Advises That 880722 Rev 1 to Fire Protection Program Plan Acceptable.Approved Plan Should Be Incorporated in Updated FSAR Per Generic Ltr 86-10
ML20247G557
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 05/18/1989
From: Heitner K
Office of Nuclear Reactor Regulation
To: Robert Williams
PUBLIC SERVICE CO. OF COLORADO
Shared Package
ML20245E659 List:
References
GL-86-10, GL-86-12, TAC-66508, NUDOCS 8905310009
Download: ML20247G557 (4)


Text

-- _ _ . _ _ - _ _ -

.?o.

c ,- May,18, 1989 N 1 ,

Docket No. S0-267

! Mr. R. O. Williams, Jr.

Senior Vice President, Nuclear Operations Public Service Company of Colorado Post Office Box 840 Denver, Colorado 80201-0840

Dear Mr. Williams:

SUBJECT:

APPROVAL OF FORT ST. VPAIN FIRE PROTECTION PROGRAM PLAN This letter is our Safety Evaluation of the Fort St. Vrain Fire Protection Program Plan., Revision 1 dated Jul 22, 1988. Our review is based on the

' Technical Evaluation Report (TER) ydone by our contractor, Science Applications InternationalCorporation(SAIC). SAIC's TER is enclosed.

This review was conducted against the applicable regulatory criteria and guidance. These include:-

Appendix A to BTP APPCSB 9.5-1,

- ' Appendix R to 10 CFR Part'50,

-- Generic Letter 86-10 and Generic Letter 88-12 The staff 'sent a draft of this TER to you by letter dated January 30, 1989, and received you comments by letter dated March 16, 1989. Based or. this evaluation and your other written commitments, we conclude that your Fire Protection Program Plan is acceptable.

The approve:I Fire Protection Program Plan should be incorporated in your updated Final Safety Analysis Report (FSAR) as per Generic Letter 86-10. This approval may also serve as a basis for deleting appropriate portions of your Fire Protection Technical Specifications, and substituting tne general license

' condition discussed in~ Generic Letter 86-10.

Sincerely,

/s/

Kennetn L. Heitner, Project Manager Project Directorate - IV Division of Reactor Projects - III, IV, V and Special Projects 6 Office of Nuclear Reactor Regulation

Enclosure:

s As stated cc w/ enclosure: /fol

'88 See next page j So

  • DISTRIBUTION l/l

! Docket File "7 NRC PDR Local PDR ' PD4 Reading Sd G. Holahan ' L. Rubenstein J. Calvo F. Hebdon

'00 P. Noonan K. Heitner OGC-Rockville E. Jordan N B. Grimes C. McCracken ACRS (10) PD4 Plant File 2

g DOCUMENT NAME:

FSV 8956 m a.u.

PD4/L PD4/PM N CE . PD4/D KHeitner:bj @c cken

, PNoon -

os'"~'8S h.J: h F. A os'$'8' @bdo,+%

_ os!F8' os'n'8'

w .

g May 18, 1989 Docket No. 50-267-Mr. R. O. Williams, Jr.

Senior Vice President, Nuclear Operations Public Service Company of Colorado Post Office Box 840 Denver, Colorado 60201-0840

Dear Mr. Williams:

SUBJECT:

APPROVAL OF FORT ST. VRAIN FIRE PROTECT!DN PROGRAM PLAN This letter is our Safety Evaluation of the Fort St. Vrain Fire Protection Program Plan, Revision 1 dated July 22, 1988. Our review is based on the Technical Evaluation Report (TER) done by our contractor, Science Applications InternationalCorporation(SAIC). SAIC's TER is enclosed.

This review was conducted against the applicable regulatory criteria and guidance. These include:

Appendist A to 9TP APPCSB 9.5-1, Appendix R to 1D CFR Part 50, Generic Letter 86-10 and Generic Letter 88-12 The staff sent a draft of this TER to you by letter dated January 30, 1989, and received you comments by letter dated March 16, 1989. Based on this evaluation and your other written consnitments, we conclude that your Fire Protection Program Plan is acceptable.

The approved Fire Protection Program Plan should be incorporated in your updated Final Safety Analysis Report (FSAR) as per Generic Letter 86-10. This approval may also serve as a basis for deleting appropriate portions of your Fire Protection Technical Specifications, and substituting the gencral license condition discussed in Generic Letter 86-10.

