CNL-22-099, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update

From kanterella
(Redirected from ML22304A145)
Jump to navigation Jump to search

Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update
ML22304A145
Person / Time
Site: Browns Ferry, Watts Bar, Sequoyah  Tennessee Valley Authority icon.png
Issue date: 10/31/2022
From: Rymer S
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
CNL-22-099
Download: ML22304A145 (1)


Text

Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-22-099 October 31, 2022 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Units 1 and 2 Facility Operating License Nos. NPF-90 and NPF-96 NRC Docket Nos. 50-390 and 50-391

Subject:

TENNESSEE VALLEY AUTHORITY - HYDROLOGIC ENGINEERING CENTER RIVER ANALYSIS SYSTEM PROJECT MILESTONE STATUS UPDATE

Reference:

TVA letter to NRC, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestones, dated June 22, 2016 (ML16175A518)

By letter dated June 22, 2016, Tennessee Valley Authority (TVA) provided the Nuclear Regulatory Commission (NRC) with dates for several project deliverables associated with the ongoing Hydrologic Engineering Center River Analysis System (HEC-RAS) external flood modeling project (referenced letter). The HEC-RAS external flood modeling project was the subject of an April 4, 2016, public meeting to discuss technical details and a resolution plan for TVAs HEC-RAS external flood modeling issues. In the referenced letter, TVA committed to provide updates on the status of the specific project deliverables on a six-month frequency.

The purpose of this letter is to provide the thirteenth written update regarding the status of the project milestones consistent with the commitment made in the referenced letter.

U.S. Nuclear Regulatory Commission CNL-22-099 Page 2 October 31, 2022 No tasks have been completed since the update provided by letter dated April 27, 2022 (ML22118A081). Task 8 is currently projected to be completed in April 2023. The additional time to complete Task 8 is associated with the resolution of a potentially unconservative assumption in one of the analyses supporting the license amendment request (LAR). The potentially unconservative assumption was discussed with NRC on October 13, 2020 (ML20293A080).

TABLE 1 PROJECT DELIVERABLE SUBMITTAL MILESTONES (Status Updates Shown in Bold Text)

Submittal Project Deliverable Milestone 1 Browns Ferry Mitigating Strategies Assessment Complete 2 Sequoyah Mitigating Strategies Assessment Complete 3 Watts Bar Mitigating Strategies Assessment Complete 4 Watts Bar Focused Evaluation Complete 5 Sequoyah Focused Evaluation Complete 6 Browns Ferry Focused Evaluation Complete 7 Sequoyah Hydrology License Amendment Request Complete 8 Watts Bar Hydrology License Amendment Request April 2023 The projected milestone for the submittal of the Watts Bar Hydrology LAR will continue to be discussed with the NRC Project Manager.

TVA will provide the fourteenth status update on these project deliverable submittal milestones by April 30, 2023, consistent with the commitment made in the referenced letter.

U.S. Nuclear Regulatory Commission CNL-22-099 Page 3 October 31, 2022 There are no new regulatory commitments made in this letter.

If additional information is needed regarding this update, please contact Russell Thompson at rrthompson@tva.gov.

Respectfully, Digitally signed by Rymer, Stuart Loveridge Date: 2022.10.31 08:23:26 -04'00' Stuart L. Rymer Director (Acting), Nuclear Regulatory Affairs cc:

NRR Director - NRC Headquarters NRC Regional Administrator - Region II NRC Project Manager - Browns Ferry Nuclear Plant NRC Project Manager - Sequoyah Nuclear Plant NRC Project Manager - Watts Bar Nuclear Plant NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant