Similar Documents at Fermi |
---|
Category:LICENSEE EVENT REPORT (SEE ALSO AO
MONTHYEARNRC-94-0025, LER 93-014-01:on 931225,turbine Generator Tripped When Mechanical Overspeed Device Was Activated.Caused by Severe Vibration.Corrective Action:Assessment of Structural Integrity of Pedestal Was conducted.W/940425 Ltr1994-04-25025 April 1994 LER 93-014-01:on 931225,turbine Generator Tripped When Mechanical Overspeed Device Was Activated.Caused by Severe Vibration.Corrective Action:Assessment of Structural Integrity of Pedestal Was conducted.W/940425 Ltr NRC-93-0058, LER 93-008-00:on 930518,discovered That Recorder T50-R802A Could Not Be Considered Operable Per TS 3.3.7.5.Caused by Personnel Error.Lessons Learned Will Be Incorporated Into Training Programs & Plant procedures.W/930618 Ltr1993-06-18018 June 1993 LER 93-008-00:on 930518,discovered That Recorder T50-R802A Could Not Be Considered Operable Per TS 3.3.7.5.Caused by Personnel Error.Lessons Learned Will Be Incorporated Into Training Programs & Plant procedures.W/930618 Ltr NRC-93-0055, LER 93-007-00:on 930420,reactor Tripped on Intermediate Range Monitor Upscale During Reactor Pressure & Feedwater Transient.Caused by Personnel Error.Affected Pressure Transmitters replaced.W/930520 Ltr1993-05-20020 May 1993 LER 93-007-00:on 930420,reactor Tripped on Intermediate Range Monitor Upscale During Reactor Pressure & Feedwater Transient.Caused by Personnel Error.Affected Pressure Transmitters replaced.W/930520 Ltr NRC-91-0058, LER 91-008-00:on 910424,reactor Bldg HVAC Tripped,Div I SGTS Auto Started & Div I Control Ctr HVAC Shifted to Recirculation Mode Due to Mispositioned Trip Output Logic switch.W/910524 Ltr1991-05-24024 May 1991 LER 91-008-00:on 910424,reactor Bldg HVAC Tripped,Div I SGTS Auto Started & Div I Control Ctr HVAC Shifted to Recirculation Mode Due to Mispositioned Trip Output Logic switch.W/910524 Ltr NRC-91-0069, LER 90-012-01:on 901016,HPIC Steam Line Flow Transmitter Failed Due to Short Circuit Across Capacitor Plates.Circuit Boards Replaced & Failure Analysis Performed by Rosemount,Inc.W/910524 Ltr1991-05-24024 May 1991 LER 90-012-01:on 901016,HPIC Steam Line Flow Transmitter Failed Due to Short Circuit Across Capacitor Plates.Circuit Boards Replaced & Failure Analysis Performed by Rosemount,Inc.W/910524 Ltr NRC-91-0055, LER 91-006-00:on 910410,balance of Plant Breaker Opened Causing Reactor Bldg HVAC Isolation.Caused by Component Failures.Nprds Search Conducted for Similiar Problems. W/910510 Ltr1991-05-10010 May 1991 LER 91-006-00:on 910410,balance of Plant Breaker Opened Causing Reactor Bldg HVAC Isolation.Caused by Component Failures.Nprds Search Conducted for Similiar Problems. W/910510 Ltr NRC-91-0004, LER 90-013-00:on 901228,determined That Inadequate Control Could Occur During Air Grab Sampling Process.Caused by Lack of Proper Administrative Controls in Sampling Procedure. Sample Suction added.W/910128 Ltr1991-01-28028 January 1991 LER 90-013-00:on 901228,determined That Inadequate Control Could Occur During Air Grab Sampling Process.Caused by Lack of Proper Administrative Controls in Sampling Procedure. Sample Suction added.W/910128 Ltr NRC-90-0144, LER 90-007-00:on 900829,control Ctr Ventilation Shifted to Recirculation Due to Blown Fuse.Caused by Design Deficiency in Div 1 & 2 Radiation Monitor Trip Circuitry.Design Change Implemented to Eliminate Trip Relay logic.W/900928 Ltr1990-09-28028 September 1990 LER 90-007-00:on 900829,control Ctr Ventilation Shifted to Recirculation Due to Blown Fuse.Caused by Design Deficiency in Div 1 & 2 Radiation Monitor Trip Circuitry.Design Change Implemented to Eliminate Trip Relay logic.W/900928 Ltr NRC-90-0107, LER 88-034-01:on 880831,RWCU Outboard Isolation Valve Closed,Causing RWCU Pumps to Trip.Caused by Loss of Continuity to Relay Due to Deposits Built Up on Surface of Contacts.Relay in Isolation Circuits replaced.W/900622 Ltr1990-06-22022 June 1990 LER 88-034-01:on 880831,RWCU Outboard Isolation Valve Closed,Causing RWCU Pumps to Trip.Caused by Loss of Continuity to Relay Due to Deposits Built Up on Surface of Contacts.Relay in Isolation Circuits replaced.W/900622 Ltr NRC-90-0087, LER 90-002-01:on 900202,determined That Area Radiation Surveillance Procedure 44.080.301 Listed Incorrect Values for Alarm Setpoints.Caused by Unavailable Setpoint Calculations.Procedure revised.W/900608 Ltr1990-06-0808 June 1990 LER 90-002-01:on 900202,determined That Area Radiation Surveillance Procedure 44.080.301 Listed Incorrect Values for Alarm Setpoints.Caused by Unavailable Setpoint Calculations.Procedure revised.W/900608 Ltr NRC-90-0075, LER 87-045-02:on 870908,operator Removed Fuse Which Deenergized Dc Control Power to Bus 72C,resulting in Loss of Power Supply to Swing Bus & to LPCI Loop Selection Valves. Caused by Design Flaw.Design Change initiated.W/900518 Ltr1990-05-18018 May 1990 LER 87-045-02:on 870908,operator Removed Fuse Which Deenergized Dc Control Power to Bus 72C,resulting in Loss of Power Supply to Swing Bus & to LPCI Loop Selection Valves. Caused by Design Flaw.Design Change initiated.W/900518 Ltr NRC-90-0073, LER 90-003-00:on 900410,Div I Reactor Protection Sys Power Supply Failure & Subsequent MSIV Closure.Caused by Coil Burn Up.Relays Replaced & MG Sets Returned to svc.W/900508 Ltr1990-05-0808 May 1990 LER 90-003-00:on 900410,Div I Reactor Protection Sys Power Supply Failure & Subsequent MSIV Closure.Caused by Coil Burn Up.Relays Replaced & MG Sets Returned to svc.W/900508 Ltr NRC-90-0048, LER 89-037-01:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed Prior to Expiration on 891125. Caused by Personnel Error.Procedure revised.W/900322 Ltr1990-03-22022 March 1990 LER 89-037-01:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed Prior to Expiration on 891125. Caused by Personnel Error.Procedure revised.W/900322 Ltr NRC-90-0027, LER 89-034-01:on 891208,two Members of Fire Watch Did Not Complete Assigned Hourly Rounds from 891002-1207 in Reactor & Auxiliary Bldgs.Both Individuals Terminated & Fire Stations Equipped W/Unique Bar code.W/900221 Ltr1990-02-21021 February 1990 LER 89-034-01:on 891208,two Members of Fire Watch Did Not Complete Assigned Hourly Rounds from 891002-1207 in Reactor & Auxiliary Bldgs.Both Individuals Terminated & Fire Stations Equipped W/Unique Bar code.W/900221 Ltr NRC-90-0021, LER 90-001-00:on 900108,annunciator 2D5 Alarmed for Div II ECCS Testability Logic/Power Failure.Caused by Blown Fuse. Fuse Installed During Course of Troubleshooting W/No Subsequent Problems noted.W/900207 Ltr1990-02-0707 February 1990 LER 90-001-00:on 900108,annunciator 2D5 Alarmed for Div II ECCS Testability Logic/Power Failure.Caused by Blown Fuse. Fuse Installed During Course of Troubleshooting W/No Subsequent Problems noted.W/900207 Ltr NRC-90-0019, LER 89-028-01:on 891028,eight Safety Relief