ML20210U819
| ML20210U819 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 06/03/1986 |
| From: | Schierling H Office of Nuclear Reactor Regulation |
| To: | Harold Denton, Eisenhut D, Lyons J NRC |
| Shared Package | |
| ML20197G068 | List:
|
| References | |
| FOIA-86-744 NUDOCS 8606060350 | |
| Download: ML20210U819 (1) | |
Text
QC(h Docket Nos. 50-275 an 0-323 June 3, 1986 MEMORANDUM FOR:
H. Denton R. Houston L. Rubenstein D. Eisenhut D. Crutchfield J. B. Youngblood J. Lyons E. Rossi V. Noonan H. Thompson G. Lainas G. Lear F. Miraglia T. Speis C. Berlinger R. Bernero W. Russell G. Holahan V. Benaroya T. Novak J. Milhoan F. Schroeder D. Vassallo THRU:
Steven A. Varga, Director PWR Project Directorate #3 Division of PWR Licensing-A FROM:
Hans E. Schierling, Senior Project Manager PWR Project Directorate #3 Division of PWR Licensing-A
SUBJECT:
DAILY HIGHLIGHT - ISSUANCE OF RERACK AMENDMENTS Plant Name Diablo Canyon Units 1 and 2 On May 30, 1986 amendments were issued for the expansion of the spent fuel pools of Diablo Canyon Units 1 and 2.
The reracking will be performed with the pools in a dry and uncontaminated condition. The licensee expects to complete the effort in about 8 weeks. Unit 1 is scheduled to shut down for the first refueling at the end of August.
Should a trip occur after August 1 the unit will not be restarted.
A prehearing conference was held on May 13, 1986. We expect a hearing to be scheduled in about September.
/s/TChan for H. Schierling Hans E. Schierling, Senior Project Manager PWR Project Directorate #3 Division of PWR Licensing-A HSchierlng/pws[
PADf3:DL,
06/3/86 YA 8606060350 860603 ADOCK 05000275 Y
j n
u