Insp Rept 50-293/96-09 on 960916-20.Violations Noted. Major Areas Inspected:Miscellaneous Security & Safeguard Issues,Access Authorization Program & Administration Organization & Background Investigation ElementsML20129A044 |
Person / Time |
---|
Site: |
Pilgrim |
---|
Issue date: |
10/11/1996 |
---|
From: |
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
---|
To: |
|
---|
Shared Package |
---|
ML20129A027 |
List: |
---|
References |
---|
50-293-96-09, 50-293-96-9, NUDOCS 9610220009 |
Download: ML20129A044 (11) |
|
|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000293/19990051999-10-0808 October 1999 Insp Rept 50-293/99-05 on 990726-0905.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19990041999-08-27027 August 1999 Insp Rept 50-293/99-04 on 990610-0725.Non-cited Violations Noted.Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support ML20209G2331999-07-0909 July 1999 Insp Rept 50-293/99-03 on 990419-0609.Violations Noted & Being Treated as non-cited Violations.Major Areas Inspected: Operations,Maint,Engineering & Plant Support.Response to Main Transformer Fire by Fire Brigade Members Was Good IR 05000293/19990021999-05-17017 May 1999 Insp Rept 50-293/99-02 on 990308-0418.Two Level 4 Violations Occurred & Being Treated as Ncv.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000293/19990011999-04-20020 April 1999 Insp Rept 50-293/99-01 on 990125-0307.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support.Also Included Routine Core Insp of Security Program During Period of 990301-05 IR 05000293/19980101998-12-22022 December 1998 Insp Rept 50-293/98-10 on 981020-1208.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support,Including Implementation of Fire Protection Program IR 05000293/19980081998-12-0101 December 1998 Insp Rept 50-293/98-08 on 980907-1019.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19982031998-11-24024 November 1998 Insp Rept 50-293/98-203 on 980928-1023.No Violations Noted. Major Areas Inspected:Capability of Selected Sys to Perform Safety Functions Required by Design Bases,Adherence of Sys to Design & Licensing Bases & Consistency of Configuration IR 05000293/19980071998-10-0707 October 1998 Insp Rept 50-293/98-07 on 980726-0906.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19980061998-08-28028 August 1998 Insp Rept 50-293/98-06 on 980609-0725.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19980091998-08-20020 August 1998 Insp Rept 50-293/98-09 on 980713-24.No Violations Noted. Major Areas Inspected:Engineering Activities in Areas Including Evaluations to Address Operability Concerns,C/A Process & Actions Associated W/Findings from Previous Insps IR 05000293/19980051998-07-0909 July 1998 Insp Rept 50-293/98-05 on 980421-0608.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support.Concerns W/Fire Proctection Area Were Identified ML20217P7801998-04-0303 April 1998 Insp Rept 50-293/98-03 on 980302-05 & 11-12.Apparent Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Licensee Security Force Capability IR 05000293/19980011998-03-24024 March 1998 Insp Rept 50-293/98-01 on 980107-0224.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19970131998-02-0606 February 1998 Insp Rept 50-293/97-13 on 971111-980106.Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19970121997-12-17017 December 1997 Insp Rept 50-293/97-12 on 971006-10 & 1119.Violations Noted. Major Areas Inspected:Eq Documents for EQ Equipment That Required Requalification Due to Containment Environ Changes Resulting from CS Flow Rate Reduction in 1988 IR 05000293/19970111997-12-11011 December 1997 Insp Rept 50-293/97-11 on 970914-1110.Violations Noted:Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970101997-11-26026 November 1997 Insp Rept 50-293/97-10 on 971104-07.No Violations Noted. Major Areas Inspected:Emergency Response Organization, Simulated Events,Mitigation Actions Emergency Declarations & off-site Agencies IR 05000293/19970081997-10-24024 October 1997 Insp Rept 50-293/97-08 on 970805-0913.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20198L9231997-10-21021 October 1997 Insp Rept 50-293/97-05 on 970514-0828.Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Engineering IR 05000293/19970071997-09-15015 September 1997 Insp Rept 50-293/97-07 on 970625-0816.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970801997-09-12012 September 1997 Insp Rept 50-293/97-80 on 970721-0801.Violations Noted.Major Areas Inspected:Effectiveness of Processes for Identifying Resolving & Preventing Issues That Degrade Quality of Plant Operations & Safety ML20216G8181997-09-0404 September 1997 Insp Rept 50-293/97-09 on 970827-28.No Violations Noted. Major Areas Inspected:Licensee Access Authorization Program IR 05000293/19970041997-08-0707 August 1997 Insp Rept 50-293/97-04 on 970505-23.No Violations Noted. Major Areas Inspected:Effectiveness of Licensees Efforts in Maintaining Design Basis of safety-related Sys ML20149K0431997-07-22022 July 1997 Insp Rept 50-293/97-03 on 970429-0624.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20141K7861997-05-22022 May 1997 Insp Rept 50-293/97-02 on 970303-0428.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20137E5671997-03-18018 March 1997 Insp Rept 50-293/97-01 on 970112-0302.Violations Noted.Major Areas Inspected:Operations,Engineering & Plant Support ML20134K5951997-02-0707 February 1997 Insp Rept 50-293/96-10 on 961123-970111.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19960081996-12-18018 December 1996 Insp Rept 50-293/96-08 on 960924-1122.Violation Noted.Major Areas Inspected:Engineering,Maint,Plant Support,Radioactive Effluent Controls Program,Radiological Environmental Monitoring & Meteorological Monitoring.Meeting Slides Encl IR 05000293/19960061996-10-30030 October 1996 Insp Rept 50-293/96-06 on 960729-0923.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20129A0441996-10-11011 October 1996 Insp Rept 50-293/96-09 on 960916-20.Violations Noted. Major Areas Inspected:Miscellaneous Security & Safeguard Issues,Access Authorization Program & Administration Organization & Background Investigation Elements ML20129D8361996-09-20020 September 1996 Insp Rept 50-293/96-07 on 960708-12,0722-26 & 0828-0903. Non Cited Violation Noted.Major Areas Inspected:C/As After Licensee Had Identified Potentially Inoperable Primary Containment as Documented in LER 96-04 IR 05000293/19930201994-01-10010 January 1994 Insp Rept 50-293/93-20 on Stated Date.No Violations Noted. Major Areas Inspected:Operations,Maintenance & Surveillance, Engineering & Plant Support IR 05000293/19930801993-12-21021 December 1993 Insp Rept 50-293/93-80 on 931018-23.No Violations Noted. Major Areas Inspected:Station Blackout Coping Sys,Onsite Ac Supplies & Reliability Program,Plant Mods & QA & Maint Practices for Station Blackout Equipment IR 05000293/19930191993-11-23023 November 1993 Insp Rept 50-293/93-19 on 930928-1101.No Violations Noted. Major Areas Inspected:Plant Operations,Maint & Surveillance, Engineering,Plant Support,W/Regard to Security & NRC Info Notice 93-079 ML20058D4771993-11-19019 November 1993 Insp Rept 50-293/93-16 on 930830-1015.Violations Noted.Major Areas Inspected:Audits & Surveillances,Training & Qualifications,Radiological Problem Repts & Associated C/A IR 05000293/19930151993-10-15015 October 1993 Insp Rept 50-293/93-15 on 930817-0927.