OFFICIAL USE ONLY - PROPRIETARY INFORMATION March 16, 2022 Mr. Jeffrey D. Greene Program Manager Electric Power Research Institute 1300 West W.T. Harris Boulevard Charlotte, NC 28262
SUBJECT:
REGULATORY AUDIT PLAN FOR ELECTRIC POWER RESEARCH INSTITUTE REPORT 3002018337, "USE OF DATA VALIDATION AND RECONCILIATION METHODS FOR MEASUREMENT UNCERTAINTY RECAPTURE: TOPICAL REPORT" (EPID L-2021-TOP-0006)
Dear Mr. Greene:
By letter dated January 27, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21053A027), Electric Power Research Institute (EPRI) submitted Report 3002018337, "Use of Data Validation and Reconciliation Methods for Measurement Uncertainty Recapture: Topical Report [(TR)], to the U.S. Nuclear Regulatory Commission (NRC) for review and approval. EPRI Report 3002018337 dated November 2020 presents a process for using a mathematical Data Validation and Reconciliation method for monitoring core thermal power and use of the methods for Measurement Uncertainty Recapture Uprates.
The NRC staff technical review of this TR, which is ongoing, had determined that a regulatory audit is needed to facilitate the review. The NRC staff will perform a virtual regulatory audit the week of March 28, 2022. Enclosure 1 is a copy of the audit plan that the NRC staff will follow. is a copy of the proprietary audit questions.
OFFICIAL USE ONLY - PROPRIETARY INFORMATION NOTICE: Enclosure 2 to this letter contains proprietary information. Upon separation from Enclosure 2, this letter is decontrolled.
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION Please contact Lois M. James at 301-415-3306 or via e-mail at Lois.James@nrc.gov with any questions you may have regarding this letter.
Sincerely,
/RA/
Richard Chang, Chief Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 99902021
Enclosures:
- 1. Audit Plan (Non-Proprietary)
- 2. Proprietary, Draft Questions (Proprietary)
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION REGULATORY AUDIT PLAN FOR ELECTRIC POWER RESEARCH INSTITUTE EPRI REPORT 3002018337, NOVEMBER 2020 "USE OF DATA VALIDATION AND RECONCILIATION METHODS FOR MEASUREMENT UNCERTAINTY RECAPTURE: TOPICAL REPORT" EPID L-2021-TOP-0006
1.0 BACKGROUND
By letter dated January 27, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21053A027), Electric Power Research Institute (EPRI) submitted EPRI Report 3002018337, "Use of Data Validation and Reconciliation Methods for Measurement Uncertainty Recapture: Topical Report [(TR)], to the U.S. Nuclear Regulatory Commission (NRC) for review and approval. EPRI Report 3002018337 dated November 2020 presents a process for using a mathematical Data Validation and Reconciliation (DVR) method for monitoring core thermal power and use of the methods for Measurement Uncertainty Recapture Uprates. In March 2021, the NRC staff completed an acceptance review of the TR and found it acceptable for docketing (ADAMS Accession No. ML21048A004).
2.0 REGULATORY AUDIT BASES To establish a licensing basis, licensees must analyze transients and accidents in accordance with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 50.34, 10 CFR 50.46, and where applicable, per NUREG-0737, Clarification of TMI [Three Mile Island]
Action Plan Requirements. These accidents and transients are described in the Standard Review Plan (SRP) (NUREG-0800). Section 15.0.2 of the SRP, Review of Transient and Accident Analysis Methods (ADAMS Accession No. ML070820123), provides guidance to NRC reviewers of transient and accident analysis methods and Regulatory Guide (RG) 1.203, Transient and Accident Analysis Methods (ADAMS Accession No. ML070820123), is intended to provide guidance for use in developing and assessing evaluation models for accident and transient analyses. RG 1.203 and SRP Section 15.0.2 cover the same subject material and are intended to be complementary, with Section 15.0.2 providing guidance to reviewers and the RG providing practices and principles for the benefit of method developers.
3.0 REGULATORY AUDIT SCOPE The NRC staff will conduct a virtual audit during the week of March 28, 2022. This audit is expected to include discussion between the NRC staff and EPRI staff regarding areas that the staff has identified in the enclosed proprietary audit questions. Details regarding the discussions and open items are provided below.
4.0 INFORMATION NEEDS The NRC staff requests that EPRI make available the appropriate engineer(s) with knowledge of the DVR methods and any appropriate references, to address questions by the NRC staff.
Documents referenced in the TR should also be made available.
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION 5.0 TEAM ASSIGNMENTS Joshua Kaizer, Technical Reviewer (NRR/DSS/SFNB)
David Rahn, Technical Reviewer (NRR/DSS/SFNB)
Santosh Bhatt, Technical Reviewer (NRR/DSS/SFNB)
Lois M. James, Senior Project Manager (NRR/DORL/LLPB)
Resources Available, if needed Dusty Brooks Nathan Porter 6.0 LOGISTICS Audit Date: Week of March 28, 2022 Entrance:
Monday, March 28, 2022, 9:30 am Exit:
Thursday, March 31, 2022, 3:00 pm The NRC staff will work with EPRI to establish times for breakout sessions based on NRC staff and EPRI staff availabilities.
The audit will be performed using the Microsoft Teams online platform and log-in information provided by the NRC to EPRI staff.
7.0 DELIVERABLES A regulatory audit summary will be provided within 90 days of the completion of the audit.
ML22073A273 (Package), ML22073A274 (Letter, Audit Plan),
ML22073A277 (Proprietary, Audit Questions)
OFFICE NRR/DORL/LLPB/PM NRR/DORL/LLPB/LA NRR/DSS/SFNB/BC NRR/DORL/LLPB/BC NAME LJames DHarrison RLukes RChang DATE 3/15/2022 3/15/2022 3/16/2022 3/16/2022