Submits Daily Highlight.On 850328,util Completed 100 H Acceptance Test.Reactor Tripped to Initiate Natural Circulation Boron Mixing Test.Natural Circulation Established.Boron Concentration Verified on 850329
ML20197J432
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 03/29/1985
From: Schierling H
Office of Nuclear Reactor Regulation
To: Harold Denton, Edison G, Eisenhut D
Office of Nuclear Reactor Regulation
Shared Package
ML20197G068 List:
References
FOIA-86-744 NUDOCS 8504120104
Download: ML20197J432 (1)


Text

. __ _ _ _ _- _______

MAR 2 91l( ,

I MEMORANDUM FOR: H. Denton, NRR l D. Eisenhut, NRR'  !

G. Edison, TOSB, NRR H. Thompson, DL F. Miraglia, DL l T. Novak, DL W. Russell, Acting Director, DHFS  !

J. Knight, Acting Director, DE R. Bernero, DSI T. Speis, DST

8. Snyder, THIPO, NRR G. Holahan, ORAB G. Lainas, DL--- - -

D. Crutchfield, DL THRU: George W. Knighton, Chief Licensing Branch No. 3 Division of Licensing FROM:

Hans Schierling, Project Manager Licensing Branch No. 3 Division of Licensing J

SUBJECT:

DAILY HIGHLIGHT Diablo Canyon Unit 1 PG&E completed the 100 hour0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> acceptance test for Unit 1 on March 28 at 6:20 am PST. The reactor was tripped at 9:30 pm PST to initiate the natural circulation boron mixing test. Natural circulation was established on March 29 at 12:45 am PST.

Baron concentration was verified. Cool down was initiated at 4:45 am PST.

Cool down to RHR mode is estimated to be completed at 1:00 pm PST March 29, 1985.

Cidy EaAb kr Hans Schierling, Project Manager Licensing Branch No. 3 Division of Licensing Distribution: