Letter Sequence Approval |
---|
EPID:L-2022-LLR-0034, Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Miilstone Status Update (Approved, Closed) |
|
MONTHYEARCNL-21-048, Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Miilstone Status Update2021-04-29029 April 2021 Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Miilstone Status Update Project stage: Request CNL-21-089, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2021-10-29029 October 2021 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update Project stage: Request ML22095A0182022-04-0404 April 2022 NRR E-mail Capture - Sequoyah Nuclear Plant - Acceptance of Request for Alternative - Pressure Isolation Valve Leakage ISTC-3630 (L-2022-LLR-0034) Project stage: Acceptance Review CNL-22-052, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status2022-04-27027 April 2022 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Project stage: Request ML22151A0092022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 Project stage: RAI ML22151A0102022-05-27027 May 2022 NRR E-mail Capture - Revised Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 Project stage: RAI CNL-22-062, Response to Request for Additional Information Regarding American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alternative RV-022022-06-28028 June 2022 Response to Request for Additional Information Regarding American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alternative RV-02 Project stage: Response to RAI ML22220A1072022-08-0909 August 2022 Regulatory Audit in Support of Review of the Request for Alternative to American Society of Mechanical Engineers Operation and Maintenance Code Project stage: Approval ML22263A0082022-09-28028 September 2022 Audit Summary Request for Alternative RV-02 - PIV Leakage Project stage: Other ML22263A3752022-09-29029 September 2022 Authorization of Alternative Request RV-02 for Pressure Isolation Valve Seat Leakage Project stage: Other CNL-22-104, Correction to Response to Request for Additional Information Regarding Sequoyah Nuclear Plant, Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alternative RV-022022-10-31031 October 2022 Correction to Response to Request for Additional Information Regarding Sequoyah Nuclear Plant, Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alternative RV-02 Project stage: Response to RAI CNL-22-099, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2022-10-31031 October 2022 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update Project stage: Request ML22304A1862022-12-0101 December 2022 Revised Authorization of Alternative Request RV-02 for Pressure Isolation Valve Seat Leakage Project stage: Other 2022-04-04
[Table View] |
|
---|
Category:Audit Plan
MONTHYEARML22224A0352022-08-12012 August 2022 Regulatory Audit Questions - Request for Alternative to ASME Operation and Maintenance Code Subsection ISTC-3630 ML22220A1072022-08-0909 August 2022 Regulatory Audit in Support of Review of the Request for Alternative to American Society of Mechanical Engineers Operation and Maintenance Code ML21246A0532021-09-15015 September 2021 Regulatory Audit in Support of Review of the Application to Adopt Risk-Informed Extended Completion Times RITSTF Initiative 4B ML16259A1892016-12-0505 December 2016 Nuclear Regulatory Commission Plan for the Audit of Mitigation Strategies Assessment Submittals Related to Order EA-12-049, Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML15106A6322015-04-17017 April 2015 Tennessee Valley Authority FHRR Audit Plan-4-22-2015 ML14356A0032015-02-10010 February 2015 Audit of Licensee Responses to the Expedited Seismic Evaluation Process to Support Implementation of Near-Term Task Force Recommendation 2.1, Seismic ML14302A1972014-11-0606 November 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 ML13067A2442013-03-26026 March 2013 Lr Environmental Site Audit Regarding Sequoyah Nuclear Plant ML13067A2012013-03-11011 March 2013 Plan for the Aging Management Program Regulatory Audit Regarding the Sequoyah Nuclear Plant, Units 1 and 2 License Renewal Application Review (TAC Nos. MF0481 and MF0482) 2022-08-09
[Table view] Category:Letter
