Category:Meeting Summary
MONTHYEARML24292A1832024-10-30030 October 2024 Summary of Meeting with Tennessee Valley Authority, October 16, 2024, to Discuss Proposed License Amendment Regarding Implementation of an Online Monitoring Methodology ML24269A0062024-10-0303 October 2024 Correction to Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the TVA Nuclear Quality Assurance Plan ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24228A2652024-08-20020 August 2024 Summary of Public Pre-Submittal Meeting with Tennessee Valley Authority Regarding a Future Sequoyah Nuclear Plant and Watts Bar Nuclear Plant LAR Related to TS 3.5.2. ECCS - Operating ML24221A0132024-08-19019 August 2024 July 10, 2024, Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24218A2182024-08-15015 August 2024 Summary of July 16, 2024, Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future Sequoyah Nuclear Plant LAR Related to Containment Penetrations and Fuel Handling ML24136A2242024-05-15015 May 2024 1B EDG NRC Regulatory Conference Meeting Summary May 2, 2024 ML24102A1212024-04-18018 April 2024 Summary of Conference Call with Tennessee Valley Authority Regarding Sequoyah Nuclear Plant, Unit 1 Spring 2024 Steam Generator Tube Inspections ML24089A0712024-04-0101 April 2024 3/20/24 & 3/27/24 2023 TVA Public Annual Assessment Meeting Summary ML24082A2532024-03-26026 March 2024 Summary of March 18, 2024, Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future License Amendment Request Related to Fuel Handling and Fuel Decay Time ML24057A3792024-03-0808 March 2024 Summary of Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future License Amendment Request Related to Fuel Handling and Fuel Decay Time ML24065A0262024-03-0101 March 2024 LAR Pre-Application Meeting TS 3.9.8 (Decay Time) and FHA Dose Analysis Meteorological Monitoring and Dispersion Modeling Topics ML24044A0372024-02-15015 February 2024 February 8, 2024, Summary of Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future License Amendment Request Related to Technical Specification Surveillance Requirement 3.1.1.8 ML24008A1592024-01-18018 January 2024 Summary of December 13, 2023, Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML23304A0682023-11-0606 November 2023 Summary of October 24, 2023, Public Mtg W/Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, and Sequoyah Nuclear Plant, Units 1 and 2 to Revise Function 5, Turbine Trip and F ML23142A2132023-05-22022 May 2023 Public Meeting Summary - 2022 Annual Assessment Meetings for Browns Ferry, Sequoyah and Watts Bar Nuclear Plants ML22312A3522022-12-0101 December 2022 – Revised - Summary of Regulatory Audit for Alternative Request RV-02 ML22207B8302022-07-28028 July 2022 Summary of July 20, 2022, Observation Public Meeting with the Tennessee Valley Authority to Discuss Planned Alternative Request RP-12 to ASME OM Code Testing for the 1B-B Centrifugal Charging Pump at Sequoyah Nuclear Plant, Unit 1 ML22168A1642022-06-27027 June 2022 Summary of June 9, 2022, Meeting with TVA Regarding a Proposed License Amendment Request Related to Low Temperature Overpressure System and Cold Overpressure Mitigation System for Sequoyah and Watts Bar Nuclear Plants ML22109A0042022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Alternative Request Related to Testing of the Motor-Driven Auxiliary Feedwater Pumps at Sequoyah and Watts Bar Nuclear Plants ML22108A1842022-04-18018 April 2022 TVA 2021 Annual Assessment Public Meeting Summary ML22048B7852022-03-0202 March 2022 Summary of February 16, 2022, Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future Submittal of a Request for an Alternative to Requirements for Addressing Pressure Isolation Valve Leakage ML21313A3482021-11-18018 November 2021 Summary of Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future Submittal of a License Amendment Request Regarding Seismic and Fire Probabilistic Risk Assessment (PRA) Modifications to 10 CFR 50.69 ML21291A0092021-11-0303 November 2021 Tennessee Valley Authority Fleet - Summary of October 13, 2021, Teleconference with Tennessee Valley Authority to Discuss Planned License Amendment Requests Related to the Emergency Action Level Scheme ML21265A5142021-10-12012 October 2021 Summary of September 15, 2021, Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future Submittal of a License Amendment Request Regarding Elimination of the High Negative Flux Rate Trip ML21218A1472021-08-11011 August 2021 August 