Transmittal Letter for the Hermes 2 Safety Evaluation
ML24200A117
Person / Time
Site: Hermes  File:Kairos Power icon.png
Issue date: 07/19/2024
From: Mohamed Shams
NRC/NRR/DANU
To: Hastings P
Kairos Power
References
EPID L-2023-CPS-0000
Download: ML24200A117 (1)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 19, 2024 Mr. Peter Hastings Vice President, Regulatory Affairs Kairos Power LLC 707 W Tower Ave Alameda, CA 94501

SUBJECT:

SAFETY EVALUATION FOR THE KAIROS POWER LLC CONSTRUCTION PERMIT APPLICATION FOR THE HERMES 2 NON-POWER TEST REACTOR FACILITY (EPID NO. L-2023-CPS-0000)

Dear Mr. Hastings:

This letter is to inform you that the U.S. Nuclear Regulatory Commission (NRC) staff has completed the safety evaluation (SE) for the Kairos Power LLC (Kairos) construction permit application for the Hermes 2 non-power test reactor facility. Kaiross application was submitted by letter dated July 14, 2023 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML23195A121).

The enclosed SE is provided to Kairos for information and will be submitted to the Commission in preparation for the mandatory (uncontested) hearing. The SE has also been made public (ML24200A115). The NRC staff issuance of this SE does not constitute a commitment to issue the construction permit.

Sincerely, Mohamed Shams, Director Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation Docket Nos. 50-611 50-612

Enclosure:

As stated MOHAME D SHAMS Digitally signed by MOHAMED SHAMS Date: 2024.07.19 09:50:07 -04'00'

Pkg: ML24200A114 Letter: ML24200A117 Safety Evaluation: ML24200A115

  • via e-mail OFFICE NRR/DANU/UAL1:PM NRR/DANU/UAL1:LA NMSS/DFM/MCAB:BC* NSIR/DPR/RLB:BC*

NAME MOrenak DGreene JRubenstone JQuichocho DATE 5/20/2024 6/5/2024 8/14/2023 1/23/2024 OFFICE NRR/DRA/APLB:BC(A)* NRR/DEX/EXHB:BC*

NRR/DEX/ESEB:BC*

NRR/DEX/EICB:BC*

NAME SMakor BHayes ITseng FSacko DATE 1/31/2024 3/18/2024 3/1/2024 3/18/2024 OFFICE NMSS/REFS/FAB:BC*

NRR/DEX/EEEB:BC*

NRR/DANU/UNPO*

NRR/DRO/IQVB*

NAME KKline WMorton TTate KKavanagh DATE 2/27/2024 2/21/2024 11/14/2023 4/4/2024 OFFICE NRR/DANU/UTB2:BC NRR/DANU/UAL1:BC(A) OGC/NLO*

NRR/DANU/D NAME CdeMessieres JBorromeo AGhoshNabler MShams DATE 7/8/2024 7/7/2024 6/27/2024 7/19/2024