Valves Failed Set Pressure Tolerance Test.Cause Under Review by Util & Generically by BWR Owners Group Safety Relief Valve Set Point Drift Committee.Valves Removed & cleaned.W/900131 Ltr1990-01-31031 January 1990 LER 89-028-01:on 891028,eight Safety Relief Valves Failed Set Pressure Tolerance Test.Cause Under Review by Util & Generically by BWR Owners Group Safety Relief Valve Set Point Drift Committee.Valves Removed & cleaned.W/900131 Ltr NRC-90-0018, LER 89-039-00:on 891226,Div I Emergency Equipment Cooling Water & Svc Water Sys Automatically Started Due to Partial Load Shed of Bus 72E.Caused by Personnel Error. Accountability Meeting Held on 900117.W/900125 Ltr1990-01-25025 January 1990 LER 89-039-00:on 891226,Div I Emergency Equipment Cooling Water & Svc Water Sys Automatically Started Due to Partial Load Shed of Bus 72E.Caused by Personnel Error. Accountability Meeting Held on 900117.W/900125 Ltr NRC-90-0008, LER 89-037-00:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed.Caused by Personnel Error. Critique of Event Being developed.W/900119 Ltr1990-01-19019 January 1990 LER 89-037-00:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed.Caused by Personnel Error. Critique of Event Being developed.W/900119 Ltr NRC-90-0007, LER 89-036-00:on 891218,control Room Operator Inadvertently Depressed Closed Push Buttons on Inboard MSIVs A,B & C & Reactor Scram Resulted.Caused by Operator Error.Operator Involved Was Removed from Licensed duties.W/900117 Ltr1990-01-17017 January 1990 LER 89-036-00:on 891218,control Room Operator Inadvertently Depressed Closed Push Buttons on Inboard MSIVs A,B & C & Reactor Scram Resulted.Caused by Operator Error.Operator Involved Was Removed from Licensed duties.W/900117 Ltr ML19354E0971990-01-12012 January 1990 LER 89-038-00:on 891223,reactor Scrammed When Fire Occurred in Vicinity of High Pressure Turbine.Caused by Oil Soaked Inlagging Pads & Ignited When Turbine Casing Heated Up to Oil Flashpoint.Insulation Pads replaced.W/900122 Ltr NRC-90-0005, LER 89-035-00:on 891210,steam Jet Air Ejectors Placed in Svc W/O Required Surveillance Completed & Required Grab Sample Not Started Until 891213.Caused by Personnel Error.Off Gas Sys Operating Procedure Will Be revised.W/900111 Ltr1990-01-11011 January 1990 LER 89-035-00:on 891210,steam Jet Air Ejectors Placed in Svc W/O Required Surveillance Completed & Required Grab Sample Not Started Until 891213.Caused by Personnel Error.Off Gas Sys Operating Procedure Will Be revised.W/900111 Ltr NRC-90-0004, LER 89-030-00:on 891026,Channel C Level 1 & 2 Replacement Transmitter Found to Be Installed Incorrectly & Condition Recognized on 891210,when Level 2 Trip Unit Was Reading Upscale.Caused by Personnel error.W/900109 Ltr1990-01-0909 January 1990 LER 89-030-00:on 891026,Channel C Level 1 & 2 Replacement Transmitter Found to Be Installed Incorrectly & Condition Recognized on 891210,when Level 2 Trip Unit Was Reading Upscale.Caused by Personnel error.W/900109 Ltr NRC-90-0002, LER 89-033-00:on 891207,volt-ohm Meter Connected to Incorrect Terminal,Causing Div II of Emergency Equipment Cooling Water Sys to Actuate.Caused by Personnel Error.Sys Secured & Channel Test Successfully completed.W/900108 Ltr1990-01-0808 January 1990 LER 89-033-00:on 891207,volt-ohm Meter Connected to Incorrect Terminal,Causing Div II of Emergency Equipment Cooling Water Sys to Actuate.Caused by Personnel Error.Sys Secured & Channel Test Successfully completed.W/900108 Ltr NRC-90-0003, LER 89-034-00:on 891208,review of Key Card Transactions Showed That Fire Watch Personnel Missed Assigned Hourly Fire Watch from 891020-1207.Fire Watch Person Discharged.Plan Re Improvement of Fire Watches developed.W/900108 Ltr1990-01-0808 January 1990 LER 89-034-00:on 891208,review of Key Card Transactions Showed That Fire Watch Personnel Missed Assigned Hourly Fire Watch from 891020-1207.Fire Watch Person Discharged.Plan Re Improvement of Fire Watches developed.W/900108 Ltr NRC-89-0261, LER 89-028-00:on 891129,ESF Actuations Occurred During Set Up for Surveillance.Caused by Blown Fuse.Blown Fuse Replaced & Affected Sys Returned to Normal Operation Following Completion of surveillance.W/891228 Ltr1989-12-28028 December 1989 LER 89-028-00:on 891129,ESF Actuations Occurred During Set Up for Surveillance.Caused by Blown Fuse.Blown Fuse Replaced & Affected Sys Returned to Normal Operation Following Completion of surveillance.W/891228 Ltr NRC-89-0260, LER 89-021-01:on 890906,35 of 237 Containment Isolation Valves Exceeded Administrative Allowable Leakage Rate When Tested.Caused by Normal Wear & Degradation During Specified Time Interval.Valves Cleaned & repaired.W/891221 Ltr1989-12-21021 December 1989 LER 89-021-01:on 890906,35 of 237 Containment Isolation Valves Exceeded Administrative Allowable Leakage Rate When Tested.Caused by Normal Wear & Degradation During Specified Time Interval.Valves Cleaned & repaired.W/891221 Ltr NRC-89-0255, LER 89-031-00:on 891120,both Div II Emergency Equipment Cooling Water (EECW) & Emergency Equipment Svc Water Sys Pumps Tripped Immediately.Caused by Inadequacies in Stated Procedures.Procedures revised.W/891220 Ltr1989-12-20020 December 1989 LER 89-031-00:on 891120,both Div II Emergency Equipment Cooling Water (EECW) & Emergency Equipment Svc Water Sys Pumps Tripped Immediately.Caused by Inadequacies in Stated Procedures.Procedures revised.W/891220 Ltr NRC-89-0259, LER 89-017-01:on 890810,new Analysis of Feedwater Line Break Scenario Assumes Failure of Feedwater Startup Control Valve in Open Position.Review of Pipe Break Documentation Conducted.Updated FSAR Change to Be submitted.W/891215 Ltr1989-12-15015 December 1989 LER 89-017-01:on 890810,new Analysis of Feedwater Line Break Scenario Assumes Failure of Feedwater Startup Control Valve in Open Position.Review of Pipe Break Documentation Conducted.Updated FSAR Change to Be submitted.W/891215 Ltr NRC-89-0256, LER 89-022-01:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse C71A-F15B Blew.On 890928, Reactor Bldg HVAC Isolated.Caused by Personnel Error. Procedures Will Be revised.W/891215 Ltr1989-12-15015 December 1989 LER 89-022-01:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse C71A-F15B Blew.On 890928, Reactor Bldg HVAC Isolated.Caused by Personnel Error. Procedures Will Be revised.W/891215 Ltr NRC-89-0258, LER 89-025-00:on 891115,low Level 2 Signal Unintentionally Induced During Reactor Pressure Vessel Hydrostatic Pressure Test.Caused by Personnel Error.Personnel Counseled on Notifying & Coordinating Instrument lineups.W/891215 Ltr1989-12-15015 December 1989 LER 89-025-00:on 891115,low Level 2 Signal Unintentionally Induced During Reactor Pressure Vessel Hydrostatic Pressure Test.Caused by Personnel Error.Personnel Counseled on Notifying & Coordinating Instrument lineups.W/891215 Ltr NRC-89-0251, LER 89-019-01:on 890819,discovered That Div I Recirculation Fan Not Rotating Which Resulted in Decrease in Control Room Air Pressure.Caused by Lack of Lubrication in Bearings. Lubrication Program Improvements evaluated.W/891130 Ltr1989-11-30030 November 1989 LER 89-019-01:on 890819,discovered That Div I Recirculation Fan Not Rotating Which Resulted in Decrease in Control Room Air Pressure.Caused by Lack of Lubrication in Bearings. Lubrication Program Improvements evaluated.W/891130 Ltr NRC-89-0249, LER 89-029-00:on 891023,half Scram Signal Received When Power Was Lost on Reactor Protection Sys Bus B,Resulting in Several ESFs Actuation.Caused by Location of Breaker Operating Switch in High Traffic area.W/891122 Ltr1989-11-22022 November 1989 LER 89-029-00:on 891023,half Scram Signal Received When Power Was Lost on Reactor Protection Sys Bus B,Resulting in Several ESFs Actuation.Caused by Location of Breaker Operating Switch in High Traffic area.W/891122 Ltr NRC-89-0246, LER 89-028-00:on 891020,eight safety-related Valves Failed Set Pressure Test.Cause Under Review.All Valves Removed for Testing Being Refurbished,Cleaned,Retested & Recertified to Be within Plant Accepted tolerances.W/891120 Ltr1989-11-20020 November 1989 LER 89-028-00:on 891020,eight safety-related Valves Failed Set Pressure Test.Cause Under Review.All Valves Removed for Testing Being Refurbished,Cleaned,Retested & Recertified to Be within Plant Accepted tolerances.W/891120 Ltr NRC-89-0244, LER 89-024-00:on 891019,recognized That Secondary Containment Dampers Not Tested as Required by Tech Spec 3.6.5.2.Caused by Operations Personnel Error.Event Critique to Be Included in Required Reading program.W/891120 Ltr1989-11-20020 November 1989 LER 89-024-00:on 891019,recognized That Secondary Containment Dampers Not Tested as Required by Tech Spec 3.6.5.2.Caused by Operations Personnel Error.Event Critique to Be Included in Required Reading program.W/891120 Ltr NRC-89-0194, LER 89-027-00:on 891015,reactor Bldg Hvac,Control Ctr HVAC & Drywell Floor & Equipment Drain Sumps Isolated & Standby Gas Treatment Sys & Noninterrruptalbe Control Air Compressors Started.Caused by Personnel error.W/891114 Ltr1989-11-14014 November 1989 LER 89-027-00:on 891015,reactor Bldg Hvac,Control Ctr HVAC & Drywell Floor & Equipment Drain Sumps Isolated & Standby Gas Treatment Sys & Noninterrruptalbe Control Air Compressors Started.Caused by Personnel error.W/891114 Ltr NRC-89-0193, LER 89-026-00:on 891010,control Ctr HVAC Shifted to Recirculation Mode of Operaton Due to Short Circuit.Caused by Failure of Lamp Filament When Being Tightened.Fuse & Lamp Replaced & Sys Returned to Normal operation.W/891109 Ltr1989-11-0909 November 1989 LER 89-026-00:on 891010,control Ctr HVAC Shifted to Recirculation Mode of Operaton Due to Short Circuit.Caused by Failure of Lamp Filament When Being Tightened.Fuse & Lamp Replaced & Sys Returned to Normal operation.W/891109 Ltr NRC-89-0192, LER 87-045-01:on 870908,fuse Removed Which Deenergized Dc Control Power to Bus 72C & Resulted in Loss of Power Supply to Swing Bus & LPCI Loop Selection Valves.Caused by Design Error.Undervoltage Relay Added & Training held.W/891106 Ltr1989-11-0606 November 1989 LER 87-045-01:on 870908,fuse Removed Which Deenergized Dc Control Power to Bus 72C & Resulted in Loss of Power Supply to Swing Bus & LPCI Loop Selection Valves.Caused by Design Error.Undervoltage Relay Added & Training held.W/891106 Ltr NRC-89-0190, LER 89-023-00:on 890924,personnel Inadvertently Caused Trip of Essential Safety Sys Buses 64B & 64C.Caused by Failure of Personnel Involved to Review Applicable Prints Prior to Performing Test.Event Reviewed w/personnel.W/891024 Ltr1989-10-24024 October 1989 LER 89-023-00:on 890924,personnel Inadvertently Caused Trip of Essential Safety Sys Buses 64B & 64C.Caused by Failure of Personnel Involved to Review Applicable Prints Prior to Performing Test.Event Reviewed w/personnel.W/891024 Ltr NRC-89-0189, LER 89-022-00:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse Blew.On 890928,reactor Bldg HVAC Isolated When Jumper Lifted Per Incorrect Work Plan Instruction.Caused by Personnel error.W/891023 Ltr1989-10-23023 October 1989 LER 89-022-00:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse Blew.On 890928,reactor Bldg HVAC Isolated When Jumper Lifted Per Incorrect Work Plan Instruction.Caused by Personnel error.W/891023 Ltr NRC-89-0186, LER 89-016-01:on 890711,Div 1 of RHR Svc Water Sys Declared Inoperable Due to Low Nitrogen Pressure for Cooling Tower Fan Brake.Caused by Leak in One Hose.Leaking Hose Replaced & Nitrogen Pressure restored.W/891006 Ltr1989-10-0606 October 1989 LER 89-016-01:on 890711,Div 1 of RHR Svc Water Sys Declared Inoperable Due to Low Nitrogen Pressure for Cooling Tower Fan Brake.Caused by Leak in One Hose.Leaking Hose Replaced & Nitrogen Pressure restored.W/891006 Ltr NRC-89-0185, LER 89-021-00:on 890906,local Leak Rate Testing of Containment Isolation Valves & Penetrations Exceeded Tech Spec Limit.Caused by Excessive Containment Isolation Valve Leakage Due to Degradation of valve.W/891006 Ltr1989-10-0606 October 1989 LER 89-021-00:on 890906,local Leak Rate Testing of Containment Isolation Valves & Penetrations Exceeded Tech Spec Limit.Caused by Excessive Containment Isolation Valve Leakage Due to Degradation of valve.W/891006 Ltr 1994-04-25
[Table view] Category:RO)
MONTHYEARNRC-94-0025, LER 93-014-01:on 931225,turbine Generator Tripped When Mechanical Overspeed Device Was Activated.Caused by Severe Vibration.Corrective Action:Assessment of Structural Integrity of Pedestal Was conducted.W/940425 Ltr1994-04-25025 April 1994 LER 93-014-01:on 931225,turbine Generator Tripped When Mechanical Overspeed Device Was Activated.Caused by Severe Vibration.Corrective Action:Assessment of Structural Integrity of Pedestal Was conducted.W/940425 Ltr NRC-93-0058, LER 93-008-00:on 930518,discovered That Recorder T50-R802A Could Not Be Considered Operable Per TS 3.3.7.5.Caused by Personnel Error.Lessons Learned Will Be Incorporated Into Training Programs & Plant procedures.W/930618 Ltr1993-06-18018 June 1993 LER 93-008-00:on 930518,discovered That Recorder T50-R802A Could Not Be Considered Operable Per TS 3.3.7.5.Caused by Personnel Error.Lessons Learned Will Be Incorporated Into Training Programs & Plant procedures.W/930618 Ltr NRC-93-0055, LER 93-007-00:on 930420,reactor Tripped on Intermediate Range Monitor Upscale During Reactor Pressure & Feedwater Transient.Caused by Personnel Error.Affected Pressure Transmitters replaced.W/930520 Ltr1993-05-20020 May 1993 LER 93-007-00:on 930420,reactor Tripped on Intermediate Range Monitor Upscale During Reactor Pressure & Feedwater Transient.Caused by Personnel Error.Affected Pressure Transmitters replaced.W/930520 Ltr NRC-91-0058, LER 91-008-00:on 910424,reactor Bldg HVAC Tripped,Div I SGTS Auto Started & Div I Control Ctr HVAC Shifted to Recirculation Mode Due to Mispositioned Trip Output Logic switch.W/910524 Ltr1991-05-24024 May 1991 LER 91-008-00:on 910424,reactor Bldg HVAC Tripped,Div I SGTS Auto Started & Div I Control Ctr HVAC Shifted to Recirculation Mode Due to Mispositioned Trip Output Logic switch.W/910524 Ltr NRC-91-0069, LER 90-012-01:on 901016,HPIC Steam Line Flow Transmitter Failed Due to Short Circuit Across Capacitor Plates.Circuit Boards Replaced & Failure Analysis Performed by Rosemount,Inc.W/910524 Ltr1991-05-24024 May 1991 LER 90-012-01:on 901016,HPIC Steam Line Flow Transmitter Failed Due to Short Circuit Across Capacitor Plates.Circuit Boards Replaced & Failure Analysis Performed by Rosemount,Inc.W/910524 Ltr NRC-91-0055, LER 91-006-00:on 910410,balance of Plant Breaker Opened Causing Reactor Bldg HVAC Isolation.Caused by Component Failures.Nprds Search Conducted for Similiar Problems. W/910510 Ltr1991-05-10010 May 1991 LER 91-006-00:on 910410,balance of Plant Breaker Opened Causing Reactor Bldg HVAC Isolation.Caused by Component Failures.Nprds Search Conducted for Similiar Problems. W/910510 Ltr NRC-91-0004, LER 90-013-00:on 901228,determined That Inadequate Control Could Occur During Air Grab Sampling Process.Caused by Lack of Proper Administrative Controls in Sampling Procedure. Sample Suction added.W/910128 Ltr1991-01-28028 January 1991 LER 90-013-00:on 901228,determined That Inadequate Control Could Occur During Air Grab Sampling Process.Caused by Lack of Proper Administrative Controls in Sampling Procedure. Sample Suction added.W/910128 Ltr NRC-90-0144, LER 90-007-00:on 900829,control Ctr Ventilation Shifted to Recirculation Due to Blown Fuse.Caused by Design Deficiency in Div 1 & 2 Radiation Monitor Trip Circuitry.Design Change Implemented to Eliminate Trip Relay logic.W/900928 Ltr1990-09-28028 September 1990 LER 90-007-00:on 900829,control Ctr Ventilation Shifted to Recirculation Due to Blown Fuse.Caused by Design Deficiency in Div 1 & 2 Radiation Monitor Trip Circuitry.Design Change Implemented to Eliminate Trip Relay logic.W/900928 Ltr NRC-90-0107, LER 88-034-01:on 880831,RWCU Outboard Isolation Valve Closed,Causing RWCU Pumps to Trip.Caused by Loss of Continuity to Relay Due to Deposits Built Up on Surface of Contacts.Relay in Isolation Circuits replaced.W/900622 Ltr1990-06-22022 June 1990 LER 88-034-01:on 880831,RWCU Outboard Isolation Valve Closed,Causing RWCU Pumps to Trip.Caused by Loss of Continuity to Relay Due to Deposits Built Up on Surface of Contacts.Relay in Isolation Circuits replaced.W/900622 Ltr NRC-90-0087, LER 90-002-01:on 900202,determined That Area Radiation Surveillance Procedure 44.080.301 Listed Incorrect Values for Alarm Setpoints.Caused by Unavailable Setpoint Calculations.Procedure revised.W/900608 Ltr1990-06-0808 June 1990 LER 90-002-01:on 900202,determined That Area Radiation Surveillance Procedure 44.080.301 Listed Incorrect Values for Alarm Setpoints.Caused by Unavailable Setpoint Calculations.Procedure revised.W/900608 Ltr NRC-90-0075, LER 87-045-02:on 870908,operator Removed Fuse Which Deenergized Dc Control Power to Bus 72C,resulting in Loss of Power Supply to Swing Bus & to LPCI Loop Selection Valves. Caused by Design Flaw.Design Change initiated.W/900518 Ltr1990-05-18018 May 1990 LER 87-045-02:on 870908,operator Removed Fuse Which Deenergized Dc Control Power to Bus 72C,resulting in Loss of Power Supply to Swing Bus & to LPCI Loop Selection Valves. Caused by Design Flaw.Design Change initiated.W/900518 Ltr NRC-90-0073, LER 90-003-00:on 900410,Div I Reactor Protection Sys Power Supply Failure & Subsequent MSIV Closure.Caused by Coil Burn Up.Relays Replaced & MG Sets Returned to svc.W/900508 Ltr1990-05-0808 May 1990 LER 90-003-00:on 900410,Div I Reactor Protection Sys Power Supply Failure & Subsequent MSIV Closure.Caused by Coil Burn Up.Relays Replaced & MG Sets Returned to svc.W/900508 Ltr NRC-90-0048, LER 89-037-01:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed Prior to Expiration on 891125. Caused by Personnel Error.Procedure revised.W/900322 Ltr1990-03-22022 March 1990 LER 89-037-01:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed Prior to Expiration on 891125. Caused by Personnel Error.Procedure revised.W/900322 Ltr NRC-90-0027, LER 89-034-01:on 891208,two Members of Fire Watch Did Not Complete Assigned Hourly Rounds from 891002-1207 in Reactor & Auxiliary Bldgs.Both Individuals Terminated & Fire Stations Equipped W/Unique Bar code.W/900221 Ltr1990-02-21021 February 1990 LER 89-034-01:on 891208,two Members of Fire Watch Did Not Complete Assigned Hourly Rounds from 891002-1207 in Reactor & Auxiliary Bldgs.Both Individuals Terminated & Fire Stations Equipped W/Unique Bar code.W/900221 Ltr NRC-90-0021, LER 90-001-00:on 900108,annunciator 2D5 Alarmed for Div II ECCS Testability Logic/Power Failure.Caused by Blown Fuse. Fuse Installed During Course of Troubleshooting W/No Subsequent Problems noted.W/900207 Ltr1990-02-0707 February 1990 LER 90-001-00:on 900108,annunciator 2D5 Alarmed for Div II ECCS Testability Logic/Power Failure.Caused by Blown Fuse. Fuse Installed During Course of Troubleshooting W/No Subsequent Problems noted.W/900207 Ltr NRC-90-0019, LER 89-028-01:on 891028,eight Safety Relief Valves Failed Set Pressure Tolerance Test.Cause Under Review by Util & Generically by BWR Owners Group Safety Relief Valve Set Point Drift Committee.Valves Removed & cleaned.W/900131 Ltr1990-01-31031 January 1990 LER 89-028-01:on 891028,eight Safety Relief Valves Failed Set Pressure Tolerance Test.Cause Under Review by Util & Generically by BWR Owners Group Safety Relief Valve Set Point Drift Committee.Valves Removed & cleaned.W/900131 Ltr NRC-90-0018, LER 89-039-00:on 891226,Div I Emergency Equipment Cooling Water & Svc Water Sys Automatically Started Due to Partial Load Shed of Bus 72E.Caused by Personnel Error. Accountability Meeting Held on 900117.W/900125 Ltr1990-01-25025 January 1990 LER 89-039-00:on 891226,Div I Emergency Equipment Cooling Water & Svc Water Sys Automatically Started Due to Partial Load Shed of Bus 72E.Caused by Personnel Error. Accountability Meeting Held on 900117.W/900125 Ltr NRC-90-0008, LER 89-037-00:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed.Caused by Personnel Error. Critique of Event Being developed.W/900119 Ltr1990-01-19019 January 1990 LER 89-037-00:on 891220,determined That Tech Spec Stroke Time Testing for Outboard Reactor Water Sample Line Isolation Valve Not Performed.Caused by Personnel Error. Critique of Event Being developed.W/900119 Ltr NRC-90-0007, LER 89-036-00:on 891218,control Room Operator Inadvertently Depressed Closed Push Buttons on Inboard MSIVs A,B & C & Reactor Scram Resulted.Caused by Operator Error.Operator Involved Was Removed from Licensed duties.W/900117 Ltr1990-01-17017 January 1990 LER 89-036-00:on 891218,control Room Operator Inadvertently Depressed Closed Push Buttons on Inboard MSIVs A,B & C & Reactor Scram Resulted.Caused by Operator Error.Operator Involved Was Removed from Licensed duties.W/900117 Ltr ML19354E0971990-01-12012 January 1990 LER 89-038-00:on 891223,reactor Scrammed When Fire Occurred in Vicinity of High Pressure Turbine.Caused by Oil Soaked Inlagging Pads & Ignited When Turbine Casing Heated Up to Oil Flashpoint.Insulation Pads replaced.W/900122 Ltr NRC-90-0005, LER 89-035-00:on 891210,steam Jet Air Ejectors Placed in Svc W/O Required Surveillance Completed & Required Grab Sample Not Started Until 891213.Caused by Personnel Error.Off Gas Sys Operating Procedure Will Be revised.W/900111 Ltr1990-01-11011 January 1990 LER 89-035-00:on 891210,steam Jet Air Ejectors Placed in Svc W/O Required Surveillance Completed & Required Grab Sample Not Started Until 891213.Caused by Personnel Error.Off Gas Sys Operating Procedure Will Be revised.W/900111 Ltr NRC-90-0004, LER 89-030-00:on 891026,Channel C Level 1 & 2 Replacement Transmitter Found to Be Installed Incorrectly & Condition Recognized on 891210,when Level 2 Trip Unit Was Reading Upscale.Caused by Personnel error.W/900109 Ltr1990-01-0909 January 1990 LER 89-030-00:on 891026,Channel C Level 1 & 2 Replacement Transmitter Found to Be Installed Incorrectly & Condition Recognized on 891210,when Level 2 Trip Unit Was Reading Upscale.Caused by Personnel error.W/900109 Ltr NRC-90-0002, LER 89-033-00:on 891207,volt-ohm Meter Connected to Incorrect Terminal,Causing Div II of Emergency Equipment Cooling Water Sys to Actuate.Caused by Personnel Error.Sys Secured & Channel Test Successfully completed.W/900108 Ltr1990-01-0808 January 1990 LER 89-033-00:on 891207,volt-ohm Meter Connected to Incorrect Terminal,Causing Div II of Emergency Equipment Cooling Water Sys to Actuate.Caused by Personnel Error.Sys Secured & Channel Test Successfully completed.W/900108 Ltr NRC-90-0003, LER 89-034-00:on 891208,review of Key Card Transactions Showed That Fire Watch Personnel Missed Assigned Hourly Fire Watch from 891020-1207.Fire Watch Person Discharged.Plan Re Improvement of Fire Watches developed.W/900108 Ltr1990-01-0808 January 1990 LER 89-034-00:on 891208,review of Key Card Transactions Showed That Fire Watch Personnel Missed Assigned Hourly Fire Watch from 891020-1207.Fire Watch Person Discharged.Plan Re Improvement of Fire Watches developed.W/900108 Ltr NRC-89-0261, LER 89-028-00:on 891129,ESF Actuations Occurred During Set Up for Surveillance.Caused by Blown Fuse.Blown Fuse Replaced & Affected Sys Returned to Normal Operation Following Completion of surveillance.W/891228 Ltr1989-12-28028 December 1989 LER 89-028-00:on 891129,ESF Actuations Occurred During Set Up for Surveillance.Caused by Blown Fuse.Blown Fuse Replaced & Affected Sys Returned to Normal Operation Following Completion of surveillance.W/891228 Ltr NRC-89-0260, LER 89-021-01:on 890906,35 of 237 Containment Isolation Valves Exceeded Administrative Allowable Leakage Rate When Tested.Caused by Normal Wear & Degradation During Specified Time Interval.Valves Cleaned & repaired.W/891221 Ltr1989-12-21021 December 1989 LER 89-021-01:on 890906,35 of 237 Containment Isolation Valves Exceeded Administrative Allowable Leakage Rate When Tested.Caused by Normal Wear & Degradation During Specified Time Interval.Valves Cleaned & repaired.W/891221 Ltr NRC-89-0255, LER 89-031-00:on 891120,both Div II Emergency Equipment Cooling Water (EECW) & Emergency Equipment Svc Water Sys Pumps Tripped Immediately.Caused by Inadequacies in Stated Procedures.Procedures revised.W/891220 Ltr1989-12-20020 December 1989 LER 89-031-00:on 891120,both Div II Emergency Equipment Cooling Water (EECW) & Emergency Equipment Svc Water Sys Pumps Tripped Immediately.Caused by Inadequacies in Stated Procedures.Procedures revised.W/891220 Ltr NRC-89-0259, LER 89-017-01:on 890810,new Analysis of Feedwater Line Break Scenario Assumes Failure of Feedwater Startup Control Valve in Open Position.Review of Pipe Break Documentation Conducted.Updated FSAR Change to Be submitted.W/891215 Ltr1989-12-15015 December 1989 LER 89-017-01:on 890810,new Analysis of Feedwater Line Break Scenario Assumes Failure of Feedwater Startup Control Valve in Open Position.Review of Pipe Break Documentation Conducted.Updated FSAR Change to Be submitted.W/891215 Ltr NRC-89-0256, LER 89-022-01:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse C71A-F15B Blew.On 890928, Reactor Bldg HVAC Isolated.Caused by Personnel Error. Procedures Will Be revised.W/891215 Ltr1989-12-15015 December 1989 LER 89-022-01:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse C71A-F15B Blew.On 890928, Reactor Bldg HVAC Isolated.Caused by Personnel Error. Procedures Will Be revised.W/891215 Ltr NRC-89-0258, LER 89-025-00:on 891115,low Level 2 Signal Unintentionally Induced During Reactor Pressure Vessel Hydrostatic Pressure Test.Caused by Personnel Error.Personnel Counseled on Notifying & Coordinating Instrument lineups.W/891215 Ltr1989-12-15015 December 1989 LER 89-025-00:on 891115,low Level 2 Signal Unintentionally Induced During Reactor Pressure Vessel Hydrostatic Pressure Test.Caused by Personnel Error.Personnel Counseled on Notifying & Coordinating Instrument lineups.W/891215 Ltr NRC-89-0251, LER 89-019-01:on 890819,discovered That Div I Recirculation Fan Not Rotating Which Resulted in Decrease in Control Room Air Pressure.Caused by Lack of Lubrication in Bearings. Lubrication Program Improvements evaluated.W/891130 Ltr1989-11-30030 November 1989 LER 89-019-01:on 890819,discovered That Div I Recirculation Fan Not Rotating Which Resulted in Decrease in Control Room Air Pressure.Caused by Lack of Lubrication in Bearings. Lubrication Program Improvements evaluated.W/891130 Ltr NRC-89-0249, LER 89-029-00:on 891023,half Scram Signal Received When Power Was Lost on Reactor Protection Sys Bus B,Resulting in Several ESFs Actuation.Caused by Location of Breaker Operating Switch in High Traffic area.W/891122 Ltr1989-11-22022 November 1989 LER 89-029-00:on 891023,half Scram Signal Received When Power Was Lost on Reactor Protection Sys Bus B,Resulting in Several ESFs Actuation.Caused by Location of Breaker Operating Switch in High Traffic area.W/891122 Ltr NRC-89-0246, LER 89-028-00:on 891020,eight safety-related Valves Failed Set Pressure Test.Cause Under Review.All Valves Removed for Testing Being Refurbished,Cleaned,Retested & Recertified to Be within Plant Accepted tolerances.W/891120 Ltr1989-11-20020 November 1989 LER 89-028-00:on 891020,eight safety-related Valves Failed Set Pressure Test.Cause Under Review.All Valves Removed for Testing Being Refurbished,Cleaned,Retested & Recertified to Be within Plant Accepted tolerances.W/891120 Ltr NRC-89-0244, LER 89-024-00:on 891019,recognized That Secondary Containment Dampers Not Tested as Required by Tech Spec 3.6.5.2.Caused by Operations Personnel Error.Event Critique to Be Included in Required Reading program.W/891120 Ltr1989-11-20020 November 1989 LER 89-024-00:on 891019,recognized That Secondary Containment Dampers Not Tested as Required by Tech Spec 3.6.5.2.Caused by Operations Personnel Error.Event Critique to Be Included in Required Reading program.W/891120 Ltr NRC-89-0194, LER 89-027-00:on 891015,reactor Bldg Hvac,Control Ctr HVAC & Drywell Floor & Equipment Drain Sumps Isolated & Standby Gas Treatment Sys & Noninterrruptalbe Control Air Compressors Started.Caused by Personnel error.W/891114 Ltr1989-11-14014 November 1989 LER 89-027-00:on 891015,reactor Bldg Hvac,Control Ctr HVAC & Drywell Floor & Equipment Drain Sumps Isolated & Standby Gas Treatment Sys & Noninterrruptalbe Control Air Compressors Started.Caused by Personnel error.W/891114 Ltr NRC-89-0193, LER 89-026-00:on 891010,control Ctr HVAC Shifted to Recirculation Mode of Operaton Due to Short Circuit.Caused by Failure of Lamp Filament When Being Tightened.Fuse & Lamp Replaced & Sys Returned to Normal operation.W/891109 Ltr1989-11-0909 November 1989 LER 89-026-00:on 891010,control Ctr HVAC Shifted to Recirculation Mode of Operaton Due to Short Circuit.Caused by Failure of Lamp Filament When Being Tightened.Fuse & Lamp Replaced & Sys Returned to Normal operation.W/891109 Ltr NRC-89-0192, LER 87-045-01:on 870908,fuse Removed Which Deenergized Dc Control Power to Bus 72C & Resulted in Loss of Power Supply to Swing Bus & LPCI Loop Selection Valves.Caused by Design Error.Undervoltage Relay Added & Training held.W/891106 Ltr1989-11-0606 November 1989 LER 87-045-01:on 870908,fuse Removed Which Deenergized Dc Control Power to Bus 72C & Resulted in Loss of Power Supply to Swing Bus & LPCI Loop Selection Valves.Caused by Design Error.Undervoltage Relay Added & Training held.W/891106 Ltr NRC-89-0190, LER 89-023-00:on 890924,personnel Inadvertently Caused Trip of Essential Safety Sys Buses 64B & 64C.Caused by Failure of Personnel Involved to Review Applicable Prints Prior to Performing Test.Event Reviewed w/personnel.W/891024 Ltr1989-10-24024 October 1989 LER 89-023-00:on 890924,personnel Inadvertently Caused Trip of Essential Safety Sys Buses 64B & 64C.Caused by Failure of Personnel Involved to Review Applicable Prints Prior to Performing Test.Event Reviewed w/personnel.W/891024 Ltr NRC-89-0189, LER 89-022-00:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse Blew.On 890928,reactor Bldg HVAC Isolated When Jumper Lifted Per Incorrect Work Plan Instruction.Caused by Personnel error.W/891023 Ltr1989-10-23023 October 1989 LER 89-022-00:on 890923 & 24,reactor Protection Sys Logic Actuations Occurred When Fuse Blew.On 890928,reactor Bldg HVAC Isolated When Jumper Lifted Per Incorrect Work Plan Instruction.Caused by Personnel error.W/891023 Ltr NRC-89-0186, LER 89-016-01:on 890711,Div 1 of RHR Svc Water Sys Declared Inoperable Due to Low Nitrogen Pressure for Cooling Tower Fan Brake.Caused by Leak in One Hose.Leaking Hose Replaced & Nitrogen Pressure restored.W/891006 Ltr1989-10-0606 October 1989 LER 89-016-01:on 890711,Div 1 of RHR Svc Water Sys Declared Inoperable Due to Low Nitrogen Pressure for Cooling Tower Fan Brake.Caused by Leak in One Hose.Leaking Hose Replaced & Nitrogen Pressure restored.W/891006 Ltr NRC-89-0185, LER 89-021-00:on 890906,local Leak Rate Testing of Containment Isolation Valves & Penetrations Exceeded Tech Spec Limit.Caused by Excessive Containment Isolation Valve Leakage Due to Degradation of valve.W/891006 Ltr1989-10-0606 October 1989 LER 89-021-00:on 890906,local Leak Rate Testing of Containment Isolation Valves & Penetrations Exceeded Tech Spec Limit.Caused by Excessive Containment Isolation Valve Leakage Due to Degradation of valve.W/891006 Ltr 1994-04-25
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217N4381999-10-25025 October 1999 Safety Evaluation Supporting Amend 17 to License DPR-9 ML20217P3551999-10-22022 October 1999 LER 99-S01-00:on 990922,loaded 9mm Handgun Was Discovered on Truck Cargo Area of Vehicle Inside Protected Area.Caused by Inadequate Vehicle Search.Guidance in Procedures & Security Training to Address Multiple Vehicle Searches Was Provided NRC-99-0095, Monthly Operating Rept for Sept 1999 for Fermi 2.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Fermi 2.With NRC-99-0067, Monthly Operating Rept for Aug 1999 for Fermi 2.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Fermi 2.With NRC-99-0065, Monthly Operating Rept for July 1999 for Fermi 2.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Fermi 2.With NRC-99-0088, Detroit Edison Co Enrico Fermi Atomic Power Plant,Unit 1 Annual Rept for Period 980701-990630. with1999-06-30030 June 1999 Detroit Edison Co Enrico Fermi Atomic Power Plant,Unit 1 Annual Rept for Period 980701-990630. with NRC-99-0064, Monthly Operating Rept for June 1999 for Fermi 2.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Fermi 2.With NRC-99-0062, Monthly Operating Rept for May 1999 for Fermi 2.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Fermi 2.With ML20206J9301999-05-10010 May 1999 SER Concluding That Util Adequately Addressed Actions Requested in GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Powered-Operated Gate Valves ML20206G5081999-05-0505 May 1999 Safety Evaluation Approving Request for Relief PR-8,Rev 2 on Basis That Licensee Committed to Meet All Related Requirements of ASME OM-6 Std & PR-12 on Basis That Proposed Alternative Will Provide Acceptable Level of Safety NRC-99-0022, Monthly Operating Rept for Apr 1999 for Fermi 2.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Fermi 2.With ML20205Q7141999-04-15015 April 1999 Safety Evaluation Supporting Amend 16 to License DPR-9 ML20205P9721999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Fermi 2 ML20204E0371999-03-17017 March 1999 Safety Evaluation Accepting Licensee Request for NRC Approval of Alternative Rv Weld Exam,Per Provisions of 10CFR50.55a(a)(3)(i) & 10CFR50.55a(g)(6)(ii)(A)(5) for Plant,Unit 2 for 40-month Period ML20204D0361999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Fermi 2 ML20198S3341999-01-0606 January 1999 Safety Evaluation Supporting Amend 15 to License DPR-9 NRC-99-0005, Monthly Operating Rept for Dec 1998 for Fermi 2.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Fermi 2.With ML20207B7491998-12-31031 December 1998 1998 Annual Operating Rept for Fermi 2 ML20205Q9621998-12-31031 December 1998 Revised Monthly Operating Rept for Dec 1998 for Fermi 2 NRC-99-0021, 1998 Annual Financial Rept for Detroit Edison Co. with1998-12-31031 December 1998 1998 Annual Financial Rept for Detroit Edison Co. with NRC-98-0153, Monthly Operating Rept for Nov 1998 for Fermi 2.