ML20238B512

From kanterella
Jump to navigation Jump to search

Responds to NRC 870804 Request for Addl Info Re Elimination of Dynamic Effects of Postulated Primary Loop Pipe Ruptures from Design Basis for Facility.Addl Time Will Be Required to Evaluate & Adequately Address Each Item of Request
ML20238B512
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 08/25/1987
From: Cockfield D
PORTLAND GENERAL ELECTRIC CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
TAC-06596, TAC-6596, NUDOCS 8709010254
Download: ML20238B512 (2)


Text

________ _______

- ~

~

PortlanciGeneral ElectricCompany David W. Cockfield Vice President, Nuclear August 25. 1987 Trojan Nuclear Plant Docket 50-344 License NPF-1 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington DC 20555

Dear Sir:

Elimination of Dynamic Effects of Postulated Primary Loop Pipo Ruptures From Desir,n Basis for Trojan Nuclear Plant By letter dated August 4,1987, the Nuclear Regulatory Commission (NRC) Staff requested that Portland Concral Electric (PGE) provide additional information regarding the elimination of dynamic offects of postulated primary loop pipe ruptures from the design basis for Trojan. It was requested that this information be provided within 30 days from receipt of the letter, or a schedule to provide this information be submitted within 15 days.

PCE has reviewed your request and determined that additional time will be required to evaluato and adequately address cach item included in the onclosure to your letter. In addition, in order to ensure an adequate response to your concerns, PGE requests a telephone discussion with the technical reviewers prior to proceeding with our evaluations. Arrangements for the telephone call will be coordinated via the NRC Project Manager for Trojan.

Accordingly, we plan to submit a detailed response to the twelvo (12) items listed in the enclosure to your August 4, 1987 letter by December 31, 1987.

Sincerely, c: Mr. John B. Martin Regional Administrator, Region V U. S. Nuclear Regulatory Commission Mr. David Kish, Director State of Oregon Department of Energy Mr. R. C. Barr NRC Resident Inspector d, .! @ " ! hf g p" Trojan Nuclear Plant g

'O C fic )

8709010254 070025 PDR ADOCK 05000344 I' P PDR

\D 121 S W SsTIOn St:M t. Powand, OT:;on 97204 Y _ _ _ _ _ _ _ _ _ _ _ _ _ _