From: Green, Kim Sent: Tuesday, June 21, 2022 2:00 PM To: Eckermann, Jeremy Beau

Subject:

Acceptance Review Results for Browns Ferry Nuclear Plant, Unit 2, Relief Request BFN-2-ISI-003 (EPID L-2022-LLR-0049)

Follow Up Flag: Follow up Flag Status: Flagged

Dear Mr. Eckermann:

By letter dated May 24, 2022 (ADAMS Accession No. ML22144A138), Tennessee Valley Authority (TVA) requested relief from the requirements of American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (BPVC),Section XI, examination requirements for Table IWB-2500-1, Category B-D and ASME Code Case N-577, Category R-A, for Browns Ferry Nuclear Plant, Unit 2. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the request has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Pursuant to Section 50.55a(g)(5)(iii) of Title 10 of the Code of Federal Regulations, if the licensee has determined that conformance with an ASME BPVC requirement is impractical for its facility, then it must notify the NRC and submit information to support the determinations.

Determinations of impracticality in accordance with this section must be based on the demonstrated limitations experienced when attempting to comply with the Code requirements during the Inservice inspection interval for which the request is being submitted. Requests for relief made in accordance with this section must be submitted to the NRC no later than 12 months after the expiration of the initial or subsequent 120-month inspection interval for which relief is sought.

The NRC staff has reviewed your request and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in TVAs submittal, the NRC staff has estimated that it will take approximately 150 hours0.00174 days <br />0.0417 hours <br />2.480159e-4 weeks <br />5.7075e-5 months <br /> to complete, and that the review can be complete d by June 21, 2023. The estimate is based on the staffs initial review of the request and could change, due to several factors including requests for additional information and unanticipated addition of scope to the review. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates will be communicated, during our routine interactions.

If you have any questions, please email, or contact me at (301) 415-1627.

Sincerely, Kimberly Green, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Hearing Identifier: NRR_DRMA Email Number: 1686

Mail Envelope Properties (DM6PR09MB5462066DE8A4BBF292DE0E1F8FB39)

Subject:

Acceptance Review Results for Browns Ferry Nuclear Plant, Unit 2, Relief Request BFN-2-ISI-003 (EPID L-2022-LLR-0049)

Sent Date: 6/21/2022 1:59:56 PM Received Date: 6/21/2022 1:59:00 PM From: Green, Kim

Created By: Kimberly.Green@nrc.gov

Recipients:

"Eckermann, Jeremy Beau" <jbeckermann@tva.gov>

Tracking Status: None

Post Office: DM6PR09MB5462.namprd09.prod.outlook.com

Files Size Date & Time MESSAGE 3332 6/21/2022 1:59:00 PM

Options Priority: Normal Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date: