Summary of the Environmental Remote Audit Related to the Review of the Subsequent License Renewal Application
ML23031A193
Person / Time
Site: Turkey Point  
Issue date: 02/01/2023
From: Lance Rakovan
NRC/NMSS/DREFS/ELRB
To: Strand D
Florida Power & Light Co
Shared Package
ML23031A190 List:
References
EPID L-2021-SLE-0002
Download: ML23031A193 (1)


Text

Dianne Strand GM Regulatory Affairs Florida Power & Light Co.

15430 Endeavor Drive (NT3/JW)

Jupiter West, FL 33478

SUBJECT:

TURKEY POINT NUCLEAR GENERATING STATION, UNITS 3 AND 4

SUMMARY

OF THE ENVIRONMENTAL REMOTE AUDIT RELATED TO THE REVIEW OF THE SUBSEQUENT LICENSE RENEWAL APPLICATION (EPID NUMBER L 2021 SLE 0002)

Dear Dianne Strand:

A review team consisting of staff from the U.S. Nuclear Regulatory Commission (NRC or the staff) participated in a remote audit December 12 - 13, 2022, and January 6, 2023, for Turkey Point Nuclear Generating Station, Unit Numbers 3 and 4, as part of the subsequent license renewal (SLR) application environmental review. The goal of the audit was to gather information to ensure that the environmental requirements for SLR, as codified in title 10 of the Code of Federal Regulations part 51 Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions, were met. A letter dated November 18, 2022 (Agencywide Documents Access and Management System (ADAMS) ML22321A323), was sent containing an audit plan.

An entrance meeting was held on December 12, 2022, to introduce participants and discuss audit logistics. During the remainder of the audit, the NRC staff participated in smaller groups (breakout sessions) with Florida Power & Light Company (FPL) and Enercon Services, Inc.

(Enercon) representatives to address the audit needs identified in the audit plan. Enclosure 1 to this letter provides a list of representatives from the NRC, FPL, and Enercon who participated in the audit.

At the conclusion of the audit, the NRC staff summarized the status of the review with FPL and Enercon representatives during the exit meeting held on January 6, 2023. Many of the NRCs questions identified in the audit plan or during the audit were answered through the conduct of the audit. Those that were not answered but needed for the site-specific Supplemental Environmental Impact Statement need to be submitted (a) as a supplement to the environmental report, (b) as responses to requests for additional information (RAI), or (c) as responses to requests for confirmation of information (RCI). Enclosure 2 to this letter provides the staffs RAIs and RCIs. We are requesting FPLs response to our requests within 30 days of the receipt of this letter.

While the NRC staff did not identify any significant environmental issues during this audit, the staff indicated that the environmental review was ongoing and that any additional information necessary to support the review would be formally requested via the RAI process in the future.

February 1, 2023

D. Strand Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC's Public Document Room staff at 800-397-4209 (or 301-415-4737) or via email at pdr.resource@nrc.gov.

If you have any questions, please contact me via email at Lance.Rakovan@nrc.gov.

Sincerely, Lance J. Rakovan Senior Environmental Project Manager Environmental Review License Renewal Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards Docket Nos. 50-250 and 251

Enclosures:

As stated cc: Listserv Signed by Rakovan, Lance on 02/01/23

D. Strand

SUBJECT:

TURKEY POINT NUCLEAR GENERATING STATION, UNITS 3 AND 4 -

SUMMARY

OF THE ENVIRONMENTAL REMOTE AUDIT RELATED TO THE REVIEW OF THE SUBSEQUENT LICENSE RENEWAL APPLICATION (EPID NUMBER L 2021 SLE 0002)

DATE:

DISTRIBUTION:

PUBLIC Listserv RidsNrrDnrl Resource RidsNrrPMTurkey Point Resource LGibson, NRR/DNRL TSmith, NMSS/REFS LRakovan, NMSS/REFS JMoses, NMSS/REFS JTrefethen, NMSS/REFS JDozier, NRR/DRA KHsueh, NRR/DRA MMahoney, NRR/DORL STurk, OGC DRoth, OGC SBurnell, HQ/OPA LWilkin, HQ/OCA JPelchat, RII/SGLO DGasperson, RII/OPA JOrr, RII/SRI RReyes, RII/RI BDesai, RII/DRS PCooper, RII/DRS ADAMS Accession No.:

OFFICE PM:ERLRB:REFS LA:REFS BC:ERLRB:REFS PM:ERLRB:REFS NAME LRakovan AWalker-Smith TSmith LRakovan DATE 01/31/2023 02/01/2023 02/01/2023 02/01/2023 OFFICE RECORD COPY February 1, 2023

Enclosure LIST OF PARTICIPANTS TURKEY POINT NUCLEAR GENERATING STATION, UNITS 3 AND 4 SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW ENVIRONMENTAL AUDIT December 12-13, 2022, and January 6, 2023 The U.S. Nuclear Regulatory Commission (NRC) environmental audit team members, Florida Power & Light Company (FPL), and Enercon Services, Inc. (Enercon) as well as their disciplines are shown below.

NRC Discipline Team Members Environmental Review Supervisor Ted Smith, NMSS Environmental Project Manager Lance Rakovan, NMSS Aquatic Resources Briana Arlene, NMSS Cumulative Impacts Beth Alferink, NMSS Environmental Justice Caroline Hsu, NMSS Jeff Rikhoff, NMSS Fuel Cycle Beth Alferink, NMSS Geologic Environment Lifeng Guo, NMSS Greenhouse Gas Emissions and Climate Change Nancy Martinez, NMSS Groundwater Lifeng Guo, NMSS Historic and Cultural Resources (Section 106 Consultation)

Nancy Martinez, NMSS Robert Hoffman, NMSS Human Health Beth Alferink, NMSS Land Use and Visual Resources Caroline Hsu, NMSS Air Quality and Noise Nancy Martinez, NMSS Postulated Accidents Jerry Dozier, NRR Replacement Power Alternatives Robert Hoffman, NMSS Socioeconomics Caroline Hsu, NMSS Jeff Rikhoff, NMSS Spent Nuclear Fuel Beth Alferink, NMSS Surface Water Lifeng Guo, NMSS Jeff Rikhoff, NMSS Terminating Power Plant Operations and Decommissioning Beth Alferink, NMSS Terrestrial Resource Caroline Hsu, NMSS Briana Arlene, NMSS Waste Management Beth Alferink, NMSS Don Palmrose, NMSS FPL Discipline Team Members Sr Environmental Services Project Manager Ken Proctor, Jr.

Environmental Services Director Paula Cobb Nuclear Licensing Engineer Boris Bazan Environmental Services Project Manager Scott Burns Sr Nuclear Chemistry Analyst Yolanda Sands Sr Environmental Services Engineer Diane Nguyen Sr Environmental Specialist Richard Eguino Sr Project Manager of Environmental Services Michael Reid Sr Project Manager Development Sara Dussich Sr Environmental Specialist Meghna Pandya Engineering Manager Andrew Whitley Construction Supervisor Adam Richardson Sr Environmental Specialist Kristin Eaton Nuclear Licensing Projects Manager Michael Davis Sr Environmental Services Project Manager Richard Estabrook Enercon Discipline Team Members Project Manager/Technical Lead Tom Slavonic Rachel Turney Air Quality & Noise Ashley Harper Jerry Riggs Cumulative Impacts Mary Hoganson Ecology (Terrestrial, Aquatic, Special Status Species &

Habitats)

Anjali Karve Groundwater and Surface Water Randall Lantz Jennifer Meek Historic and Cultural Resources Gary Eddington Human Health and Microbial Hazards Mary Hoganson Land Use and Visual Resources Fred Woolridge Jerry Riggs Replacement Power Alternatives Mary Hoganson Radiation Protection, Effluents, Solid Radioactive Waste Programs (additional Waste Management session)

Mary Hoganson Fred Woolridge Severe Accident Mitigation Alternatives Neil Johnson Socioeconomics Cheyenne Riggs Waste Management and Spent Nuclear Fuel Mary Hoganson Fred Wooldridge