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls Maint & Surveillance,Emergency Preparedness,Security,Safety Assessment & Quality Verification IR 05000293/19930171993-09-24024 September 1993 Insp Rept 50-293/93-17 on 930830-0903.No Violations Noted. Major Areas Inspected:Mgt Controls,Qa Audits & ODCM IR 05000293/19930141993-09-0808 September 1993 Insp Rept 50-293/93-14 on 930713-0816.No Violations Noted. Major Areas Inspected:Plant Operations,Maintenance & Surveillance,Engineering & Plant Support IR 05000293/19930111993-08-0404 August 1993 Insp Rept 50-293/93-11 on 930606-11.No Violations Noted. Major Areas Inspected:Licensee Corrective Actions of Previously Identified Electrical Distribution Sys Functional Insp Findings & Observations IR 05000293/19930011993-02-0303 February 1993 Insp Rept 50-293/93-01 on 930111-14.Weaknesses Noted.Major Areas Inspected:Eop Review,Rev,Approval Process,Qa Involvement in EOP Program & Operator Training in EOPs IR 05000293/19920811993-02-0202 February 1993 Probabilistic Risk Assessment Based Insp Rept 50-293/92-81 on 921130-1218.Violation Noted.Major Areas Inspected:Review of Emergency Diesel Generators & Hpcis.App a Encl IR 05000293/19920281993-01-28028 January 1993 Insp Rept 50-293/92-28 on 921124-1231.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Emergency Preparedness, Security,Safety Assessment & Quality Verification IR 05000293/19920261993-01-21021 January 1993 Insp Rept 50-293/92-26 on 921207-11.No Violations or Deviations Noted.Major Areas Inspected:Ep Program Changes, Emergency Response Facilities,Equipment,Instrumentation, Supplies & Organization & Mgt Control IR 05000293/19920231992-12-29029 December 1992 Safety Insp Rept 50-293/92-23 on 921020-1123.No Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Emergency Preparedness, Security & Safety Assessment & Quality Verification IR 05000293/19920241992-11-23023 November 1992 Insp Rept 50-293/92-24 on Stated Date.No Safety Concerns or Violations Noted.Major Areas Inspected:Audits & Surveillances,Collective Personnel Exposure Status,Outage Radiological Controls & Implementation of Exposure Programs IR 05000293/19900201990-11-0707 November 1990 Safety Insp Rept 50-293/90-20 on 900816-1008.Violation Noted.Major Areas Inspected:Plant Operations,Security, Maint & Surveillance,Engineering & Technical Support, Radiological Controls,Emergency Preparedness & Safety IR 05000293/19900211990-10-11011 October 1990 Insp Rept 50-293/90-21 on 900905-07.Major Areas Inspected: 900902-03 Event Involving Number of Component Malfunctions & Operational Complications Following Shutdown.Operating Procedures Lacked Adequate Guidance for Operators IR 05000293/19900091990-08-20020 August 1990 Insp Rept 50-293/90-09 on 900806-10.No Violations or Deviations Noted.Major Areas Inspected:Control of Design, Design Changes,Mods,Engineering & Technical Support Organization,Staffing,Communications,Qa & Training IR 05000293/19900161990-07-30030 July 1990 Partially Withheld Physical Security Insp Rept 50-293/90-16 on 900625-29 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Mgt Support & Program Plans,Protected & Vital Area Physical Barriers & Detection & Assessment Aids 1999-08-27
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000293/19990051999-10-0808 October 1999 Insp Rept 50-293/99-05 on 990726-0905.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19990041999-08-27027 August 1999 Insp Rept 50-293/99-04 on 990610-0725.Non-cited Violations Noted.Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support ML20209G2331999-07-0909 July 1999 Insp Rept 50-293/99-03 on 990419-0609.Violations Noted & Being Treated as non-cited Violations.Major Areas Inspected: Operations,Maint,Engineering & Plant Support.Response to Main Transformer Fire by Fire Brigade Members Was Good IR 05000293/19990021999-05-17017 May 1999 Insp Rept 50-293/99-02 on 990308-0418.Two Level 4 Violations Occurred & Being Treated as Ncv.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000293/19990011999-04-20020 April 1999 Insp Rept 50-293/99-01 on 990125-0307.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support.Also Included Routine Core Insp of Security Program During Period of 990301-05 IR 05000293/19980101998-12-22022 December 1998 Insp Rept 50-293/98-10 on 981020-1208.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support,Including Implementation of Fire Protection Program IR 05000293/19980081998-12-0101 December 1998 Insp Rept 50-293/98-08 on 980907-1019.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19982031998-11-24024 November 1998 Insp Rept 50-293/98-203 on 980928-1023.No Violations Noted. Major Areas Inspected:Capability of Selected Sys to Perform Safety Functions Required by Design Bases,Adherence of Sys to Design & Licensing Bases & Consistency of Configuration IR 05000293/19980071998-10-0707 October 1998 Insp Rept 50-293/98-07 on 980726-0906.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19980061998-08-28028 August 1998 Insp Rept 50-293/98-06 on 980609-0725.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19980091998-08-20020 August 1998 Insp Rept 50-293/98-09 on 980713-24.No Violations Noted. Major Areas Inspected:Engineering Activities in Areas Including Evaluations to Address Operability Concerns,C/A Process & Actions Associated W/Findings from Previous Insps IR 05000293/19980051998-07-0909 July 1998 Insp Rept 50-293/98-05 on 980421-0608.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support.Concerns W/Fire Proctection Area Were Identified ML20217P7801998-04-0303 April 1998 Insp Rept 50-293/98-03 on 980302-05 & 11-12.Apparent Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Licensee Security Force Capability IR 05000293/19980011998-03-24024 March 1998 Insp Rept 50-293/98-01 on 980107-0224.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19970131998-02-0606 February 1998 Insp Rept 50-293/97-13 on 971111-980106.Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19970121997-12-17017 December 1997 Insp Rept 50-293/97-12 on 971006-10 & 1119.Violations Noted. Major Areas Inspected:Eq Documents for EQ Equipment That Required Requalification Due to Containment Environ Changes Resulting from CS Flow Rate Reduction in 1988 IR 05000293/19970111997-12-11011 December 1997 Insp Rept 50-293/97-11 on 970914-1110.Violations Noted:Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970101997-11-26026 November 1997 Insp Rept 50-293/97-10 on 971104-07.No Violations Noted. Major Areas Inspected:Emergency Response Organization, Simulated Events,Mitigation Actions Emergency Declarations & off-site Agencies IR 05000293/19970081997-10-24024 October 1997 Insp Rept 50-293/97-08 on 970805-0913.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20198L9231997-10-21021 October 1997 Insp Rept 50-293/97-05 on 970514-0828.Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Engineering IR 05000293/19970071997-09-15015 September 1997 Insp Rept 50-293/97-07 on 970625-0816.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970801997-09-12012 September 1997 Insp Rept 50-293/97-80 on 970721-0801.Violations Noted.Major Areas Inspected:Effectiveness of Processes for Identifying Resolving & Preventing Issues That Degrade Quality of Plant Operations & Safety ML20216G8181997-09-0404 September 1997 Insp Rept 50-293/97-09 on 970827-28.No Violations Noted. Major Areas Inspected:Licensee Access Authorization Program IR 05000293/19970041997-08-0707 August 1997 Insp Rept 50-293/97-04 on 970505-23.No Violations Noted. Major Areas Inspected:Effectiveness of Licensees Efforts in Maintaining Design Basis of safety-related Sys ML20149K0431997-07-22022 July 1997 Insp Rept 50-293/97-03 on 970429-0624.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20141K7861997-05-22022 May 1997 Insp Rept 50-293/97-02 on 970303-0428.