ML22220A107

From kanterella
Jump to navigation Jump to search

Regulatory Audit in Support of Review of the Request for Alternative to American Society of Mechanical Engineers Operation and Maintenance Code
ML22220A107
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 08/09/2022
From: Perry Buckberg
Plant Licensing Branch II
To: Jim Barstow
Tennessee Valley Authority
Buckberg P
References
EPID L-2022-LLR-0034
Download: ML22220A107 (7)


Text

August 9, 2022

Mr. James Barstow Vice President, Nuclear Regulatory Affairs and Support Services Tennessee Valley Authority 1101 Market Street, LP 4A-C Chattanooga, TN 37402-2801

SUBJECT:

SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 - REGULATORY AUDIT IN SUPPORT OF REVIEW OF THE REQUEST FOR ALTERNATIVE TO AMERICAN SOCIETY OF MECHANICAL ENGINEERS OPERATION AND MAINTENANCE CODE (EPID L-2022-LLR-0034)

Dear Sir or Madam:

By letter dated March 15, 2022, (Agencywide Documents Access an d Management System (ADAMS) Accession No. ML22074A315), as supplemented by a letter dated June 28, 2022 (ML22179A357), Tennessee Valley Authority (the licensee) submitted a request f or an alternative to Inservice Testing (IST) Program requirements for Sequoyah Nuclear Plant, Units 1 and 2, respectively. The alternative would apply to compliance with the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code, Subsection ISTC, paragraphs ISTC-3630, ISTC-3630(f), ISTC-5221(a)(1), and ISTC-5 224, for specific IST Program requirements for certain pressure isolation valves (PIV s).

The U.S. Nuclear Regulatory Commission (NRC) staff has identifi ed the need for a regulatory audit to examine the licensees non-docketed information with t he intent to gain understanding, to verify information, or to identify information that will req uire docketing to support the basis of the licensing or regulatory decision.

The NRC staff will conduct the audit virtually at NRC Headquart ers in Rockville, Maryland, via a licensee-established electronic portal available to NRC staff f rom approximately August 10, 2022, through August 31, 2022, with formal audit meetings to be scheduled during this period as needed. The detailed audit plan is enclosed with this letter.

J.Barstow

If you have any questions, please contact me at (301) 415-1383 or by e-mail at Perry.Buckberg@nrc.gov.

Sincerely,

/RA/

Perry H. Buckberg, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Docket Nos. 50-327 and 50-328

Enclosure:

Audit Plan

cc: Listserv REGULATORY AUDIT PLAN

BY THE OFFICE OF NUCLEAR REACTOR REGULATION

TO SUPPORT THE REVIEW OF THE REQUEST FOR ALTERNATIVE TO

AMERICAN SOCIETY OF MECHANICAL ENGINEERS OPERATION AND MAINTENANCE

CODE SUBSECTION ISTC-3630

TENNESSEE VALLEY AUTHORITY

SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2

DOCKET NOS. 50-327 AND 50-328

1.0 BACKGROUND

By letter dated March 15, 2022, (Agencywide Documents Access an d Management System (ADAMS) Accession No. ML22074A315), as supplemented by a letter dated June 28, 2022 (ML22179A357), Tennessee Valley Authority (the licensee) submitted a request f or an alternative to the Inservice Testing (IST) Program requirements for Sequoyah Nuclear Plant, Units 1 and 2, respectively. The alternative would apply to com pliance with American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code of Record, Subsection ISTC, paragraphs ISTC-3630, ISTC-3630(f), ISTC-5221(a)(1), and ISTC-5224, for specific IST Program requirements for certain pressure isolation valves (PIV s).

The staff from the U.S. Nuclear Regulatory Commissions (NRC) O ffice of Nuclear Reactor Regulation (NRR) has initiated its review of the request in acc ordance with NRR Office Instruction LIC-102, Revision 3, Review of Relief Requests, Pr oposed Alternatives, and Requests to Use Later Code Editions and Addenda (ML18351A218).

2.0 REGULATORY AUDIT BASIS

A regulatory audit is a planned license-or regulation-related activity that includes the examination and evaluation of primarily non-docketed informatio n associated with the licensees request. An audit is conducted to gain understanding, to verify information, and to identify information that will require docketing to support the basis of a licensing or regulatory decision.

An audit will assist the NRC staff in efficiently conducting it s review and gaining insights to the licensees processes and procedures. Information that the NRC s taff relies upon to make the safety determination must be submitted on the docket. This audi t will be conducted in accordance with NRR Office Instruction LIC-111, Regulatory Aud its, Revision 1, dated October 2019 (ADAMS Accession No. ML19226A274), with exceptions noted within this audit plan.

The NRC staff will perform the audit to support its evaluation of whether the licensees request can be approved per Title 10 of the Code of Federal Regulations (10 CFR), Section 50.55a, "Codes and Standards," paragraph (z)(2). The audit will assist the NRC staff with understanding the licensees proposed alternative to ISTC-3630.

Enclosure

3.0 REGULATORY AUDIT SCOPE AND METHODOLOGY

NRCs objectives of the audit are the following:

Gain a better understanding of the specific actions that the l icensee may take to address pressure isolation valve (PIV) leakage and use of mechanical ag itation as an alternative to compliance with ISTC-3630.

The NRC staff will audit the methods that the licensee would us e to mechanically agitate a PIV following failure of a leakage test as part of a repair activit y to achieve acceptable seat leakage.

4.0 INFORMATION AND OTHER MATERIAL NECESSARY FOR THE AUDIT

The NRC staff will request information and an audit meeting(s) throughout the audit period. The NRC staff will use an Audit Items List to identify the inform ation (e.g., methodology, process information, and calculations) to be audited. The NRC staff will provide the final Audit Items List as an enclosure to the audit summary report, which will b e publicly available. The attachment to this audit plan includes the Initial Audit Items List. Throughout the audit period, the NRC staff may provide the licensee with audit questions and audit-related requests so that the licensee can better prepare for audit discussions with NRC staff. Any information accessed through the licensees portal will not be held or retained in a ny way by NRC staff. The NRC staff requests the licensee to have the information listed in the aud it items list to be readily available and accessible for the NRC staffs review via a web-based porta l.

5.0 TEAM ASSIGNMENTS

The audit team will consist of the following NRC staff from NRR and contractors.

Perry Buckberg, Plant Licensing Branch II-2 (LPL2-2)

Gurjendra Bedi, Mechanical Engineering and Inservice Testing B ranch (EMIB)

Thomas Scarbrough, EMIB Ian Tseng, EMIB

6.0 LOGISTICS

To support the review schedule communicated to Tennessee Valley Authority (TVA) when the NRC staff accepted the request for technical review, audit acti vities will be performed remotely and virtually using Microsoft Teams, teleconference, and a web-based portal or other virtual meeting space created by the licensee. NRC information requests and communications with licensee staff will be coordinated through the NRCs licensing project manager.

The virtual audit will begin approximately August 10, 2022 and will continue through August 31, 2022. The NRCs entrance meeting with the licensee w ill take place the first week of the audit. The NRCs licensing project manager will inform the licensee of the entrance and exit meeting dates when they are established. The NRC intends to est ablish an audit meeting(s)

(e.g., a single, multi-day audit meeting; periodic audit meetin gs throughout the audit period) on mutually agreeable dates and times (to be determined) to discus s information needs and questions arising from the NRCs review of the audited items.

The NRC staff requests the licensee to have the information ref erenced in section 4.0 of this audit plan available and accessible for the NRC staffs review via an internet-based portal within 1-week of the date of this audit plan. The NRC staff requests t hat any supplemental information requested be available and accessible for the NRC staffs revie w within 1-week of the date of the NRCs notification to the licensee of the new requests. The NRCs licensing project manager will inform the licensee via routine communications when the NR C staff no longer needs access to the portal. The NRC staff requests the licensee to notify th e review team when an audit item is added to its portal by sending an e-mail to the NRC licensin g project manager.

7.0 SPECIAL REQUESTS

The NRC requests access to requested documents and information through a web-based portal that allows the NRC staff to access documents over the internet. The following conditions associated with the online portal must be maintained while the NRC staff and contractors have access to the online portal:

The online portal will be password-protected. A separate passw ord will be assigned to each member of the NRC staff and NRC contractors participating in the audit.

The online portal will prevent the NRC participants from print ing, saving, downloading, or collecting any information directly from the online portal.

Conditions of use of the online portal will be displayed on th e login screen and will require acknowledgment by each user.

Username and password and/or other web-based portal access info rmation should be provided directly to members of the NRC staff and contractors as needed. The NRC licensing project manager will provide the licensee with names and contact inform ation of the NRC staff and contractors participating in the audit. All other communication s should be coordinated through the NRC project manager.

8.0 DELIVERABLES

The NRC staff will develop any requests for additional informat ion (RAIs), as needed, via NRR Office Instruction LIC-115, Revision 1, Processing Requests fo r Additional Information (ML21141A238) and issue such RAIs s eparately from audit-related correspondence. The NRC staff will issue an audit summary report prior to completing it s review of the request.

Initial Audit Items List

Item # Audit Item 1 The Tennessee Valley Authority (TVA) developed technical eval uation to formally document the guidance for performing mechanical agitation of th e pressure isolation valves. This technical evaluation was referred to in the June 28, 2022, TVA letter (ML22179A357)

2 Technical evaluation supporting documentation as requested by the NRC

Attachment

ML22220A107 OFFICE NRR/DORL/LPLII-2/PM NRR/DORL/LPLII-2/LA NRR/DEX/EMIB/BC NRR/DORL/LPLII-2/PM NAME PBuckberg RButler SBailey PBuckberg DATE 8/8/2022 8/9/2022 8/8/2022 8/9/2022 OFFICE NRR/DORL/LPLII-2/BC NAME DWrona (LHaeg for)

DATE 8/9/2022