MONTHYEARML24032A0202024-01-31031 January 2024 NPDES Biocide/Corrosion Treatment Plan Annual Report, Cy 2023 ML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24018A0142024-01-17017 January 2024 Engine Systems, Inc., Report No. 10CFR21-0137, Rev. 1, 56913-EN 56913 ML24011A3182024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), October 2023 ML24011A3172024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), September 2023 ML24011A3202024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), December 2023 ML24011A3162024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), August 2023 ML24011A3192024-01-11011 January 2024 Submittal of Discharge Monitoring Report (Dmr), November 2023 IR 05000327/20234422024-01-11011 January 2024 95001 Supplemental Inspection Report 05000327/2023442 and 05000328/2023442 and Follow-Up Assessment Letter ML24010A2132024-01-10010 January 2024 CFR 21.21 Final Report Regarding Siemens Medium Voltage Circuit Breakers ML24018A0952024-01-0404 January 2024 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance Report No. 10CFR21-0137, Rev. 0 ML24004A0332024-01-0303 January 2024 Interim Report of a Deviation or Failure to Comply Crompton Instruments Type 077 Ammeter ML24004A0402024-01-0303 January 2024 Response to NRCs November 8, 2023, Request for Additional Information - Related to Independent Spent Fuel Storage Installation CNL-23-068, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) ML23346A1222023-12-12012 December 2023 Annual Non-Radiological Environmental Operating Report - 2023 IR 05000327/20234202023-11-28028 November 2023 Security Baseline Inspection Report 05000327/2023420 and 05000328/2023420 CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23324A4362023-11-0909 November 2023 Exam Corporate Notification Letter Aka 210-day Letter ML23307A0822023-11-0808 November 2023 Request for Additional Information August 4, 2022, Exemption Request for Deviating from the Conditions of Certificate of Compliance No. 1032, Amendment No. 3, Related to Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation IR 05000327/20230032023-11-0303 November 2023 Integrated Inspection Report 05000327/2023003 and 05000328/2023003 ML23306A1592023-11-0202 November 2023 Enforcement Action EA-22-129 Inspection Readiness Notification ML23292A0792023-10-19019 October 2023 Tennessee Valley Authority - Emergency Plan Implementing Procedure Revision, Includes EPIP-5, Revision 58, General Emergency IR 05000327/20230112023-10-16016 October 2023 Triennial Fire Protection Inspection Report 05000327/2023011 and 05000328/2023011 ML23285A0882023-10-12012 October 2023 Submittal of Sequoyah Nuclear Plant, Units 1 and 2, Submittal of Updated Final Safety Analysis Report Amendment 31 ML23284A4252023-10-11011 October 2023 10 CFR 50.59 and 10 CFR 72.48 Changes, Tests, and Experiments Summary Report; Commitment Summary Report; and Update to the Fire Protection Report ML23283A2792023-10-10010 October 2023 Revisions to the Sequoyah Nuclear Plant Units 1 and 2 Technical Requirements Manual ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23277A0462023-10-0404 October 2023 Revisions to the Sequoyah Nuclear Plant Units 1 and 2 Technical Specification Bases ML23275A0272023-09-29029 September 2023 Submittal of Discharge Monitoring Report (DMR) Quality Assurance Study 43 Final Report 2023 ML23271A1662023-09-28028 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision IR 05000327/20234032023-09-14014 September 2023 Cyber Security Inspection Report 05000327/2023403 and 05000328/2023403 (Cover Letter) ML23257A0062023-09-14014 September 2023 Enforcement Action EA-22-129 Inspection Postponement Request ML23254A2192023-09-11011 September 2023 Emergency Plan Implementing Procedure Revisions ML23254A0652023-09-0707 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000327/20230052023-08-29029 August 2023 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2023005 and 05000328/2023005 ML23233A0122023-08-17017 August 2023 Unit 1 Cycle 25 Refueling Outage - 90-Day Inservice Inspection Summary Report - Supplement ML23233A0142023-08-15015 August 2023 Discharge Monitoring Report (Dmr), July 2023 ML23215A1212023-08-0303 August 2023 301 Exam Administrative Items (2B) Normal Release ML23215A1572023-08-0303 August 2023 Enforcement Action EA-22-129 Inspection Readiness Notification CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-01-04
[Table view] |
Text
August 9, 2022 Mr. James Barstow Vice President, Nuclear Regulatory Affairs and Support Services Tennessee Valley Authority 1101 Market Street, LP 4A-C Chattanooga, TN 37402-2801
SUBJECT:
SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 - REGULATORY AUDIT IN SUPPORT OF REVIEW OF THE REQUEST FOR ALTERNATIVE TO AMERICAN SOCIETY OF MECHANICAL ENGINEERS OPERATION AND MAINTENANCE CODE (EPID L-2022-LLR-0034)
Dear Sir or Madam:
By letter dated March 15, 2022, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22074A315), as supplemented by a letter dated June 28, 2022 (ML22179A357), Tennessee Valley Authority (the licensee) submitted a request for an alternative to Inservice Testing (IST) Program requirements for Sequoyah Nuclear Plant, Units 1 and 2, respectively. The alternative would apply to compliance with the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code, Subsection ISTC, paragraphs ISTC-3630, ISTC-3630(f), ISTC-5221(a)(1), and ISTC-5224, for specific IST Program requirements for certain pressure isolation valves (PIVs).