Sincerely,

/s/

, Kenneth L. Heitner, Project Manager Project Directorate - IV Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation

Enclosure:

As stated cc w/ enclosure:

See next page DISTRIBUTION Docket File NRC PDR Local POR PD4 Reading l

G. Holahan L. Rubenstein J. Calvo F. Hebdon P. Noonan K. Heitner OGC-Rockville E. Jordan B. Grimes C. McCracken ACRS (10) PD4 Plant File DOCUMENT NAME: FSV 8956 PD4/L PD4/PM N E PD4/D PNoon KHeitner:bj c cken JGalvo F. Hude 05/k/89 05/ir/89 05/[)/89 05/lg/89 ( f.h

_ -__ _ - _ . n)

~ ,feKai a

(, - .

3- . [S, UNITED STATES y g. NUCLEAR REGULATORY COMMISSION 5 'j WASHINGTON, D C. 20655

%, ...- May 18, 1989 Docket No. 50-267 Mr. R. O. Williams, Jr.

Senior Vice President, Nuclear Operations Public Service Company of Colorado Post Office Box 840 Denver, Colorado 80201-0840

Dear Mr. Williams:

SUBJECT:

APPROVAL OF FORT ST. VRAIN FIRE PROTECTION PROGRAM PLAN This letter is our Safety Evaluation of the Fort St. Vrain Fire Protection Program Plan, Revision 1 dated July 22, 1988. Our review is based on the Technical Evaluation Report (TER) done by our contractor, Science Applications InternationalCorporation(SAIC). SAIC's TER is enclosed.

This review was conducted against the applicable regulatory criteria and guidance. These include:

Appendix A to 8TP APPCSB 9.5-1, Appendix R to 10 CFR Part 50, Generic Letter 86-10 and Generic Letter 88-12.

The staff ser.t a draft of this TER to you by letter dated January 30, 1989, and received you comments by letter dated March 16, 1989. Based on this evaluation and your other written ccmitments, we conclude that your Fire Protection Program Plan is acceptable.

The approved Fire Protection Drogram Plan should be incorporated in your updated Final Safety Analysis Report {FSAR) as per Generic Letter 86-10. This approval may also serve as a basis for deleting appropriate portions of your Fire Protection Technical Specifications, and substituting the general license condition discussed in Generic Letter 86-10.

Sincerely,

% B 91 L .' h Kenneth L. Heitner, Project Manager Project Directorate - IV Division of Rear; tor Projects - III,.

IV, Y and Special Projects Office of Nuclear Reactor Regulation

Enclosure:

As stated i cc w/ enclosure:

l See next page

6 t *

, Mr. R. 0. Williams, Jr.

l Public Service Company of Colorado Fort St. Vrain l CC:

! Mr. D. W. Warembourg, Manager Albert J. Hazle, Director Nuclear Engineering Division- Radiation Control Division Public Service Company Department of Health-of Colt'rado 4210 East ,11th Avenue P. O. '; x 840 Denoer, Colorado 80220 Denvet,' Colorado 80201-0840 Mr. David Alberstein, Manager Mr. Charles H. Fuller Fort St. Vrain Services Manager, Nuclear Production GA International Services Corporation and Station Manager Post Office Box 85608 Public Service Company of Colorado

. San Diego, California 92138 16805 Weld County Road 19-1/2 Platteville, Colorado 80651-Mr. H. L. Brey, Manager Nuclear Licensing and Resource Mr. P. F. Tomlinson, Manager -

Management Division Quality Assurance Division Public Service Company cf Colorado Public Service Company of Colorado P. O. Box 840 16805 Weld County Road 19-1/2 Denver, Colorado 80201-0840 Platteville, Colorado 80651 Senior Resident Inspector Mr. D. D. Hock U.S. Nuclear Regulatory Comission President and Chief Executive Officer P. O. Box 640 Public Service Company of Colorado Platteville, Colorado 80651 Post Office Box 840 Denver, Colorado 80201-0840 Kelley, Standfield & 0'Donnell ATTN: Mr. J. K. Tarpey Commitment Control Program Public Service Company Building Coordinator Room 900 Public Service Company of Colorado 550 15th Street 2420 P. 26th Ave. Suite 100-0 Denver, Colorado 80202 Denver, Colorado 80211 Regional Administrator, Region IV U.S. Nuclear Regulatory Comission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011 Chairman, Board of County Commissioners of Weld County, Colorado Greeley, Colorado 80631 j

\