Final Data Validation and Reconciliation Methods (DVR) Schedule - Updated
ML22066B001
Person / Time
Site: Electric Power Research Institute
Issue date: 02/28/2022
From: Serita Sanders
Licensing Processes Branch
To: Pimentel F
Nuclear Energy Institute
Lois James, NRR/DORL/LLPB, 301-415-3306
References
3002018337-NP, 3002018337-P, EPID L-2021-TOP-0006
Download: ML22066B001 (4)


Text

From:

Sanders, Serita To:

PIMENTEL, Frances Cc:

Kaizer, Joshua; James, Lois

Subject:

RE: RE: Audit of Understanding Timeline in FINAL DVR Schedule Date:

Monday, February 28, 2022 8:21:00 AM Hi Frankie!

I just wanted to see if you were paying attention (lol). Sorry about the typo.

The A-version of the TR is scheduled to be issued November 2023. Please see your updated timeline below.

My apologies. Have a great day!

Best,

Serita

From: PIMENTEL, Frances <fap@nei.org>

Sent: Thursday, February 24, 2022 5:13 PM To: Sanders, Serita <Serita.Sanders@nrc.gov>

Cc: Kaizer, Joshua <Joshua.Kaizer@nrc.gov>; James, Lois <Lois.James@nrc.gov>

Subject:

[External_Sender] RE: Audit of Understanding Timeline in FINAL DVR Schedule

Hi Serita, Lois, and Josh,

Thank you very much! I really appreciate the detailed schedule information and will be sure to share these milestones with the DVR Team. I have reached out to EPRI regarding getting dates for the audit of understanding and am waiting to hear back from them. I expect to get feedback early next week and will contact Josh and Lois with the information.

Also, I have a question on the date for Receiving the -A Version of the Topical Report. I thought the final SE would be issued prior to the -A version of the TR being issued but below it has the Final SE in August 2023 and the -A TR in July 2023 - are these correct? Im not as familiar with the process as you, so Im just trying to be sure I understand before I share with the team.

Also, during the DVR team meeting, Constellation provided they talked to someone in NRR that indicated the DVR TR would not be done until March 2024Im just letting you know what was reported out during the meeting since it didnt line up with the information you provided. Has there been any changes to the schedule below or should I assume their information was just inaccurate?

Always a pleasure to work with you too Serita! And, welcome to Lois, who I look forward to working with, in addition to Josh, on the DVR project!

Take care, Frankie

Issue Draft SE to Vendor 06/07/2023 Receive Vendor's Draft SE Proprietary Review 07/05/2023 Final SE Issued to Vendor 08/09/2023 Receive -A Version of Topical Report 11/23/2023 Issue -A Version Review Letter 02/21/2024

From: Sanders, Serita <Serita.Sanders@nrc.gov>

Sent: Friday, February 18, 2022 9:04 AM To: PIMENTEL, Frances <fap@nei.org>

Cc: Kaizer, Joshua <Joshua.Kaizer@nrc.gov>; James, Lois <Lois.James@nrc.gov>

Subject:

[EXTERNAL] Audit of Understanding Timeline in FINAL DVR Schedule

CAUTION: This email originated from outside of NEI. DO NOT CLICK on any links or attachments unless you trust the sender, know the content is safe, and are expecting this email.

Hi Frankie,

This e-mail serves as a follow-up to our prior conversation on February 10th. Im sure you are still on leave and not giving the DVR project/schedule a thought (as it should be). Our next important milestone is the audit of understanding and you have the action to provide NRC w/dates that EPRI can support an audit. To ensure you enjoyed your away time, I didnt want to bombard you with items/e-mails that could wait until your return. Dont forget about providing dates to Lois (new PM for this project) and Josh, NRCs lead reviewer, with 3 dates between now and March 26th for audits of understanding. Please send your response to them as soon as reasonably possible.

Thanks so much! It was a pleasure working with you again.

Best,

Serita

From: Sanders, Serita Sent: Tuesday, February 15, 2022 3:37 PM To: PIMENTEL, Frances <fap@nei.org>

Subject:

FINAL DVR Schedule - Finalized

Hi Frankie,

This e-mail serves as a follow-up to our February 10, 2022 meeting whereby we discussed preliminary dates for the updated DVR schedule; more specifically, NRC RAIs submittals and EPRIs response.

Below is the NRC RAI issuance date and EPRI response as we previously discussed with the updated DVR schedule, RAIs will be issued on 5/06/2022. This date has not changed from the original schedule, nor has the vendor RAI completion date.

Since this is a first-of-a-kind design and the vendor is new to the NRC, the staff would ordinarily send, perhaps 2 rounds of RAIs. We discussed the amount of time that EPRI believes it needs to resolve very technical complex issues. As indicated below, EPRI feels confident that all RAIs can be resolved w/in 6-months. Therefore, we have staggered EPRIs RAI responses in two Phases, I and II, respectively. EPRI has 3-months to respond to the highly technical, risk significant RAIs. If any of these RAI responses have not adequately addressed the staffs concern and there are remaining issues, the staff will turn-a-round a review w/in one month and issue a response to the subject RAIs. Phase II RAIs will be issued 4-months after the initial NRC RAI issuance date. These are the non-technical or low significance technical RAIs. Thus, EPRI will have 2-months to resolve these RAIs, along with the aforementioned Phase I RAIs that the staff has already responded too and requires a second EPRI response to resolve the issue. For your convenience, this 6-month schedule is as follows:

Issue Round 1, Phase 1 of Partial List RAIs 05/06/2022 Vendor Respond Round 1, Phase 1 RAI 08/08/2022 3mons Issue Round 1, Phase 2 of RAIs to Vendor 09/21/2022 4mons (NRC will also issue follow-up RAIs to those Phase 1, Round 1 RAIs that did not adequately address the staffs concerns)

Vendor Respond Round 1, Phase 2 RAI 11/07/2022 6mons (note, this date essentially did not change from the original schedule)

      • All RAIs Completed***

It is important to note that EPRI can submit RAIs before the hard stops in the schedule for all the technically complex RAIs (or otherwise). Further, NRC will provide EPRI with completed responses to RAIs when they are completed as to help facilitate a timely review.

NRC took every measure to provide as much flexibility as possible to ensure that EPRI has enough time to provide a timely resolution to the staffs RAIs. If by the 5-month in this 6-month period, EPRI determines that more time is needed to resolve the staffs concerns, please send me an e-mail with Richard Chang (richard.chang@nrc.gov) on cc, with a request for a schedule extension. We will meet with the staff to determine how much additional time is adequate to resolve all of the RAIs.

Additionally, NRC was able to compensate for the additional time that it took NRC to secure a contract with the technical expertise necessary to conduct its review. This technology being a first-of-a-kind requires that the Advisory Committee on Reactor Safeguards review this technical report, which adds 3-months to the schedule. Therefore, additional important dates for EPRI have now shifted the original schedule by 3-months and is as follows:

Issue Draft SE to Vendor 06/07/2023 Receive Vendor's Draft SE Proprietary Review 07/05/2023 Final SE Issued to Vendor 08/09/2023 Receive -A Version of Topical Report 07/05/2023 Issue -A Version Review Letter 02/21/2024

If you have any questions please dont hesitate to reach out to me.

Have a great rest of the day!

Best,

Serita From: PIMENTEL, Frances <fap@nei.org>

Sent: Friday, January 21, 2022 7:17 AM To: Sanders, Serita <Serita.Sanders@nrc.gov>

Subject:

[External_Sender] RE: RE: DVR update

Hi Serita, I spoke with Kurt Crytzer from EPRI and the length of time to respond to the RAI depends on the nature and level of complexity of the RAI. He doesnt envision the response time taking longer than six months for even the most difficult RAI, so I think using six months should be good.

Thanks!

Frankie

This electronic message transmission contains information from the Nuclear Energy Institute, Inc. The information is intended solely for the use of the addressee and its use by any other person is not authorized. If you are not the intended recipient, you have received this communication in error, and any review, use, disclosure, copying or distribution of the contents of this communication is strictly prohibited. If you have received this electronic transmission in error, please notify the sender immediately by telephone or by electronic mail and permanently delete the original message. IRS Circular 230 disclosure: To ensure compliance with requirements imposed by the IRS and other taxing authorities, we inform you that any tax advice contained in this communication (including any attachments) is not intended or written to be used, and cannot be used, for the purpose of (i) avoiding penalties that may be imposed on any taxpayer or (ii) promoting, marketing or recommending to another party any transaction or matter addressed herein.