The U.S. Nuclear Regulatory Commission (NRC) staff has identified the need for a regulatory audit to examine the licensees non-docketed information with the intent to gain understanding, to verify information, or to identify information that will require docketing to support the basis of the licensing or regulatory decision.
The NRC staff will conduct the audit virtually at NRC Headquarters in Rockville, Maryland, via a licensee-established electronic portal available to NRC staff from approximately August 10, 2022, through August 31, 2022, with formal audit meetings to be scheduled during this period as needed. The detailed audit plan is enclosed with this letter.
J. Barstow If you have any questions, please contact me at (301) 415-1383 or by e-mail at Perry.Buckberg@nrc.gov.
Sincerely,
/RA/
Perry H. Buckberg, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-327 and 50-328
Enclosure:
Audit Plan cc: Listserv
REGULATORY AUDIT PLAN BY THE OFFICE OF NUCLEAR REACTOR REGULATION TO SUPPORT THE REVIEW OF THE REQUEST FOR ALTERNATIVE TO AMERICAN SOCIETY OF MECHANICAL ENGINEERS OPERATION AND MAINTENANCE CODE SUBSECTION ISTC-3630 TENNESSEE VALLEY AUTHORITY SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 DOCKET NOS. 50-327 AND 50-328
1.0 BACKGROUND
By letter dated March 15, 2022, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22074A315), as supplemented by a letter dated June 28, 2022 (ML22179A357), Tennessee Valley Authority (the licensee) submitted a request for an alternative to the Inservice Testing (IST) Program requirements for Sequoyah Nuclear Plant, Units 1 and 2, respectively. The alternative would apply to compliance with American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code of Record, Subsection ISTC, paragraphs ISTC-3630, ISTC-3630(f), ISTC-5221(a)(1), and ISTC-5224, for specific IST Program requirements for certain pressure isolation valves (PIVs).
The staff from the U.S. Nuclear Regulatory Commissions (NRC) Office of Nuclear Reactor Regulation (NRR) has initiated its review of the request in accordance with NRR Office Instruction LIC-102, Revision 3, Review of Relief Requests, Proposed Alternatives, and Requests to Use Later Code Editions and Addenda (ML18351A218).
2.0 REGULATORY AUDIT BASIS A regulatory audit is a planned license- or regulation-related activity that includes the examination and evaluation of primarily non-docketed information associated with the licensees request. An audit is conducted to gain understanding, to verify information, and to identify information that will require docketing to support the basis of a licensing or regulatory decision.
An audit will assist the NRC staff in efficiently conducting its review and gaining insights to the licensees processes and procedures. Information that the NRC staff relies upon to make the safety determination must be submitted on the docket. This audit will be conducted in accordance with NRR Office Instruction LIC-111, Regulatory Audits, Revision 1, dated October 2019 (ADAMS Accession No. ML19226A274), with exceptions noted within this audit plan.
The NRC staff will perform the audit to support its evaluation of whether the licensees request can be approved per Title 10 of the Code of Federal Regulations (10 CFR), Section 50.55a, "Codes and Standards," paragraph (z)(2). The audit will assist the NRC staff with understanding the licensees proposed alternative to ISTC-3630.
Enclosure
3.0 REGULATORY AUDIT SCOPE AND METHODOLOGY NRCs objectives of the audit are the following:
Gain a better understanding of the specific actions that the licensee may take to address pressure isolation valve (PIV) leakage and use of mechanical agitation as an alternative to compliance with ISTC-3630.
The NRC staff will audit the methods that the licensee would use to mechanically agitate a PIV following failure of a leakage test as part of a repair activity to achieve acceptable seat leakage.
4.0 INFORMATION AND OTHER MATERIAL NECESSARY FOR THE AUDIT The NRC staff will request information and an audit meeting(s) throughout the audit period. The NRC staff will use an Audit Items List to identify the information (e.g., methodology, process information, and calculations) to be audited. The NRC staff will provide the final Audit Items List as an enclosure to the audit summary report, which will be publicly available. The attachment to this audit plan includes the Initial Audit Items List. Throughout the audit period, the NRC staff may provide the licensee with audit questions and audit-related requests so that the licensee can better prepare for audit discussions with NRC staff. Any information accessed through the licensees portal will not be held or retained in any way by NRC staff. The NRC staff requests the licensee to have the information listed in the audit items list to be readily available and accessible for the NRC staffs review via a web-based portal.
5.0 TEAM ASSIGNMENTS The audit team will consist of the following NRC staff from NRR and contractors.
Perry Buckberg, Plant Licensing Branch II-2 (LPL2-2)
Gurjendra Bedi, Mechanical Engineering and Inservice Testing Branch (EMIB)
Thomas Scarbrough, EMIB Ian Tseng, EMIB 6.0 LOGISTICS To support the review schedule communicated to Tennessee Valley Authority (TVA) when the NRC staff accepted the request for technical review, audit activities will be performed remotely and virtually using Microsoft Teams, teleconference, and a web-based portal or other virtual meeting space created by the licensee. NRC information requests and communications with licensee staff will be coordinated through the NRCs licensing project manager.
The virtual audit will begin approximately August 10, 2022 and will continue through August 31, 2022. The NRCs entrance meeting with the licensee will take place the first week of the audit. The NRCs licensing project manager will inform the licensee of the entrance and exit meeting dates when they are established. The NRC intends to establish an audit meeting(s)
(e.g., a single, multi-day audit meeting; periodic audit meetings throughout the audit period) on mutually agreeable dates and times (to be determined) to discuss information needs and questions arising from the NRCs review of the audited items.
The NRC staff requests the licensee to have the information referenced in section 4.0 of this audit plan available and accessible for the NRC staffs review via an internet-based portal within 1-week of the date of this audit plan. The NRC staff requests that any supplemental information requested be available and accessible for the NRC staffs review within 1-week of the date of the NRCs notification to the licensee of the new requests. The NRCs licensing project manager will inform the licensee via routine communications when the NRC staff no longer needs access to the portal. The NRC staff requests the licensee to notify the review team when an audit item is added to its portal by sending an e-mail to the NRC licensing project manager.
7.0 SPECIAL REQUESTS The NRC requests access to requested documents and information through a web-based portal that allows the NRC staff to access documents over the internet. The following conditions associated with the online portal must be maintained while the NRC staff and contractors have access to the online portal:
The online portal will be password-protected. A separate password will be assigned to each member of the NRC staff and NRC contractors participating in the audit.
The online portal will prevent the NRC participants from printing, saving, downloading, or collecting any information directly from the online portal.
Conditions of use of the online portal will be displayed on the login screen and will require acknowledgment by each user.
Username and password and/or other web-based portal access information should be provided directly to members of the NRC staff and contractors as needed. The NRC licensing project manager will provide the licensee with names and contact information of the NRC staff and contractors participating in the audit. All other communications should be coordinated through the NRC project manager.
8.0 DELIVERABLES The NRC staff will develop any requests for additional information (RAIs), as needed, via NRR Office Instruction LIC-115, Revision 1, Processing Requests for Additional Information (ML21141A238) and issue such RAIs separately from audit-related correspondence. The NRC staff will issue an audit summary report prior to completing its review of the request.
Initial Audit Items List Item # Audit Item 1 The Tennessee Valley Authority (TVA) developed technical evaluation to formally document the guidance for performing mechanical agitation of the pressure isolation valves. This technical evaluation was referred to in the June 28, 2022, TVA letter (ML22179A357) 2 Technical evaluation supporting documentation as requested by the NRC Attachment
ML22220A107 OFFICE NRR/DORL/LPLII-2/PM NRR/DORL/LPLII-2/LA NRR/DEX/EMIB/BC NRR/DORL/LPLII-2/PM NAME PBuckberg RButler SBailey PBuckberg DATE 8/8/2022 8/9/2022 8/8/2022 8/9/2022 OFFICE NRR/DORL/LPLII-2/BC NAME DWrona (LHaeg for)
DATE 8/9/2022