ML20238A583

From kanterella
Jump to navigation Jump to search
Forwards Draft Rev 1 to Comanche Peak Rept Review Group Task Group 3 Rept on Safety Significance. Rev Adds Section on Lessons Learned,Clarifies Methodology Used in Evaluation & Adds Tables Highlighting Hardware Deficiencies
ML20238A583
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 02/27/1987
From: Crutchfield D
Office of Nuclear Reactor Regulation
To: Arlotto G
NRC OFFICE OF NUCLEAR REGULATORY RESEARCH (RES)
Shared Package
ML20237K807 List: ... further results
References
NUDOCS 8708210017
Download: ML20238A583 (1)


Text

- - - - - ~ _ _

Il --

UNITED STATES

  1. o, I

['

,p,

'j NUCLEAR REGULATORY COMMISSION WASHING TON, D. C. 20555 i

February 27, 1987 k...../ i MEMORANDUM FOR: Guy A. Arlotto, Director Division of Engineering Technology 3 j

Office of Nuclear Regulatory Research e l j

FROM:

' Dennis M. Crutchfield, Assistant Director  :

Division of PWR Licensing-B Office of Nuclear Reactor Regulation

SUBJECT:

COMANCHE PEAK REPORT REVIEW GROUP (CPRRG)

TASK GROUP 3 REPORT The purpose of this memo is to transmit a revised draft report to the This report CPRRG supersedes thatearlier our documents the results draft, Rev. O. of the Task Group 3 effort.The significant changes th follows: (1) addition of a section on lessons learned; (2) clarification of the methodology used in the evaluation; (3) addition of two new Tables that separate the broader issues raised by Task Group 3 from the 34 issues of attact at MM to the OIA report and specifically highlight the identified ignificant hardware deficiency; (4) deletion of the Table summarizing accomplishments that were dictated by the original Task Group 3 charter; (5) safety addition of an Appendix that provides a comparison of the Task Group 2 and Task Group 3 conclusions. Minor changes have been made to the narrative portion of the original Task Group 3 report to highlight our conclusions with Through these changes we believe that Task regard to hardware deficiencies.

Group 3 has completed the additional assignments provided by the CPRRG on February 24, 1987. Questions on the report should be directed to either me or Marty Virgilio. ,

Den . tc eld Ass ant Director Division of PWR Licensing-B

Enclosure:

As stated cc w/ enclosure:

C. J. Heltemes, Jr.

C. Paperiello J. Lieberman R. Erickson P. McKee S. Collins R. Hartfield 0708210017 870312 DR ADOCK 05000445 PDR

,