ML25105A220

From kanterella
Jump to navigation Jump to search
Summary of the April 9 2025 Public Outreach to Discuss the NRC 2024 End-Of-Cycle Plant Performance Assessment of Dresden Nuclear Power Station Units 2 and 3
ML25105A220
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 04/17/2025
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To:
Shared Package
ML24353A190 List:
References
Download: ML25105A220 (1)


Text

LICENSEE:

Constellation Energy Generation, LLC FACILITY:

Dresden Nuclear Power Station, Units 2 and 3

SUBJECT:

SUMMARY

OF THE APRIL 9, 2025, PUBLIC OUTREACH TO DISCUSS THE NRC 2024 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 On April 9, 2025, from 5:00 p.m. to 6:00 p.m. (CDT), an information meeting (open house) with a question-and-answer session was held by representatives of the U.S. Nuclear Regulatory Commission (NRC) to provide the public with information on the 2024 End-of-Cycle plant performance assessment of the Dresden Nuclear Power Station, Units 2 and 3, with general information on the NRC. The open house was held at the Morris American Legion Post 294 in Morris, Illinois. The NRC representatives discussed plant performance with members of the public and a number of state employees. Representatives from Constellation Nuclear were also present at the event.

The NRC discussed their assessment of Dresdens performance during the public outreach.

The assessment information was documented in the March 11, 2025, End-of-Cycle Assessment Letter (ADAMS Accession Number ML25069A720). Copies of the above letter and other brochures and fact sheets were made available to the public in attendance. Throughout the open house, members of the public and state and local government officials were given the opportunity to ask questions of NRC staff.

Robert Ruiz, Branch Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 50-237 and 50-249 License Nos. DPR-19 and DPR-25 cc: Distribution via LISTSERV April 17, 2025 Signed by Ruiz, Robert on 04/17/25

SUBJECT:

SUMMARY

OF THE APRIL 9, 2025, PUBLIC OUTREACH TO DISCUSS THE NRC 2024 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 DISTRIBUTION:

Alejandro Alen Arias RidsNrrDorlLpl3 RidsNrrPMDresden Resource RidsNrrDroIrib Resource Jack Giessner Mohammed Shuaibi Diana Betancourt-Roldan Harral Logaras Bryan Bergeon David Curtis Jared Heck R3-DORS ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML25105A220 OFFICE RIII RIII NAME NShah:gmp RRuiz DATE 04/16/2025 04/17/2025 OFFICIAL RECORD COPY

Enclosure PUBLIC MEETING ATTENDEES April 9, 2025 U.S. Nuclear Regulatory Commission R. Ruiz, Chief, Reactor Projects Branch 1 J. Steffes, Senior Resident Inspector J. Meszaros, Resident Inspector N Shah, Senior Project Engineer, Branch 1 P. Chandrathil, Public Affairs Officer G. Moore-Powe, Resident Inspector Office Assistant Constellation Energy Generation, LLC P. Dempsey S. Johnson M. Currier R. Ward D. Murphy M. McGuire K. Goff B. Hess T. Noah State and Local Government N. Norton, Grundy Economic Development Council, President & CEO A. Hogan, Grundy Economic Development Council, Vice President of Development S. Hogan-Entwistle, Illinois State Senator Sue Rezin, Chief of Staff M. Porfirio, Illinois Emergency Management Agency (IEMA), State Resident Inspector Members of the Public C. Phillips K. Goff D. Goff D. Kimble