5, 2021 N-769 Relief Pre-Submittal Meeting Summary ML21165A1482021-06-30030 June 2021 Summary of Closed Meeting with Tennessee Valley Authority to Discuss Planned Requests for Exemption from Certain Requirements of 10 CFR Part 37 ML21152A1252021-06-0202 June 2021 Summary of Verbal Authorization of Alternative Request RP-10 for the 1B-B Motor Driven Auxiliary Feedwater Pump ML21137A0022021-05-17017 May 2021 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plants, Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, 50-390, and 50-391, Meeting Number 20210392 ML21112A3262021-04-30030 April 2021 Summary of April 21, 2021, Teleconference with Tennessee Valley Authority to Discuss a Planned License Amendment Request for Sequoyah Nuclear Plant, Units 1 and 2 ML21067A2132021-03-23023 March 2021 Summary of March 2, 2021, Teleconference with Tennessee Valley Authority to Discuss a Planned Alternative Request ML20357A0092021-01-19019 January 2021 Summary of December 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to Use of Alternate Probability of Detection at Watts Bar Nuclear Plant, Unit 2 ML20293A0802020-10-28028 October 2020 Summary of October 13, 2020, Closed Meeting with TVA on Responses to Requests for Additional Information Updated Final Safety Analysis Report Hydrologic Analysis License Amendment Request ML20175A8012020-08-11011 August 2020 Summary of June 23, 2020, Public Meeting with Tennessee Valley Authority to Discuss a Planned License Amendment ML20203M2292020-08-11011 August 2020 July 16, 2020, Summary of Partially Closed Meeting with Tennessee Valley Authority to Discuss Responses to Requests for Additional Information Regarding Updated Final Safety Analysis Report Hydrologic Analysis License Amendment Request ML20197A2722020-07-15015 July 2020 2020 Beaver Valley, Calvert Cliffs, Limerick Peach Bottom, Susquehanna Annual Assessment Webinar Summary ML20108E9092020-06-22022 June 2020 Summary of April 16, 2020, Virtual Meeting with Tennessee Valley Authority to Discuss Submittal of an Exigent License Amendment Request Operate One Cycle with One Control Rod Removed ML20127H8412020-05-0606 May 2020 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plant, Meeting No. 20200384 ML20055C2312020-03-0505 March 2020 Summary of February 20, 2020 Pre-submittal Meeting - Operation Without Control Rod H8 and Fuel Transition ML20035C8192020-02-12012 February 2020 Summary of January 27, 2020, Public Meeting with Tennessee Valley Authority Regarding the Future Submittal of Steam Generator Tube Inspection Related License Amendment Request ML19325C7142019-12-0202 December 2019 November 15,2019, Summary of Conference Call with Tennessee Valley Authority to Discuss Submittal of Exigent License Request (EPID L-2019-LLA-0239) for Sequoyah Nuclear Plant, Unit 1 ML19142A2772019-05-21021 May 2019 Summary of Public Meeting - Sequoyah Nuclear Plant ML19038A4692019-02-28028 February 2019 Summary of January 31, 2019 Meeting with Tennessee Valley Authority Regarding Presubmittal Licensing Actions - ML18344A5672019-01-15015 January 2019 November 14, 2018, Summary of Public Meeting with Tennessee Valley Authority Regarding Presubmittal Licensing Actions - Sequoyah Nuclear Plant, Units 1 and 2 ML18164A3092018-06-13013 June 2018 June 6, 2018 Summary of Public Meeting - Sequoyah Nuclear Plant - Docket Nos. 50-327 and 50-328 ML17278A8972017-10-17017 October 2017 Summary of Meeting with TVA Regarding Hydrology-Related Licensing Actions, Browns Ferry, Units 1, 2, and 3, Sequoyah Nuclear, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2(EPID L2016-TOP-0011; CAC Nos. MF8391-MF8397 ML17227A5142017-09-0101 September 2017 Summary of August 1, 2017, Pre-Submittal Public Meeting with TVA Regarding a Class 1E Unbalanced Voltage Relay Licensing Amendment Request for Browns Ferry Nuclear Plant, Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant ML16280A2912016-10-31031 October 2016 September 23, 2016, Summary of Public Meeting with TVA Regarding Hydrology-Related Licensing Actions, Browns Ferry Nuclear Plant, Units 1, 2, and 3, Sequoyah Nuclear Plant, Units 1 & 2 and Watts Bar Nuclear Plant, Units 1 & 2 (CAC Nos. MF83 ML16117A5512016-05-0202 May 2016 04/01/2016 Sequoyah Nuclear Plant, Units 1 and 2 - Summary Of Public Meeting With TVA Regarding Hydrology-Related Licensing Actions (CAC Nos. ME9238 And ME9239) ML16035A4802016-02-12012 February 2016 Jsc Meeting Summary Attachment 2024-09-23
[Table view] |