ML20197J383

From kanterella
Jump to navigation Jump to search
Submits Daily Highlight.On 850313,facility Reached 100% Power W/Full Power Testing to Be Completed by 850320. Facility Expected to Be Ready for Commercial Operation by Late Apr 1985
ML20197J383
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 03/14/1985
From: Schierling H
Office of Nuclear Reactor Regulation
To: Harold Denton, Edison G, Eisenhut D
Office of Nuclear Reactor Regulation
Shared Package
ML20197G068 List:
References
FOIA-86-744 NUDOCS 8503270543
Download: ML20197J383 (1)


Text

I 'I4 125 E MORANDUM FOR:

H. Denton, NRR D. Eisenhut, NRR G. Edison, TOSB, NRR H. Thompson, DL F. Miraglia, DL T. Novak, DL W. Russell, Acting Director, DHFS J. Knight, Acting Director, DE R. Bernero, DSI T. Speis, DST B. Snyder, TMIPO, NRR G. Holahan, ORAB G.-Lainas DL D. Crutchfield, DL l

THRU:

George W. Knighton, Branch Chief Licensing Branch No. 3 Division of Licensing FROM:

Hans Schierling, Project Manager Licensing Branch No. 3 Division of Licensing

SUBJECT:

DAILY HIGHLIGHT Diablo Canyon' Unit 1 Diablo Canyon Unit I reached 100 percent power on March 13,1985 at 5:30 pm PST.

Full power testing is expected to be completed by March 20 and the 100 hour0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> 1

acceptance test by March 26. This will be followed by a natural circulation boron mixing test. Unit 1 is expected to be ready for comercial operation by late April 1985.

Hans Schierling, Project Manager Licensing Branch No. 3 Division of Licensing Distribution: