E-Mail - Final Set 2 Request for Additional Information - EPRI Report 3002018337, Use of Data Validation and Reconciliation Methods for Measurement Uncertainty Recaptutopical Report
ML22341A076
Person / Time
Site: Electric Power Research Institute
Issue date: 12/08/2022
From: Lois James
Licensing Processes Branch
To: Greene J
Electric Power Research Institute
Shared Package
ML22341A075 List:
References
EPID L-2021-TOP-0006
Download: ML22341A076 (2)


Text

From:

Lois James To:

jgreene@epri.com Cc:

RidsNrrOd Resource; RidsNrrDex Resource; RidsNrrDexELTB Resource; RidsNrrDss Resource; RidsNrrDssSfnb Resource; RidsNrrDorl Resource; RidsNrrDorlLlpb Resource; RidsNrrLADHarrison Resource; RidsACRS_MailCTR Resource; Scott Krepel; Joshua Kaizer; Jason Paige; David Rahn; Jonathan Evans; Lois James; kcrytzer@epri.com; PIMENTEL, Frances

Subject:

FINAL SET 2 REQUEST FOR ADDITIONAL INFORMATION - EPRI REPORT 3002018337, "USE OF DATA VALIDATION AND RECONCILIATION METHODS FOR MEASUREMENT UNCERTAINTY RECAPTURE: TOPICAL REPORT (EPID NO.

L-2021-TOP-0006)

Date:

Thursday, December 8, 2022 4:23:20 PM Attachments:

DVR RAI Set 2 - final.pdf Mr. Jeffrey D. Greene Program Manager Electric Power Research Institute 1300 West W.T. Harris Boulevard Charlotte, NC 28262

Mr. Greene:

By letter dated January 27, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21053A027), Electric Power Research Institute (EPRI) submitted EPRI Report 3002018337, "Use of Data Validation and Reconciliation Methods for Measurement Uncertainty Recapture: Topical Report, to the U.S. Nuclear Regulatory Commission (NRC) for review and approval. EPRI Report 3002018337, November 2020, presents a process for using a mathematical Data Validation and Reconciliation (DVR) method for monitoring core thermal power and use of the methods for Measurement Uncertainty Recapture (MUR) Uprates.

The NRC staff in the Nuclear Methods and Fuel Analysis Branch (SFNB) in the Division of Safety Systems (DSS) and the Long-Term Operations and Modernization Branch (ELTB) in the Division of Engineering and External Hazards (DEX) is in the process of reviewing your application. Based on our review, the NRC staff has identified the attached draft requests for additional information (RAIs).

These requests for additional information were discussed with Kurt Crytzer of your staff and Frances Pimentel of Nuclear Energy Institute, and a mutually agreeable date for the response is no later than March 9, 2023.

If you have any questions, please contact me by e-mail Lois.James@nrc.gov.

Sincerely,

Lois M. James, Senior Project Manger Office of Nuclear Reactor Regulation (NRR)

U.S. Nuclear Regulatory Commission Lois.James@nrc.gov

Docket No. 99902021

Enclosure:

As stated

ML22341A075 (pkg); ML22341A076 (e-mail); ML22341A080 (RAIs)

  • via email NRR-106 OFFICE NRR/DORL/LLPB/PM NRR/DSS/SFNB/BC DORL/LLPB/BC (A)

NRR/DORL/LLPB/PM NAME LJames SKrepel ASmith* for JEvans LJames DATE 12/01/2022 12/01/2022 12/07/2022 12/08/2022