IR 05000237/2024006

From kanterella
(Redirected from ML25069A720)
Jump to navigation Jump to search
Annual Assessment Letter for Dresden Nuclear Station Units 2 and 3 Report 05000237/2024006 05000249/2024006
ML25069A720
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 03/11/2025
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To: Rhoades D
Constellation Energy Generation
Shared Package
ML24353A190 List:
References
IR 2024006
Download: ML25069A720 (1)


Text

March 11, 2025

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR DRESDEN NUCLEAR STATION, UNITS 2 AND 3 (REPORT 05000237/2024006; 05000249/2024006)

Dear David Rhoades:

The NRC has completed its end-of-cycle performance assessment of Dresden Nuclear Power Station, Units 2 and 3, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2024, through December 31, 2024. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.

The NRC determined the performance at Dresden Nuclear Power Station, Units 2 and 3, during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2026.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

This letter and its enclosure will be made available for public inspection and copying at ADAMS Public Documents l NRC.gov and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding. Please contact me at 630-829-9732 with any questions you have regarding this letter.

Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000237 and 05000249 License Nos. DPR-19 and DPR-25 Enclosure:

Inspection Plan cc: Distribution via LISTSERV Signed by Ruiz, Robert on 03/11/25

ML25069A720

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available OFFICE RIII NAME RRuiz:sw DATE 03/11/2025

Site Inspection Activity Plan 07200037 - Dresden (ISFSI)

01/01/2025 - 12/31/2026 Unit Start End Activity CAC Title Staff Count ISFSI Cask Loading Inspection

3/17/2025 3/21/2025 IP 60855 001001 Operation Of An ISFSI ISFSI License Renewal Inspection

4/21/2025 4/25/2025 IP 60859 001921 Independent Spent Fuel Storage Installation (ISFSI) License Renewal Inspection Prepared on 2/28/2025 12:28:46 PM 1 of 3

Site Inspection Activity Plan Dresden 01/01/2025 - 12/31/2026 Unit Start End Activity CAC Title Staff Count Material Control and Accounting

2,3 1/1/2025 12/31/2025 IP 71130.11 000742 Material Control and Accounting (MC&A)

Biennial Problem Identification and Resolution Inspection

2,3 3/3/2025 3/21/2025 IP 71152B 000747 Problem Identification and Resolution Dresden April 2025 Initial License Examination

2,3 3/9/2025 3/13/2025 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

2,3 4/13/2025 4/19/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Force-On-Force Planning and Exercise Weeks - DRE

2,3 3/10/2025 3/14/2025 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 2,3 3/31/2025 4/4/2025 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Emergency Preparedness Exercise Inspection / Performance Indicator Verification

2,3 2/10/2025 4/11/2025 IP 71114.08 000723 Exercise Evaluation - Scenario Review 2,3 4/7/2025 4/11/2025 IP 71114.07 000722 Exercise Evaluation - Hostile Action (HA) Event 2,3 4/7/2025 4/11/2025 IP 71151 001397 Performance Indicator Verification Functional Engineering Inspection - Fire Protection

2,3 4/14/2025 5/2/2025 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

Radiation Protection Baseline Inspection

2,3 5/5/2025 5/9/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program 2,3 5/5/2025 5/9/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Security Baseline Inspection

2,3 8/18/2025 8/22/2025 IP 71130.02 000734 Access Control 2,3 8/18/2025 8/22/2025 IP 71130.14 000743 Review of Power Reactor Target Sets 2,3 8/18/2025 8/22/2025 IP 71151 001338 Performance Indicator Verification 2,3 10/13/2025 10/17/2025 IP 71130.07 000739 Security Training 2,3 10/13/2025 10/17/2025 IP 71130.09 001656 Security Plan Changes Eplan and EAL Changes Review

2,3 11/1/2025 12/31/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Radiation Protection Baseline Inspection

2,3 11/3/2025 11/7/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 2,3 11/3/2025 11/7/2025 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 2,3 11/3/2025 11/7/2025 IP 71124.04 000728 Occupational Dose Assessment Emergency Preparedness Baseline Inspection / Performance Indicator Verification

Prepared on 2/28/2025 12:28:46 PM 2 of 3

Site Inspection Activity Plan 2,3 2/9/2026 2/13/2026 IP 71114.02 000717 Alert and Notification System Testing 2,3 2/9/2026 2/13/2026 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 2,3 2/9/2026 2/13/2026 IP 71114.05 000720 Maintenance of Emergency Preparedness 2,3 2/9/2026 2/13/2026 IP 71151 001397 Performance Indicator Verification Functional Engineering Inspection - Commercial Grade Dedication

2,3 3/2/2026 3/20/2026 IP 71111.21N.03 001808 Commercial Grade Dedication Dresden April 2026 Initial License Exam

2,3 3/15/2026 3/21/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

2,3 4/19/2026 4/25/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Security Baseline Inspection

2,3 4/6/2026 4/10/2026 IP 71130.05 000737 Protective Strategy Evaluation Corporate Security Baseline Inspection

2,3 4/6/2026 4/10/2026 IP 71130.08 000740 Fitness-For-Duty Program Radiation Protection Baseline Inspection

2,3 4/20/2026 4/24/2026 IP 71124.05 000729 Radiation Monitoring Instrumentation Security Baseline Inspection

2,3 7/13/2026 7/17/2026 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance Dresden 2026 Biennial Requalification Program Inspection

2,3 8/16/2026 8/22/2026 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Inservice Inspection - Unit 3

3 10/26/2026 11/6/2026 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

Security Baseline Inspection

2,3 10/26/2026 10/30/2026 IP 71130.02 000734 Access Control 2,3 10/26/2026 10/30/2026 IP 71130.09 001656 Security Plan Changes 2,3 10/26/2026 10/30/2026 IP 71151 001338 Performance Indicator Verification EAL & EPlan Changes Review

2,3 11/1/2026 12/31/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Radiation Protection Baseline Inspection

2,3 11/2/2026 11/6/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 2,3 11/2/2026 11/6/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 2,3 11/2/2026 11/6/2026 IP 71124.04 000728 Occupational Dose Assessment Prepared on 2/28/2025 12:28:46 PM 3 of 3