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Fermi 2.With NRC-98-0160, Monthly Operating Rept for Oct 1998 for Fermi 2.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Fermi 2.With ML20154R2331998-10-21021 October 1998 Safety Evaluation Supporting Amend 13 to License DPR-9 ML20154L1031998-10-14014 October 1998 Safety Evaluation Accepting Licensee Response to NRC Bulletin 95-002, Unexpected Clogging of Residual Heat Removal Pump Strainer While Operating in Suppression Pool Cooling Mode NRC-98-0139, Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With ML20154H8161998-09-30030 September 1998 Rev 0 to COLR Cycle 7 for Fermi 2 ML20153B8811998-09-18018 September 1998 Safety Evaluation Accepting Request for Relief from Certain Requirements of ASME Boiler & Pressure Vessel Code,Section Xi,For Plant,Unit 2 ML20151X0651998-09-11011 September 1998 Safety Evaluation Re Inservice Testing Program Relief Request VR-63 for Plant NRC-98-0111, Monthly Operating Rept for Aug 1998 for Fermi 2.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Fermi 2.With ML20153B7921998-08-31031 August 1998 Rev 0 to Fermi 1 Sar ML20237E1171998-08-25025 August 1998 Safety Evaluation Accepting Licensee Relief Requests for First 10-yr Interval Inservice Insp Nondestructive Exam Program ML20236X8611998-08-0505 August 1998 SER Related to Revised Feedwater Nozzle Analysis to Facility Operating License NPF-43,Enrico Fermi Nuclear Power Plant, Unit 2 NRC-98-0109, Monthly Operating Rept for July 1998 for Fermi 21998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Fermi 2 ML20236K3261998-07-0101 July 1998 SER Accepting Licensee Response Related to Revised Feedwater Nozzle Analysis to License NPF-43 for Enrico Fermi Nuclear Power Plant,Unit 2 NRC-98-0097, Monthly Operating Rept for June 1998 for Fermi,Unit 21998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Fermi,Unit 2 NRC-98-0127, Annual Rept for Period 970701-9806301998-06-30030 June 1998 Annual Rept for Period 970701-980630 NRC-98-0079, Monthly Operating Rept for May 1998 for Fermi 21998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Fermi 2 NRC-98-0076, Monthly Operating Rept for Apr 1998 for Fermi 21998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Fermi 2 NRC-98-0072, Monthly Operating Rept for Mar 1998 for Fermi 21998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Fermi 2 NRC-98-0050, Monthly Operating Rept for Feb 1998 for Fermi 21998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Fermi 2 NRC-98-0019, Monthly Operating Rept for Jan 1998 for Fermi 21998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Fermi 2 ML20198L4241998-01-0808 January 1998 Safety Evaluation Accepting Proposed Rev 2 to Relief Request VR-51 Under Fermi 2 Pump & Valve Inservice Testing Program Per 10CFR50.55a(f)(6)(i) for First 10-yr Interval NRC-98-0015, Monthly Operating Rept for Dec 1997 for Fermi 21997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Fermi 2 ML20217N3821997-12-31031 December 1997 Annual Operating Rept for 970101-1231 NRC-98-0053, 1997 Annual Financial Rept for Detroit Edison Company1997-12-31031 December 1997 1997 Annual Financial Rept for Detroit Edison Company ML20205Q9601997-12-31031 December 1997 Revised Monthly Operating Rept for Dec 1997 for Fermi 2 NRC-97-0141, Deficiency Rept Re Malfunction of EDG Number 11 Automatic Voltage Regulator (AVR) Printed Circuit Board Rev B,Due to Failure of Operational Amplifier U8 Chip.Avr Board Rev B Was Sent Offsite to Independent Engineering Facility1997-12-23023 December 1997 Deficiency Rept Re Malfunction of EDG Number 11 Automatic Voltage Regulator (AVR) Printed Circuit Board Rev B,Due to Failure of Operational Amplifier U8 Chip.Avr Board Rev B Was Sent Offsite to Independent Engineering Facility ML20197A9921997-12-15015 December 1997 Rev 0 to Efp,Unit 1 Fermi 1 Sar NRC-97-0131, Monthly Operating Rept for Nov 1997 for Fermi 21997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Fermi 2 ML20248H1151997-10-31031 October 1997 Rev 1 to Colr,Cycle 6 for Fermi 2 1999-09-30
[Table view] |
Text
p"* s N .
L a ..
i r;m ,s or.:e f'. oea EY,'IE$,1,0.,, 10CFR50.73
("p Nb ,
October 24 1989 ' m J NRC-89-0190 U. S. Nuclear Regulatory Commission Attention Document Control Desk Washington, D.C. 205$5 Reference Fermi 2 NRC Docket No. $0-341 Facility Operating License No. NPF-43 Subject Licencee Event Report (LER) No. 89-023-00 Please find enclosed LER No. 89-023-00 dated October 24 1989 for a reportable event that occurred on September 24, 1989. A copy of this LER is also being sent to the Regional Adm!.nistrator. USNRC Region III.
If you have any questions, please contact Patricia Anthony at (313) 586-1617.
Sincerely.
Enclosures NRC Forms 366 366A cct A. B. Davis J. R. Eckert R. C. Knop W. G. Rogers J. F. Stang Wayne County Emergency Management Division l
l l
TE} ,
I '
I S
O
- b 8 U 6 wuC48 Am hl996tomy Cansessettoes C PPhDVIp paing wo. 3)e6 pigs a UCENSEE EVENT REPORT (LER) 8 " *'a' * ' '8"" !
9 ACILIT V tea.pt 41t 54006 8I NWh0Dt h 43) _ raps T Fermi 2 016 t o 1010131411 1lorb15 -
i nt 4 8 ... ;
less of Power to Division I Due to Personnel Error By Belay Division '
tytWT DAYS (DI L t h hutset h st) DIPORT Daf t (,e 01Mt h # ACILITit t sWVOLviD 16l MDkTM DAY 9tAh ViaW '$
m
. "OhlH! D'Y %IAR E0'" O I ' 8"#M"t h '0' N/A 0 161010101 l 1
"- ~
0l9 2l4 89 8l9 0l2l3 0l0 1l 0 2l4 8 l9 N/A 0 1 61 0 1 0:0 i l l
,,,,,,,,,,, vue atrontissonMirrtDevnev&=,to v I u ovia0.,4wn o, o Can s ,c w .. .,,* ,.,.. , nii
" * *
n .a.i.i no n.imn.i gn.> n .ni.i,Hui nui.ini wn.iun.i n eu.i O I00 m mi.in na so wi.im n n aimn.m g
me3, p.,y A.7p ,e n i.innai n n.iuno nn imn..nAi n .06 ton 1Hwi 60 73w'WHid 90 78to,Wli.6dentI
.,n n., ....,...., .....,,.,
Lectk64 0 COW 1&cf D0h TMit 4t h titi N1WE TittPHOht hvM6tri Patt1 cia Anthony, Compliance Engineer '"*'
3l13 51 86 i -i l 6 1 i i 171 COMPLItt ONE LINE 90R 4 ACM CDe4PONIWT f AILUAE DESchl6tD 4N TM.8 DIP 0ft? H3i
" To$,'nY CALtt tvittv COM*0NikT $0 C Atill $t tilw Coup 0Nt hi
"$N$C H{ ,fpg a i l I I l ._ l I i i i i l i i i l l l l 1 l 1 l l 1 i i l i 1 SurPLEME NT AL htP0mf t KPECTE D (14) MONYM DAY 4 TAR
& DwliSIDN Yit 404 von rompen $ K94CilO $ltMI$$20N DAT(I NO l l l AS$TxACT <&sut to fe00 serse 4 e, appresemes'y Fermea sgeavere frerwe, rwa Aaesi tit)
On September 24 1989 Detroit Edison Relay personnel were performing a check of the 13.2 kv switchgear while the plant was defueled. While testing a relay string, personnel Inadvertantly caused the trip of Essential Safety System Buses 64B and 640.
This caused various actuations/isolations of engineered safety features, including the start and loading of Emergency Diesel Generator 11. In addition. power to other Division I equipment, including the "A" Fuel Pool Cooling Pump, was lost. Operators took prompt actions to restore power to the necessary components and systems.
This event was caused by the failure of the personnel involved to review the applicable prints prior to performing the test. This event was reviewed by the involved personnel and their management. Any disciplinary action warranted will be l cdministered in accordancc with company policy. In order to l disseminate the lessons learned during this event, it was be l reviewed during the October Relay monthly meeting.
l
=ac ..,. m
' 88' . - . _ i
m a
' j c
- g. '
us mi_a ...ou- a UCENSEE WENT CEPORT (LER) TEXT CONTINUATION peaovco owe o mo-4*
[ < c e .w. i t -m .- m m u.a . .. ,,..,,,,..., ...n, naa WA" tm I renui a o lo lo lo le l 31411 81 9 -
01213 -
0 10 01 2 0F 015 w -. m ,nn l
Initial Plant conditions:
! Operational Conditions. defueled
, Ri, 'or Power 0 parcent t
JR _ ser Pressure: O psis Reactor Temperature 85 degrees Fahrenheit i
Description ut occurrences
. On September 24, 1989. Detroit Edison Relay Division personnel
! were performing a check of the 13.2 kv switchgear [(EA)(SWGR))
which is located at Fermi I. Part of the testing includes verifying the function of the. relay controls (RLY) listed on Detroit Edison drawings as circuit positions A. B. C and D.
Foritions b. C and D are tested to verify that under fault conditions where the respective breaker (BKR) does not open. the bus feed to position A does open. This test requires the manual operation of the protective tripping relay and a set of instantaneous operating relays designated as phase-50's (see attached figure). This action energises the coil of a d.c. ,
auxiliary relay designated as the 96 relay. In addition, position l D has another relay. 1CJ94 in parallel with relays phase-50 and j 96 which does not appear on positions B and C. !
When the technician was manually simulating a fault on the i protective relay for position D. he energized relay 1CJ94 which trippel Essential Safety System Buses 64B and 64C (BU) at 1643 hours0.019 days <br />0.456 hours <br />0.00272 weeks <br />6.251615e-4 months <br />. As a result, power was lost to Division I and various engineered safety features were actuated / isolated. These I
( actuations/isolations included automatic start and loading of .
Emergency Diesel Generator 11 [(EK)(DG)). isolation of the )
Secondary Containment (NF) and isolation of primary containment valve groups 13 and 14 [(JM)(ISV)). Also, power was lost to the "A" Fuel Pool Cooling Pump [(DA)(P)). Division I Battery Chargers ,
[(EI)(BYC)) and Modular Power Unit (EC) 1. Turbine and Radweste Building Heating. Ventilating and Air Conditioning Systems ~
[(VH)(VK)) also tripped. Other engineered safety features q P received actuation signals but did not respond due to their being i out of service during the outages i.e.. the Emergency Diesel !
Generator 12 was out of service for maintenance. Control Center !
Heating. Ventilating and Air Conditioning System (VI) was already l in. recirculation mode and primary containment isolation valve i i
groups 2 10 12 15 16, 17 and 18 were already isolated. A !
half-scram signal would have been received due this this event. 1 l but one was already present since the Reactor Protection System l (RPS)(JC) was out of service for maintenance. I I
l gne. g 3 a. 'U.S. Croe ID..al2D 5 9 4001
_ _ . _ . . _ - - - - - ~ - , - . - - , ,- ,
- _ .- .- - - . - ~ .
Sfst pom asta . US. IshttA3 #699LatO,V COMauges00f UCENSEE EVENT REPORT ILER) TEXT CONTINUAT60N **awso owe wo mo-eine i t 6 .. . :. w . i L . .n am e ., uvuu. in ,,,,,o.,,, ....,,,
n- "uw 22: l Fermi 2 !
o is 1010101314 l 1 81 9 -
o l 2l3 -
olo ol3 or ol5 ;
mm c == . o= = w we n. nuu nn ,
e Ar 1725 hours0.02 days <br />0.479 hours <br />0.00285 weeks <br />6.563625e-4 months <br />. power was restored to RPS motor-generator set "A" .
and Division I of RPS. Ths Shift Technical Advisor verified that !
the proper isolations had occurred. Fuel Pool Cooling Pump "A" ;
was restarted at 1741 hours0.0202 days <br />0.484 hours <br />0.00288 weeks <br />6.624505e-4 months <br />. Power to the battery chargers was :l restored by 1757 hours0.0203 days <br />0.488 hours <br />0.00291 weeks <br />6.685385e-4 months <br /> and Emergency Diesel Generator 11 was {
un3oaded and shutdown by 1955 hours0.0226 days <br />0.543 hours <br />0.00323 weeks <br />7.438775e-4 months <br />. ,
cause of Event:
This event was caused by personnel error on the part of Relay [
personnel (non-nuclear division, utility). It was assumed that .
.the logic for' circuit position D was identical to that of ,
positions B and C which had been successfully tected as part of !
the same evolution. !
A contributing factor to this event was the failure to follow :
normal work practices for Detroit Edison Relay personnel. These i work practices include reviewing the prints and preparing a check i list prior to starting work. The personnel involved did not do j this for circuit position D. <
i
' Analysis of Event:
l Since this type of testing is only performed while the plant is !
shutdown, the effects of this event need only be considered under ;
those conditions. The affected components and systems that !
actuated during this event responded per their design. Power to !
Division II components was unaffected by this event. Fuel Fool i Cooling Pump "B". which is powered from Division II. was available i to provide fuel pool cooling. This is a 100% capacity pump. The !
ventilating systems were restored to service without any adverse i consequences on the work environment in the plant. The systems !
such as CCHVAC which did not respond to this event were j conservatively aligned. The loss of Modular Power Unit 1 did not j adversely impact the operators; ability to respond to this event. j As a result, this event had no impact on the health and safety of L the public or plant personnel or the safe operation of the plant. l i
Corrective Actions:
As described previously, the actuated equipment was restored. The f personnel involved in this event reviewed the sequence of events !
with Relay Division management. Any disciplinary action warranted l will be administered in accordance with company policy.
In order to disseminate the lessons learned during this event, this event was reviewed during the Relay's monthly meeting in ;
October of 1989. t
.ac o2u w.. .v.. . cw, i.. 4 n 4.. mm o su _
f '
I g' '
v . auce u.um , o- .o., l UCENSEE EVENT REPORT ILE'J TEXT CONTINUAT60N c*aov io ov. wo nt.o-cies
....,,3,,.
,,,v..,., ......, i
~
,9iff 6 mee esse 4 #souper, ame asesummer 44C #enn mitih o ls l0 lc l0 l 3l 41 8l9 -
0 l 213 -
0l0 ] ui4 lotl 015 l
i General Employee Training. Orientation "A". which includes the topic of procedural compliance, will be given to Detroit Edison personnol not normally assigned to Fermi 2 before performing work. This will be incorporated into Orientation "A" by January 1 1990.
l Previous Similar Events: !
None. l l
1 t
.h f
v f
i i
E i
f l
l 6
i I
,# C #0I3 assa V 8+ GFD I *Si
l h,'* *'*
men .
v4.wuotit.aeto u tav~ - - - !
UCENSEE EVENT REPORT ILETJ TEXT CONTINUATION eraovio ow wo mo-eios i i, . .
avials. we !
OG"', ff t hhb86 Ill Doctt18800ADen 486 tem espaWOR tel PA04 45)
.. - .. w. . = ;
+ Fermi 2
,w a n .
015101010131411 819 -
01213 -
0l0 015 OF 0 15 u - .~,.a w,c o ,, am,w,
)
1 PROTECTIVE RELAY CONTACTS .
'" : #-50 CONACTS 1
)
M RELAY I i
J Ptllfl0NS B AND C !
e l
+
A PROTECTIVE
(# ICJN CUT our i ItELAY comACTS o TRIP FOR
-~
F50 CONT ACTS""~_ ; . .- ~ ~ - 648 f iCan ! .............................r- _ !
M RELAY .....#kM............i
' T_ :
l
[ 1 L i TRIP FOR l 64c l,
Pesm0N9 l I
i l
l i
I
. . . m , . . . . , m e , . i.-,.
gro- . . - . _ . . . . _ . . . - . - . . .. _ - _ - - _.. __ - . _ .... _