IR 05000255/2025004

From kanterella
(Redirected from ML25260A036)
Jump to navigation Jump to search
Restart Inspection Report 05000255/2025004
ML25260A036
Person / Time
Site: Palisades Entergy icon.png
Issue date: 09/17/2025
From: April Nguyen
NRC/RGN-III/DORS
To: Mlynarek M
Palisades Energy
References
IR 2025004
Download: ML25260A036 (1)


Text

SUBJECT:

PALISADES NUCLEAR PLANT - RESTART INSPECTION REPORT 05000255/2025004

Dear Mr. Michael Mlynarek:

On August 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the Palisades Nuclear Plant. The enclosed inspection report documents the inspection results, which the inspectors discussed on September 9, 2025, with yourself and other members of your staff.

No violations of more than minor significance were identified during this inspection.

On June 13, 2022, Palisades ceased permanent power operations and subsequently removed all fuel from the reactor, as detailed in the letter from Entergy to the NRC, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel, (ADAMS Accession No. ML22164A067). On September 28, 2023, Holtec Decommissioning International, LLC (Holtec) submitted a letter to the NRC requesting exemptions from certain portions of the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 50.82(a)(2) to pursue the potential reauthorization of power operations at Palisades (ADAMS Accession No. ML23271A140).

On July 24, 2025, the NRC approved an exemption from the requirements of 10 CFR 50.82(a)(2), as detailed in the letter, Palisades Nuclear Plant - Exemption from the Requirements of 10 CFR 50.82(a)(2) Concerning the Prohibition to Operate and Emplace Fuel in the Reactor Vessel, (ADAMS Accession No. ML25163A182) and a set of licensing actions supporting reauthorization of Palisades Nuclear Plant. On August 25, 2025, Palisades notified the NRC that they rescinded their 10 CFR 50.82(a)(1) certification, which removed the prohibition on operation and emplacement of fuel in the reactor (ADAMS Accession No. ML25237A317). Palisades also implemented the set of licensing actions to support reimplementation of their operational licensing basis.

On August 25, 2025, the NRC transitioned oversight of Palisades to the Reactor Oversight Process (ROP).

September 17, 2025 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, April M. Nguyen, Lead Palisades Restart Team Division of Operating Reactor Safety Docket No. 05000255 License No. DPR-20 Enclosure:

As stated cc: Distribution via LISTSERV Signed by Nguyen, April on 09/17/25

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) performed inspection activities of the licensees performance associated with the return to an operational status.

List of Findings and Violations

None.

Additional Tracking Items

None.

PLANT STATUS

On August 25, 2025, Palisades notified the NRC that they rescinded their 10 CFR 50.82(a)(1)certification, which removed the prohibition on operation and emplacement of fuel in the reactor.

Palisades also implemented the set of licensing actions to support reimplementation of their operational licensing basis. On August 25, 2025, the NRC transitioned oversight of Palisades to the Reactor Oversight Process (ROP).

The NRC is conducting inspections to evaluate and assess the licensees activities for restoration to an operating status. The resident inspectors, as well as supplemental inspectors, continue to provide daily oversight of the restart activities occurring at the site.

The unit ended the inspection period in a defueled status.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the referenced inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted.

Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown (IP Section 03.01)

The inspectors evaluated system configurations during a partial walkdown of the following system/train:

(1) emergency diesel generator (EDG) 1-2 during maintenance on EDG 1-1 on August 6, 2025

71111.07 - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01)

The inspectors observed and evaluated the licensees inspection and maintenance activities of the following heat exchanger:

(1) component cooling water (CCW) heat exchanger E-54B from August 12, 2025 through August 22, 2025 71111.08P - Inservice Inspection Activities (PWR)

From July 1 through August 31, 2025, the inspectors observed and verified the licensees nondestructive examination (NDE) and repair/replacement activities of the reactor vessel closure head, Alloy 600 weld mitigation activities, and steam generator tube plugging, stabilization, and sleeving, conducted in accordance with the requirements of the ASME Code Section XI and other guidance documents. The purpose of these inspections was to verify that the reactor coolant system boundary, reactor vessel closure head, steam generators, and risk-significant piping system boundaries are appropriately monitored for degradation. The inspectors also verified that the examination results were thoroughly reviewed and appropriately evaluated, and that required corrective actions to address identified indications and defects are being appropriately implemented. During this quarter, the licensee conducted repair/replacement activities for the reactor vessel closure head, steam generator tubes, and Alloy 600 welds in the primary coolant system and in other areas. Further NRC inspections will monitor repair/replacement activities as they are conducted.

The inspectors verified that the following NDE and repair/replacement activities were conducted appropriately per the ASME Code or required standard, and that any potential indications and defects were identified and evaluated at the proper thresholds:

Nondestructive Examination and Welding Activities (IP Section 03.01)

(1) reactor vessel inside surface ultrasonic examination Vessel Upper Head Penetration Inspection Activities (IP Section 03.02)
(1) reactor head penetration Alloy 690 nozzle repair welds ultrasonic examinations
(2) reactor head vent line repair welding Steam Generator Tube Inspection Activities (IP Section 03.04)
(1) steam generators A and B tube sleeving and eddy current testing

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management (IP Section 03.01)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned work activities to ensure configuration changes and appropriate work controls were addressed:

(1) risk management for work activities with the following equipment out of service:

EDG 1-1 maintenance outage; battery charger 1; CCW pump P-52A; fire pump P-9B; and service water pump P-7C during the work week of August 11, 2025

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01)

The inspectors verified that the following outage activities important to safety were appropriately managed:

(1) control of work activities and foreign material exclusion control during steam generator B nozzle dam installation on July 1, 2025
(2) primary coolant pump P-50B motor heavy lift activities in containment and spent fuel pool areas during work from July 17, 2025, to August 13, 2025
(3) main generator rotor heavy lift and installation activities on August 21, 2025 Additionally, the inspectors verified that the licensee managed fatigue by ensuring workers subject to the requirements in 10 CFR 26 Subpart 4 met all the requirements listed therein.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01)

(1) post-maintenance testing following EDG 1-1 work window during the week of August 11, 2025 Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02)
(1) testing of FLEX pump P-990 and FLEX generators K-1 and K-2 on July 29 and 30, 2025
(2) testing of FLEX pump P-1003 on August 27, 2025

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution The inspectors observed and evaluated the licensees performance during:

(1) emergency preparedness exercise on July 29, 2025 OTHER BASELINE ACTIVITIES

71152 - Problem Identification and Resolution

System Return to Service During the inspection period, the inspectors continued reviews of Phases I and II of the licensees system return to service (SRTS) plans. The SRTS plans document licensee activities to verify that the configuration and condition of systems, structures, and components (SSCs)are consistent with the design and licensing bases to support potential restart. The inspectors reviewed Phases I and II of the SRTS plans, which include areas such as licensing and design-basis functions, system material conditions, reviewing open and deferred work prior to shutdown, and program applicability. The inspectors conducted these reviews using IP 71152, Problem Identification and Resolution, and IP 71111.21M, Comprehensive Engineering Team Inspection (CETI), as applicable.

The inspectors commenced reviews of the SRTS plans for the following systems:

  • datalogger The inspectors completed initial reviews of the SRTS plans for the following systems:
  • alternate shutdown panel
  • containment air coolers
  • spent fuel pool and auxiliary building HVAC These systems were selected based on the importance of the SSCs during normal and emergency plant operating conditions, risk significance and defense-in-depth of the SSCs specific functions and required work/modifications of the SSCs scheduled prior to potential restart.

The inspectors evaluated the initial SRTS plans for each system to identify if planned licensee activities will verify that the configuration and condition of the SSCs are consistent with the proposed operational design and licensing bases to support restart and verify readiness of the SSCs to support a return to service. The inspectors noted that the SRTS plans are intended to be living documents with a phased approach to SRTS. As the licensee progresses through the SRTS phases, the SRTS plans will undergo additional reviews by NRC inspectors to ensure appropriate SSC restoration and operability/functionality.

INSPECTION RESULTS

No additional inspection results.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On September 9, 2025, the inspectors presented the inspection results to M. Mlynarek, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Procedures

SOP-22

Emergency Diesel Generators

71111.07A

Corrective Action

Documents

25011445

E-54B ECT Possibly Affected by Tube Cleanliness

08/20/2025

25010690

RVCH UT Inspection Results

07/26/2025

CR 2024-3591

Rejectable PT Indications

2/17/2024

CR 2025-1653

Tube 105-112 (row-col) Sleeve Mid Expansion Inadvertently

Performed Twice

06/13/2025

Corrective Action

Documents

CR 2025-1661

Palisades SG A, 05H TSP Sleeve Mid Expansion

Inadvertently Performed Twice

06/11/2025

NDE Reports

180-9392377-000

Palisades Unit 1 Restart RPV ID Cladding Ultrasonic

Examination Final Report

54-ISI-619-001

Automated Ultrasonic Examination of Open Tube RPV

Closure Head Penetrations - Palisades Specific

71111.08P

Procedures

PAL 1 D28 ETSS

  1. 2

3-Coil + Point Examination Technique Specification Sheet

71111.13

Corrective Action

Documents

25011236

Sinkhole Starting Near Walkway

08/14/2025

25011226

Rigging plan change for P-50B Motor installation

08/13/2025

Corrective Action

Documents

25011481

Main Generator Rotor Rigging Jacket Tear

08/21/2025

FHS-M-23

Movement of Heavy Loads in the Spent Fuel Pool Area

FHS-M-24

Movement of Heavy Loads in the Containment Building Area

MA-314

Movement of Heavy Loads in the Turbine Building

RFL-SG-2

S/G Primary Nozzle Dam Installation and Removal

71111.20

Procedures

WI 00584410-06

Primary Coolant Pump Motor Receipt, Movement, and

Preoperational Checks

06/17/2025

25010759

Working Order Enhancements for FLEX Hale Pump

07/29/2025

25010942

Pin Hole Leak Found on Hale pump P-990

08/04/2025

25010946

Yr FLEX Pump Testing Not Completed

08/04/2025

25010960

Automatic Load Trip Setting Was Too Low

08/04/2025

25011229

EDG 1-1 Governor Oil Drop During SOP-22 Testing

08/14/2025

71111.24

Corrective Action

Documents

25011239

DBA Load Exhaust Temperatures Missed During MO-7A-1

08/13/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

25011267

This CR is to Document the Replacement of EMB-0116D

(Q1) with a Q4 motor

08/14/2025

25011274

CK-DE412 OUTLET FITTING HAS LEAK

08/14/2025

25011278

XJ-802 Small Leak ~ 5 Drops A Minute

08/14/2024

25011286

Unexpected Alarm EK-0515

08/14/2025

OPS-201

Diverse and Flexible Coping Strategies (FLEX)

Program Document

OPS-203

Palisades FLEX Program Document

Procedures

SOP-22

Emergency Diesel Generators

00583510

FLEX Standby PM: K-1 FLEX Three Year Load Test (FSB A)

08/11/2025

00583511

FLEX Standby PM: K-2 FLEX Three Year Load Test

08/11/2025

00583512

FLEX Standby PM: P-990 Three Year Performance Test

(FSB B)

08/11/2025

Work Orders

00583513

FLEX Standby PM: P-1003 Three Year Performance Test

(FSB A)

08/27/2025

25010825

EP Graded Exercise Objective Unsatisfactory

07/30/2025

25010827

EP Graded Exercise Evaluation Criteria, N.2.3, Needs

Improvement

07/30/2025

25010828

EP Graded Exercise Objective Unsatisfactory

07/30/2025

25010830

EP Graded Exercise Evaluation Criteria Needs Improvement

07/30/2025

25010833

EP Graded Exercise Evaluation Criteria B.3.2 Needs

Improvement

07/30/2025

25010834

EP Graded Exercise Evaluation Criteria Needs Improvement

07/30/2025

25010835

EP Graded Exercise Evaluation Criteria I.1.5 Needs

Improvement

07/30/2025

71114.06

Corrective Action

Documents

25010837

EP Graded Exercise Objective, K.2 Needs Improvement

07/30/2025

PLP-SRTSP-ASP

Alternate Shutdown Panel

PLP-SRTSP-CIS

Containment Isolations and Penetrations (Airlocks)

PLP-SRTSP-CRS

Containment Air Coolers System

PLP-SRTSP-DEH

Digital Electro-Hydraulic Controls

PLP-SRTSP-DTA

Datalogger

PLP-SRTSP-ELU

Emergency Lighting

71152

Miscellaneous

PLP-SRTSP-VAS

Spent Fuel Pool and Auxiliary Building HVAC

0