

l of Byp' ass Leakage Paths in Dual Containment Plants", item B.9. Item B 9  !

i? specifies the criteria for when a closed i l

system may be used as a leakage l boundary to preclude bypass leakage. This j approach is also substantiated by PNPP  ;

leak test program results, where joints that  ;

showed water leakage at full system j operating pressures, did not exhibit l measurable air leakage when tested at P..

The piping of each FWLC subsystem which will connect to the bonnets / seats of the gate  :

I valves contains two currently existing isolation valves. These valves receive a b high-to-low pressure interface water test

} since they connect back to the RHR/LPCS L, waterleg pumps. These tests will continue j l

l' to be performed. Although these valves will continue to receive this test, they also do not meet the definition of PlVs and will not L be added to the list in ORM Attachment 3.

18. Intersystem leakage is acceptably addressed. 18. Intersystem leakage continues to be acceptably addressed.

. During normal plant operation, the Feedwater system is operated at pressures higher than Normal operation of Feedwater remains i

n u - . . _ . _ _ . . - _. ._.

Attachment 1 PY-CEl/NRR-2322L Page 16 of 26 Summary of Existina Licensinn Basis Summary of Proposed Licensinn Basis (see Sectior, V for details) [see UsAR markups in Att. 4 for addt'l details RPV pressures, so that flow is into the reactor. unchanged.

If Feedwater system flow into the reactor is shut When Feedwater flow into the reactor is off entirely, the Feedwater check valves serve shut off, the check valves will continue to to prevent significant reverse flow back into the perform their safety function. As discussed Feedwater piping. When Feedwater flow into in Generic Letter 89-04, the periodic ISTP the reactor has been stopped, plant Category C visualinspection of the check procedures / instructions direct that the high valve internals will continue to show that the integrity third (gate) valves also be closed to disc is in the closed position on its seat, in provide additionalisolation capability. order to perform its safety function to prevent significant reverse flow back into the Feedwater piping. A design basis unisolable LOCA does not exist in such a situation. The other vessel water injection systems will provide sufficient makeup capacity to prevent fuel damage. When Feedwater flow into the reactor has been stopped, plant procedures / instructions will continue to direct that the high integrity third (gate) valves also be closed to provide additionalisolation capability.

19. Technical Specification 3.6.1.8 "Feedwater 19. Remains unchanged.

Leakage Control System (FWLCS)" ensures the waterleg pumps operate properly, on a 31 day Frequency.

PART V. Details of Existing Licensing Basis / References The above statements about the existing licensing basis evolved as a result of the " question and response"(O&R) period of the license application process. Synopses of some of the relevant correspondence, in chronological order, are provided later in this section.

The Feedwater penetrations are unique since the isolation valves are not designed to automatically close even though the Feedwater system is non-safety-releted. During a design basis accident, it is desirable to maintain reactor coolant make-up from all potential nources and at such the Feedwater containment isolation valves (the gate valves) do no! receive an automatic closure signal. For these valves to close, the operator must first d@rmine that continued make-up from the Feedwater is unnecessary, and then initiate remote nenual closure. However, since it is also necessary for the Feedwater penetrations to autommically isolate in response to a Feedwater line break outside of containment, the penetration configuration includes two check valves in series provided to close to prevent significant reverse flow. Industry guidance documents such as ANS 56.2/N271-76," Containment Isolation Provisions for Fluid Systems" conclude that " greater safety is assured by maintaining a feedwater supply to the reactor" as opposed to automatically isolating the penetration. The most definitive PNPP licensing basis / docketed statements regarding the above position on

" greater safety" due to maintaining Feedwater flow to the reactor vessel can be found in letter PY-CEl/NRR-0295L,

Subject:

"Feedwater Isolation Valve Testing (Question 480.50)," dated

Attachment 1 PY-CEl/NRR-2322L Page 17 of 26 August 30,1985. That August 30,1985 letter and Supplement 7 to the NRC Safety Evaluation Report (SSER 7) provide the best descriptions of the overall licensing basis for the Feedwater penetrations, with SSER 7 being the most important. A summary of the correspondence leading up to that letter and the subsequent NRC approval of the as-built Feedwater penetration configuration in SSER 7 is:

. The NRC originally raised generic secondary containment bypass leakage path concerns in several Questions that were later summarized in the PNPP Safety Evaluation Report (SER), i dated May 1982, in Section 6.2.1.9 "Seconoary Containment" and Section 6.2.3 l

" Containment isolation System." The staff felt that the Cleveland Electric illuminating l Company (CEI), the licensee, had not yet provided enough justification for eliminating consideration of leakage from lines that penetrate the primary and secondary containment j (which could be considered potential bypass leakage paths). The staff also noted, as provided by General Design Criteria (GDC) 55 and 56, that there are containment  !

penetrations whose isolation provisions do not have to satisfy the explicit requirements of the General Design Criteria, but can be accepted on some other defined basis. At that time the NRC felt that CEI had "not correlated all the design deviations from the explicit requirements of the General Design Criteria to the justifications for such deviations."

. CEl's response to NRC Question 480.45, presented to the NRC via a letter dated April 26,1982, was that the feedwater penetrations had been excluded as potential bypass leakage paths. CEI stated that the feedwater system has a dedicated leakage control system which pressurizes the Feedwater line between the inboard check valve and outboard gate valve. CEI also stated that the FWLC subsystems meet single failure criteria, are missile protected, Seismic Category 1, Safety Class 2 and have a temperature and pressure rating in excess of that for the Containment.

1

. CEl's response to NRC Question 480.48, presented to the NRC via a letter dated l April 26,1982, provided additiorui information regarding CEl's Containment Leakage ,

Testing Program. CEI informed the NRC that:

" Isolation valves, pressurized by a water seal system, will be Type C tested with water and the leakage excluded in combined leakage rate, consistent with the Type C test acceptance criteria in 10 CFR 50, Appendix J."

'The feedwater lines are Type C tested with water and the leakage is not included in the 0.60 La. This is consistent with 10 CFR 50, Appendix J acceptance criteria since a dedicated Feedwater Leakege Control system is provided. Refer to response to 480.45 (NOTE 10 to [FSAR] Table 6.2-33) and new FSAR Section 6.9."

. The deviations for the Feedwater Lines were accepted in PNPP hpplemental Safety Evaluation Report (SSER) No. 2, Sections 6.2.1.9 and 6.2.6, dated January 1983. The basis for the acceptance was the letter dated April 26,1982 (discussed above) wWcn addressed the issue and provided the criteria the applicant used to determine and assess potential bypass leakage paths (note that there is a typographical error in SSER 2 Section 6.2.1.9 where it references an incorrect CEI letter date, this was corrected in SSER 5, Arp.

G). These criteria showed that the penetration lines in question were excluded because they contain physical barriers or design provisions (e.g., the lines contain water seals, they involve closed Category I piping systems, and/or leakage controls are provided in the design) that will effectively eliminate leakage. Where relied on to eliminate leakage, these

Attachment 1 PY-CEl/NRR-2322L Page 18 of 26 provisions are designed to (1) meet the single-f ailure criteria, (2) be missile protected, and (3) have a temperature and pressure rating in excess of that for containment. It was concluded in Section 6.2.1.9 of SSER 2 that the applicant provided sufficient justification to exclude the Feedwater lines as potential bypass leakage paths.

. In a letter from the NRC (B. J. Youngblood to M. R. Edelman) dated December 21,1983, the concern was raised that within the first hour the FWLCS would not yet have established a water seal and that air testing should be performed. This was defined as question l 480.50(a). The NRC was basing this quettion on their review of the Grand Gulf FWLCS design.

. Concerning NUREG-0737 Post-TMl Action item Ill.D.1.1 on Primary Coolant Leakage Outside Containment, letter PY-CEl/NRR-0237L, dated May 29,1985, provided the proposed PNPP " Leakage Surveillance and Preventive Maintenance Program". This Program was in response to License Condition 16. It committed to implementing a program to reduce leakage from systems outside of containment that would or could contain highly radioactive fluids during serious transients or accidents to a level as low as possible. This letter noted that the Feedwater Leakage Control System would be included in the Program, i

! e in letter PY-CEl/NRR-0259L,

Subject:

" Containment Bypass Leakage (Questions 480.49 -

l 480.51, License Condition 16)", dated July 10,1985, from CEl's Murray R. Edelman to NRC's B. J. Youngblood, CEI provided some additional information in response to testing with air or water. This letter, nowever, did not attempt to close the air vs. water test issue for the feedwater lines. In a number of places in Attachment 1 to the letter, it was stated i

that leakage through the Feedwater lines was still under evaluation.

l

(

l . Letter PY-CEl/NRR-0295L,

Subject:

"Feedwater Isolation Valve Testing (Question 480.50)",

dated August 30,1985, from CEI's Murray R. Edelman to NRC's B. J. Youngblood, provided the basis for NOT testing the penetration with air. This letter was provided in l

response to NRC's request to justify leak testing of the feedwater valves with water in lieu of air. At this time, CEI had already installed the FWLCS, and replacement check valves with metal seats, and therefore discussed the possibility of "backfit" in the cover letter, since the NRC had approved water testing (versus air testing) of the penetrations in SSER 2, dated January 1983. CEI also furnished the justification that the design was acceptable as is. This letter, together with the approval of the issue by the NRC in SSER 7, represents lL the most definitive basic for the Feedwater configuration.

l This letter does include a commitment to add the leakage through the Third valves (the motor operated Feedwater gate valves) into the Primary Coolant Sources Outside Containment leakage redoction program (NUREG-0737, item Ill.D.1.1). The commitment on page 2 of the Attachrnentwas as follows:

I "Anyleakage through the motor operated gate valve has been accounted for through NUREG 0737 testing and added to the water bypass allowable."

Some of the statements relevant to the current license amendment am as follows:

J "The attachment to this letter summarizes the redundant and independent means of keeping feedwaterpiping filled with waterpost-LOCA, and the results of the requested (by the NRC staff) analyses of the system response to a LOCA (RETRAN).

1

Attachment 1 PY-CEl/NRR-2322L Page 19 of 26

. "Following a LOCA, the FWLCS is manually initiated from the Control Room.

The operator first verifies feedwater unavailability through low feedwater pressure, then closes the outboard motor operated gate valves with the keylock switches, and opens the motor operated FWLCS valves from the Control Room.

Sealing wateris provided from the suppression pool via the RHR & LPCS Waterleg Pun'p[s]. Since the source of sealing wateris the suppression pool, a 30 day water supplyis assured.

"When the FWLCS is initiated following a LOCA, there should be no demand for keep-fill waterin the RHR and LPCS systems since these systems will be operating. Therefore, the Waterleg Pumps should be totally dedicated to provide sealing water to the FWLCS." ...

'In the case of a LOCA where the feedwaterlines remain water filled, static head pressure and the feedwatercheck valve disc weight force the feedwater check valves to close. Initiation of the FWLCS pressurizes the volumes between the inboard and outboard isolation check valves and between the outboard isolation 1

check valve and the motor operated gate valve.

'Since the waterleg pumps operate at a pressure higher than the static head pressure, leakage is into the Reactor Vessel.

'Any leakege through the motor operated gate valve has been accounted for through NUREG 0737 (Closed System Leak Testing) testing and added to the waterbypass allowable.

"In the case where the feedwaterlines do not remain completely water-filled, the feedwater system can be operated to ensure positive pressurization up to the gate valve, and thus leakage would be into the Reactor Vessel. Then FWLCS will be initiated and begin to fill the volumes between the inboard and outboard isolation check valves and between the outboard isolation check valve and motor operated gate valve. The weight of the check valve discs, and no upstream pressure, will force the check valves to close. When the volumes fill up, the  :

pressure willincrease uniilthe weight of the discis overcome. At this point, the disc willlift andleakage into the vessel will occur. As the pressure is relieved, i

the disc will re-seat untilpressure builds up again and the disc lifts. This process will continue throughout the duration of the LOCA event. ...' }

Following a LOCA event, "the feedwater system will not be completely drained since the system will be Intact and operating initially post-LOCK 1

"The Perry design includes a backup feedwater flow path through a motor-driven pump. When the turbine-driven feed pumps lose driving steam and trip on vessel

- level 2 post-LOCA, flow is automatically diverted through the motor-driven pump.

The motor-driven feed pump and/or the feedwater booster pumps will continue to pump waterinto containment post-LOCA."

  • 'The pumps will continue to operate for about 10 minutes before the feedwater boosterpumps in*p on low waterlevel. During this time, no extraction heating is available and ccid water from the condenser hotwellis being pumped into the vessel which cools down the feedwater and the piping. When feedwater flowis finally stopped, feedwater flashing is not expected to occur. Therefore, a

._ ._ _- _ _- . . . _ _ _ _ _ . .m Attachment 1 PY-CEUNRR-2322L Page 20 of 26 significant voiding of the piping is not expected."

. *the FW LCS willprovide an adequate seal within one hour following a LOCA. If a loss of off-site poweris assumed at this time, the FW-LCS will

, maintain the volume of water between the inboard isolation check valve and the l outboard motor operated gate valve. During this one hour, operation of the \

feedwater system will maintain a system pressure higher than the containment l pressure, thus assuring waterleakage into the vessel.

i RETRAN Analysis l

'Feedwater system response to a LOCA was analyzed using the RETRAN 02 MOD 3 computer code. These calculations were performed to determine certain response characteristics of the feedwater system and do not represent a realistic ,

basis for design. No substantive conclusions can be drawn conceming the reliability orintegrity of the feedwatersystem. These resultc only contribute to understanding characteristics of the system which affect post-LOCA leakage.

"The RETRAN analysis modeled the guillotine rupture of a feedwaterline inside i the drywell concurrent with a Loss of Offsite Power (loss of all feed pumps). The ,

modelincluded piping between the feed pumps and the break. Computer output shows that initial blowdown and boil-off result in depletion of all feedwater liquid in about 3 minutes after the LOCA. After the initial 3 minutes, stored heat in the  ;

pipe walls maintains vaporpressure in the piping higher than drywellpressure for i 20 minutes (resulting in net flow into the drywell). At 20 minutes post-LOCA, the  ;

1 FWLCS isinitiated.

'RETRAN results show that the piping is totally filled with liquid in 44 minutes l

after FWLCS initiation. The 44 minute time assumes a divisional failure in the i FWLCS. During the fill time, almost all flow is either into the drywell or into the volume being cooled by incoming FWLCS water.

'With the exception of a 1 minute period shortly after FWLCS initiation, there is 1 no leakage past the motor operated gate valves (B21-F065A & B) into the non-safety feedwaterpiping during the time the feedwaterlines fill with liquid."

... Based

" on the high Integrity of the piping and the ability to withstand single pump failures, there is a high degree of assurance that the Condensate and Feedwater systems will be available post-accident.

'The feedwater system from the reactor vessel through the outboard containment isolation check valve is classified as Safety Class 1, Seismic Category I. . From the outboard containment isolation check valve to the motor-operated gate valve the system is classified as Safety Class 2, Seismic Category I. . . All other i feedwater and condensate lines and pressure retaining parts are designod to l ANSI B31.1. AII stress levels in the piping are below the ANSI B31.1 allowables.

'Except for(Isnges at some equipment requiring removal for maintenance, all piping connections are welded. The systems are designed to be leak tight at normal operating pressures. Because operating pressures are much higher than the pressures existing in the piping poshLOCA when the reactor vesselis

l Attachment 1 i l PY-CEl/NRR-2322L I

! Page 21 of 26 depressurized, leakage out of the lines post-LOCA is not expected.

"All feedwater and condensate pumps have backup pumps. The feedwater boosterpump backup will automatically start on a trip of another boosterpump, ensuring positive pressure is maintained in the feedwaterlines.

l "The probability of a full circumferential!arge line break is extremely small. If a pipe failed it would crack or split, just enough to relieve stresses. This less severe failure would not result in a rapid depressurization of the feedwaterlines.

In such event, the piping would remain filled with water, then once the FWLC was l

initiated, water would be injected into an already water-filled volume.

"Even if an earthquake occurred concurrent with the LOCA and LOOP, the non- l safety piping would most likely maintain its integrity. A recent study of actual piping performance during earthquakes states that "The performance oflarge l and small bore welded steelpiping studied in several recent domestic and foreign earthquakes has been excellent. Very few, if any, failures have been

! reported due to inertialloads. (NUREG-1061 Vol. 2)"

+ in letter PY-CEl/NRR-0352 L,

Subject:

"Feedwater Isolation Valve Testing Question  !

(480.50)", dated September 20,1985, from CEl's Murray R. Edelman to NRC's l l '

B J. Youngblood, CEI stated that based on Letter PY-CEl/NRR-0295 L and discussions that l took place between CEI and PNPP personnel on September 17,1985, that the following l

resolutions were reached and would be reflected in the next amendment to the FSAR-

"The feedwater check valves (N27-F559A & B and B21-F032A & B) will be tested with water and only included in the Technical Specification limits for water leakage since through line leakage is not considered a potential bypass leakage path based on system design andintegrity." l l

This is consistent with 10 CFR 50 Appendix J (and the more recent guidance endorsed by i Option B to App. J, i.e., NEl 94-01) which note that primary containment barriers sealed  ;

l with fluid from a seal system do not have to be added into the 0.60 L. leakage test totals.

However, to satisfy a Staff concern regarding potential stem and bonnet leakage through l l l the mctor operated gate valves, CEI did commit to test the third (gate) valves with air to l

identify any air leakage from the stems / bonnets, and add any leakage to the 0.0504 L.

Technical Specification bypass leakage totals. Technical Specification changes to reflect these agreements with the Staff were committed to be incorporated prior to issuance of the Final Draft Specifications. 4

. The response to NRC Question 480.48 was subsequently revised and submitted to the 4 NRC under Amendment No. 21, dated September 30,1985. This provided details on the types of testing that would be performed on the feedwater isolation valves.

"The inboard and outboard check valves will be tested with water to a pressure'not less than 1.10 Pa. The outboard gate valves will be tested with air. Water leakage through the check valves is not included in the 0.60 La Type B and C test totals. Air leakage through the gate valves is included in the bypass leakage test total, even though through-seat leakage is not considered bypass leakage ~

i.e., although check valve leakage does not factor in to the dose calculations, the gate valve

Attachment 1 PY-CEl/NRR-2322L Page 22 of 26 stem and bonnet (and seat) air leakage would be factored in to the dose calculations (seat '

leakage was included simply because it was not considered possible at the time to determine air leakage from the stem and bonnet separately from seat leakage). A corresponding stem / bonnet requirement was put into the Technical Specification i Containment Isolation Valve table for valves B21-F065A and B which stated "During Type i C testing, valve stem and bonnet are checked for leaks as potential secondary containment bypass leakage paths."

)

e Portions of the positions discussed above from Letter PY-CEl/NRR-0295L dated l August 30,1985, were approved in Section 6.2.6 of Supplemental Safety Evaluation Report (SSER) No. 7, dated November 1985. Specifically, the NRC agreed that the FWLCS is a {

manually activated system, effective within approximately 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> after the onset of a LOCA, l that the Feedwater piping outboard of the third valve would remain intact and a water seal l would be maintained in the feedwater piping during the first hour after the LOCA (even if the j feedwater system becomes inoperable at the time of the LOCA), and that the water seal would remain until the control room operator remote-manually closes the third (motor operated gate) valve. The pertinent statements from SSER 7 are as follows:

"As reported in Section 6.2.6 of SSER No. 2, the staff concluded that the applicant's proposed leak testing program meets the requirements of Appendix J to 10 CFR 50 andis acceptable. However, the design details for the feedwater leakage control system (FWLCS) had not been reviewed before the issuance of SSER 2. The applicant stated that the FWLCS would provide post-accident sealing for both feedwaterlines thus precluding the need to perform " Type C" leak testing (Appendix J) of the feedwaterisolation valves with an air test medium. The feedwaterisolation valve arrangement consists of an inboard (Inside containment) check valve, an outboard (outside containment) check valve which is of the same design as the inboard valve, and an outboard remote manual motor-operatedIsolation valve. Thus, there are three isolation valves In series for each feedwaterline which the applicant has proposed to hydrostaticallyleak test."

"The FWLCS is a manually activated system and is estimated by the appIlcant to be effective within approximately 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> after the onset of a LOCA. Byletter dated August 30,1985 (M. R. Edelman to B. J. l Youngblood), the apr* : ant has provided sufficient information to l demonstrate a water r sal would also be maintained by the feedwater '

system outside the containment during the initial hour after a LOCA. That is, if the feedwater system becomes inoperable during the rapid vessel depressurization following a LOCA, the water within the feedwater piping will begin to flash into the dryweII. It is expected that a water seal would remain for a sufficient length of time following tire accident until the operator remotely Isolates the motor-operated valve. Thus, a water seal would exist in the piping beyond the motor-operated valve." ,

'On the basis of the above, the staff recognizes the existence of a water seal throughout the event to eliminate " valve through leakage." However, leakage can also occur through the valve's stem andpacking. To address this concem, the applicant provided a detailed description of the feedwaterisolation valves to demonstrate the lowprobability ofleakage occurring in this manner. The staff has reviewed the design of both the feedwater check valve and the motor operatedisolation valve. Regarding the check valve, the staff agrees with the

Attachment 1 PY-CEl/NRR-2322L Page 23 of 26 l applicant's assertion that the stem leakage is eliminated by a flanged and gasketed bonnet design arrangement. However, for the motor-operated valve, the staff finds that there is a potential for stem leakage. Therefore the staff will ,

require a Type C (Appendix J) pneumatic leakage test to be performed on each \

feed-water motor-operated valve. The check valves may be hydrostatically i tested because stem leakage may be considered incredible. . On the basis of }

conformance with the above, the staff considers this issue resolved.

PART VI. Details of The Design Change The Feedwater Leakage Control System (FWLCS) currently consists of two independent trains, one Division 2 powered train that furnishes sealing water to an inboard volume and a Division 1 train that furnishes sealing water to an outboard volume. The FWLCS system was designed and installed as a single failure proof, safety-related, seismically qualified system that was designed to withstand the dynamic effects of postulated piping failures in the steam tunnel including protection from internally generated missiles. The FWLCS piping that connects to the inboard and outboard Feedwater volumes is ASME Class 2.

The FWLCS, which is manually initiated, includes interlocks to ensure that the outboard FWLCS is not initiated without the Feedwater MOV being closed thereby preventing the inadvertent discharge of the suppression pool water to the Feedwater piping system. The inboard FWLCS system is not interlocked with the Feedwater MOV.

In the proposed design, both independent trains of the FWLCS will be routed to the bonnet area of the existing Feedwater MOV. To allow the FWLCS to seal the 20" gate valves, FWLCS will be supplied to an existing 1/2" threaded connection in the packing area of the valve bonnet.

The original purpose of the 1/2" threaded connection was for a packing leak-off line. A modified lantern ring is already installed which permits flow down along the valve stem and into the valve bonnet area. Once in the bonnet area of the 20" gate valve, FWLCS seal water flows around l the wedge-shaped gate into the area between the two hardfaced mainseats in the valve body.

Since FWLCS is supplied at higher than accident pressure, any leakage path available past the mainseats in the valve body would be sealed by the FWLCS.

The rerouted FWLCS subsystems will continue to be designed and installed as a single failure proof, safety-related, seismically qualified system and will be designed to withstand the dynamic effects of postulated piping failures in the steam tunnel including protection from internally generated missiles. The FWLCS piping that connects to the bonnet area of the existing MOV will conform to the requirements of ASME Class 2. In the revised configuration both trains of the FWLCS will be interlocked so that the systems can not be operated unless the Feedwater MOVs are closed. The proposed addition of both divisions of FWLCS to the bonnets of both of the gate valves on the Feedwater lines, together with the provisions for providing attemate power from Division 3 over to the gate valves, eliminates the possibility of FWLCS single failure, with the exception of a failure of one of the gate valves to close. As discu] sed above, the current licensing basis, as reflected in SSER 7, accepted the as-built configuration of the Feedwater lines. It assumes that the third (gate) valves will be successfully closed by the operator. This part of the licensing basis is being retained (the closure of the third (gate) valves.

This will allow initiation of one of the FWLC subsystems to the bonnet of the valves, resulting in the desired water seal on the lines.

Attachment 1 l PY-CEl/NRR-2322L Page 24 of 26 ENVIRONMENTAL CONSIDERATION The proposed Technical Specification change request was evaluated against the criteria of 10 CFR 51.22 for environmental considerations. The proposed change does not significantly increase individual or cumulative occupational radiation exposures, does not significantly change the types or significantly increase the amounts of effluents that may be released off-site and, as discussed in Attachment 2, does not involve a significant hazards consideration. Based on the foregoing, it has been concluded that the proposed Technical Specification change meets the criteria given in 10 CFR 51.22(c)(9) for categorical exclusion from the requirement for an Environmental Impact Statement.

COMMITMENTS WITHIN THIS LETTER The following table identifies those actions considered to be regulatory commitments. Any other actions discussed in this document represent current or planned actions, and are described for the NRC's information. Please notify the Manager- Regulatory Aihirs at the Perry Nuclear Power Plant of any questions regarding this document or any associard regulatory commitments.

Commitments

1. Although the current licensing basis already assumes that the third valve will be remote-manually closed by the control room operator following a loss-of-coolant-accident (LOCA) to provide the long term, high integrity leakage protection, an even higher confidence level on closure of these valves will be provided by a design change and revisions to plant emergency procedures. The procedures will direct operators to implement an alternate division of electrical power to the gate valves, in the event that the valves normal power supply is lost. An alternate division of power such as this is not a new concept; the operators already receive training on a similar arrangement that is utilized in the PNPP licensing basis for the Station Blackout event. The capability to provide power from Division 3 will be a permanent design modification, but physical and electrical separation between Divisions 1 and 3 will be maintained by employing two featurer.

Normally open, fused disconnect switches at both ends of the circuit, and Fuses normally stored out of the circuit.

2. If Division 1 power is not available, Division 3 power to the gate valves can be established, which will enable FWLCS to still be established within the "approximately one hour" time frame in the current licensing basis. An evaluation of the operator action per ANSI /ANS 58.8-1984 guidelines is being performed to determine the actual time and dose that would be involved with this action. This will be submitted to the NRC when completed.
3. Due to the injection of the seal water into the bonnet of the valve, air leakage will not be a concern. Stem and bonnet water leakage will be checked and any leakage will be eliminated (this will be controlled by the TS 5.5.2 " Primary Coolant Sources Outside Containment Program". This leakage elimination will be ensured through system walkdowns per the Program at > 1000 psig, with the gate valves in the closed position.

' 4. Due to the water seal provided by the high integrity Third Valves, the gate valve

Attachment 1 PY-CEl/NRR-2322L Page 25 of 26 Commitments j seat leakage will continue to be checked by a water test conducted at 21.1 P., and l the results will continue to be added into the Primary Coolant Sources Outside l Containment Program totals (Technical Specification 5.5.2).

l

5. Generic Letter (GL) 89-04 Position 3 "Back Flow Testing of Check Valves" noted that tests on check valves that perform a safety function in the closed position to prevent reversed flow should be performed. " Category C" tests on such " safety function check valves" were described as needing to prove that the disc closes on its seat. An example method discussed for such safety function Category C tests is a visual observation. It is proposed that the Feedwater Check Valves be Category C tested for their safety function by performance of a visualinspection of the valve internals at an appropriate frequency as determined by the Inservice Testing l Program (ISTP). A tap would be added adjacent to each check valve to permit l

visualinspections of the valves to verify proper closure. This inspection would constitute the " exercise closed (EC)" test in the ISTP. The " exercise open (EO)"

testing would remain the same, i.e., the valves pass proper flow during plant operation.

6. The RHR branch line off of the Feedwater line will be treated as a closed system l outside of containment, similar to the lines discussed in Note 4 to USAR Table 6.2-33 and Note 7 to Table 6.2-40. These Notes explain why leakage is not considered to be bypass leakage. A safety-related globe valve (1E12-F053A/B) in l this branch line will be treated as a high integrity containment isolation valve, j similar to the Feedwater gate valves. The 1E12-F053A/B valves will be added to the containment isolation valve listings. These valves meet the qualifications of a containment isolation valve. An air test will be performed on 1E12-F053A/B, and the air leakage will be added into the Type C totals and limited by 0.601... Also, the leakage from the F053 valves will be added into the Type A Integrated Leak Rate Test (ILRT), since the Feedwater penetrations will not be drained during the ILRT. Leakage from the systems listed in USAR Notes 4 and 7 as " closed" are i controlled by the Primary Coolant Sources Outside of Containment Program, as l described in the Notes. Thus, this RHR branch pathway would consist of an air I leak rate tested containment isolation valve and a closed system outside of containment. In addition, a high-to-low-pressure interface water test is performed l

on the E12-F053 globe valve and the check valve inboard of the F053 (E12-l F050A/B)(see the Figures)in accordance with ASME Section XI. Thase valves are tested to water leakage limits of s 5 gpm.

7. The remainder oi % RWCU line between the Feedwater line and Penetration P132 will be added tu the Technical Specification 5.5.2 Primary Coolan: Sources Outside Containment Progom, with a specific leakage acceptance limit ~of zero (0) l leakage when tested at RWCU operating pressures (>1000 psig). This obviates

, the nec't to add the RWCU branch line check valves (1G33-F052A/B) into a leak rate testing program, since zero water leakage outside the lines when operating at over 1000 psig ensures that there will be no air leakage from those mechanical joints at P. (7.8 psig for PNPP). This approach meets Branch Technical Position CSB 6-3 " Determination of Bypass Leakage Paths in Dual Containment Plants",

item B.9.

i Attachment 1 i i PY-CEl/NRR-2322L Page 26 of 26 +

Commitments

8. The piping of each FWLC subsystem which will connect to the bonnets / seats of the gate va!ves contains two currently existing isolation valves. These valves receive a high-to-low pressure interface water test since they connect back to the RHR/LPCS waterleg pumps. These tests will continue to be performed.
9. When Feedwater flow into the reactor has been stopped, plant procedures / instructions will continue to direct that the high integrity third (gate) ,

valves also be closed to provide additional isolation capability.  !

10. In the proposed design, both independent trains of the FWLCS will be routed to the '

bonnet area of the existing Feedwater MOV. To allow the FWLCS to seal the 20" gate valves, FWLCS will be supplied to an existing 1/2" threaded connection in the ,

packing area of the valve bonnet. The rerouted FWLCS subsystems will continue  ;

to be designed and installed as a single fa!!ure proof, safety-related, seismically qualified system and will be designed to withstand the dynamic effects of l

poctulated piping failures in the steam tunnel including protection froni internally l generated missiles. The FWLCS piping that connects to the bonnet area of the l existing MOV will conform to the requirements of ASME Class 2.

i- _

l i

q l  !

l i

! l l

f~ l i

)

- . ... . .. . . .. .. - ~ . - .- .-

k Attachment 2 PY-CEl/NRR-2322L Page 1 of 3 SIGNIFICANT HAZARDS CONSIDERATION l

The standards used to arrive at a determination that a request for amendment does not involve a significant hazard are included in Commission regulation 10 CFR 50.92, which ,

states that operation of the facility in accordance with the proposed changes would not-

1) involve a significant increase in the probability or consequences of an accident previously evaluated; l
2) create the possibility of a new or different kind of accident from any accident  !

previously evaluated; or

3) involve a significant reduction in a margin of safety.

The proposed amendment has been reviewed with respect to these three factors, and it has been determined that the proposed change does not involve a significant hazard because:

1) This proposed amendment does not involve a significant increase in the probability or consequences of an accident previously evaluated.

It is proposed that water leakage from the Feedwater motor-operated containment isolation valves will be added into the Primary Coolant Sources Outside Containment Program (Technical Specification 5.5.2), and therefore the Feedwater lines do not need to also be ,

included in the hydrostatic test program addressed by Surveillance Requirement 3.6.1.3.11.

The proposed testing change is based on design / licensing basis changes being impiemented to improve functioning of the Feedwater Leakage Control System. The proposed design change will provide Feedwater Leakage Control Systein seal water directly to the bonnets and seats of the motcr opeiated gate valves in the Feedwater lines, and allow for power to the  !

valves to be provided from redundant power supplies.

The proposed changes do not increase the probability of occurrence of an accident previously evaluated because the Feedwater Leakage Control System is not an initiator of a previously evaluated accident. The Feedwater Leakage Control System is used to mitigate the consequences of an event that has already been initiated due to some other cause, specifically a design basis Loss of Coolant Accident (LOCA). Therefore, changes to the design and testing on the Feedwater Leakage Control System have no impact on the probability of occurrence of an accident previously evaluated. The Feedwater Leakage Control System is a manually initiated system, and the prot, ability of an inadvertent initiation remains unchanged from that previously reviewed, so the possibility of a loss of feedwater transient is not increased. j The proposed changes do not significantly increase the radiological consequences of an l accident previously evaluated, because the Feedwater lines will continue to be isolated l following a LOCA either inside or outside of containment. For a line break outside of  !

containment, the check valves will provide the necessary short-term closure function to prevent significant loss of reactor coolant inventory, as currently stated in Updated Safety Analysis Report (USAR) Section 6.2.4.2.2.1.a.1. The third (gate) valves in the Feedwater line will also ,

be available to provide the long-term, high integrity leakage protection. The check valves Code l Class 1 closure function will be verified at an appropriate frequency by performance of an l exercise closed (EC) test comprised of a visualinspection of the internals of the valves, in

_----.--.--..-_.--..7 Attachment 2 l PY-CEl/NRR-2322L

! Page 2 of 3  !

l accordance with the Inservice Testing Program. The radiological consequences of such a line break outside of containment event are not significant, as there is no postulated fuel damage.

For a line break inside of containment (a design basis LOCA event), the majority of the j currently reviewed and accepted licensing basis is being maintained. Design changes are being implemented to improve the functioning of the Feedwater Leakage Control System. The redundant subsystems will be piped to the bonnets of the third, high integrity valves in the Feedwater lines (the gate valves) to provide a more rapid and effective seal on the stem, bonnet and flexible wedge seats. Water leakage from the stem, bonnets and seats of the gate valves will be addressed through controls imposed by Technical Specification 5.5.2, Primary Coolant Sources Outside Containment". The doses from such water leakage are accounted I

for in the radiological dose calculations. Since the leakage from the Feedwater lines is accounted for by the Primary Coolant Sources Outside Containment Program, there is no need to include the water test results of the Feedwater lines No tM unteillance Requirement 3.6.1.3.11 leak test totals.

I The branch lines off of the Feedwater lines will also be addressed either through the Primary Coolant Sources Outside Containment Program (Technical Specification 5.5.2) or through additional Appendix J air leak rate test requirements (Technical Specification Surveillance Requirement 3.6.1.1.1 and Specification 5.5.12 " Primary Containment Leakage Rate Testing ,

Program"). The new test methods for these lines do not impact the existing radiological dose l calculations, since the existing leakage limits of the leak rate test programs are not changed by I the proposal.

l The design changes associated with the Feedwater Leakage Control System will continue to satisfy licensing / design criteria for this piping to an equivalent degree as the current design.

The minor exception is where the two Feedwater Leakage Control subsystems tie in to the bonnets of the gate valves, and this constitutes only a separation issue. Since the Feedwater  ;

Leakage Control System piping at this juncture is Code Class 2, break excluded, and protected  !

from pipe whips and jet impingements, it is considered to be acceptable.

i Addition of the provisions for an attemate power supply to be provided to the gate valves (if necessary following a LOCA event) willimprove the probability of closure of these high integrity valves without creating an electrical separation concem. A separation concern will not be created since the supply circuitry from the attemate power source will be a permanent modification, and physical and electrical separation between electrical divisions will be maintained by employing two features:

1. Normally open, fused disconnect switches at both ends of the circuit, and i
2. Fuses normally r1 red out of the circuit.

Based on the discussions above, it is concluded that neither the probability nor the consequencm vi previously evaluated accidents are significantly increased as a result of the proposed changes to the Technical Specifications and to the licensing and design bases for i the Feedwater penetrations.

Attachment 2 PY-CEl/NRR-2322L Page 3 of 3

2) This proposed amendment does not create the possibility of a new or different kind of accident from any accident previously evaluated.

The Feedwater Leakage Control System was developed specifically to mitigate the consequences of a design basis LOCA inside the containment. The system itself and the proposed changes do not produce parameters or conditions that could contribute to the initiation of accidents different than those already evaluved in the Updated Safety Analysis Report. The proposed changes are intended to improve the functioning nf the Feedwater Leakage Control System should it be called upon following a LOCA. The changes affect mitigation of that previously evaluated event. In other plant conditions, including normal operation, the system is not activated and cannot induce events. Thus, the proposed amendment does not create the possibility of a new or different kind of accident from any accident previously evaluated.

3) This proposed amendment does not involve a significant reduction in a margin of safety.

The proposed changes only affect the methods used to ensure Feedwater Leakage Control System performance and reliability, and clarification of the licensing / design basis of the system.

The new proposed Note in Surveillance Reouirement 3.6.1.3.11 clarifies that the water leakage from the Feedwater lines does not need to be counted in two separate leak test programs.

The Primary Coolant Sources Outside Containment Program (Technical Specification 5.5.2) will ensure that leakage from the Feedwater lines is minimized, and accounted for in an appropriate fashion in the radiological dose calculations. Leak rate testing on the branch lines off of the Feedwater lines will also be controlled and limited by existing acceptance criteria for plant programs that protect the assumptions of the radiological dose calculations. Therefore, I

the margin of safety provided in the PNPP dose calculations will remain unchanged.

The majority of the existing licensing bases, and therefore the margins of safety, are maintained by this proposal. The items that are changed are done so to improve the reliability of the system or for an administrative clarification. The Feedwater Leakage Control System Technical Specification itself (Technical Specification 3.6.1.8) does not need revision. The design changes will maintain the existing licensing / design criteria, with the minor exception of divisional separation at the point that the two divisions have to be piped into the bonnets of the third (gate) valve. Since the piping at this junction point is Code Class 2, break excluded, and protected from pipe whips and jet impingements, it is considered to be acceptable. It will not lead to a significant reduction in a margin of safety. The manually initiated divisional cross-tie will not create an electrical separation concem. The alternate power supp!y provision will be a permanent modification, and physical and electrical separation between electrical divisions will be maintained.

Based on the above discussions, the proposed license amendment is concluded to not result in a significant reduction in the margin of safety.