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20137E5671997-03-18018 March 1997 Insp Rept 50-293/97-01 on 970112-0302.Violations Noted.Major Areas Inspected:Operations,Engineering & Plant Support ML20134K5951997-02-0707 February 1997 Insp Rept 50-293/96-10 on 961123-970111.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19960081996-12-18018 December 1996 Insp Rept 50-293/96-08 on 960924-1122.Violation Noted.Major Areas Inspected:Engineering,Maint,Plant Support,Radioactive Effluent Controls Program,Radiological Environmental Monitoring & Meteorological Monitoring.Meeting Slides Encl IR 05000293/19960061996-10-30030 October 1996 Insp Rept 50-293/96-06 on 960729-0923.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20129A0441996-10-11011 October 1996 Insp Rept 50-293/96-09 on 960916-20.Violations Noted. Major Areas Inspected:Miscellaneous Security & Safeguard Issues,Access Authorization Program & Administration Organization & Background Investigation Elements ML20129D8361996-09-20020 September 1996 Insp Rept 50-293/96-07 on 960708-12,0722-26 & 0828-0903. Non Cited Violation Noted.Major Areas Inspected:C/As After Licensee Had Identified Potentially Inoperable Primary Containment as Documented in LER 96-04 IR 05000293/19930201994-01-10010 January 1994 Insp Rept 50-293/93-20 on Stated Date.No Violations Noted. Major Areas Inspected:Operations,Maintenance & Surveillance, Engineering & Plant Support IR 05000293/19930801993-12-21021 December 1993 Insp Rept 50-293/93-80 on 931018-23.No Violations Noted. Major Areas Inspected:Station Blackout Coping Sys,Onsite Ac Supplies & Reliability Program,Plant Mods & QA & Maint Practices for Station Blackout Equipment IR 05000293/19930191993-11-23023 November 1993 Insp Rept 50-293/93-19 on 930928-1101.No Violations Noted. Major Areas Inspected:Plant Operations,Maint & Surveillance, Engineering,Plant Support,W/Regard to Security & NRC Info Notice 93-079 ML20058D4771993-11-19019 November 1993 Insp Rept 50-293/93-16 on 930830-1015.Violations Noted.Major Areas Inspected:Audits & Surveillances,Training & Qualifications,Radiological Problem Repts & Associated C/A IR 05000293/19930151993-10-15015 October 1993 Insp Rept 50-293/93-15 on 930817-0927.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls Maint & Surveillance,Emergency Preparedness,Security,Safety Assessment & Quality Verification IR 05000293/19930171993-09-24024 September 1993 Insp Rept 50-293/93-17 on 930830-0903.No Violations Noted. Major Areas Inspected:Mgt Controls,Qa Audits & ODCM IR 05000293/19930141993-09-0808 September 1993 Insp Rept 50-293/93-14 on 930713-0816.No Violations Noted. Major Areas Inspected:Plant Operations,Maintenance & Surveillance,Engineering & Plant Support IR 05000293/19930111993-08-0404 August 1993 Insp Rept 50-293/93-11 on 930606-11.No Violations Noted. Major Areas Inspected:Licensee Corrective Actions of Previously Identified Electrical Distribution Sys Functional Insp Findings & Observations IR 05000293/19930011993-02-0303 February 1993 Insp Rept 50-293/93-01 on 930111-14.Weaknesses Noted.Major Areas Inspected:Eop Review,Rev,Approval Process,Qa Involvement in EOP Program & Operator Training in EOPs IR 05000293/19920811993-02-0202 February 1993 Probabilistic Risk Assessment Based Insp Rept 50-293/92-81 on 921130-1218.Violation Noted.Major Areas Inspected:Review of Emergency Diesel Generators & Hpcis.App a Encl IR 05000293/19920281993-01-28028 January 1993 Insp Rept 50-293/92-28 on 921124-1231.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Emergency Preparedness, Security,Safety Assessment & Quality Verification IR 05000293/19920261993-01-21021 January 1993 Insp Rept 50-293/92-26 on 921207-11.No Violations or Deviations Noted.Major Areas Inspected:Ep Program Changes, Emergency Response Facilities,Equipment,Instrumentation, Supplies & Organization & Mgt Control IR 05000293/19920231992-12-29029 December 1992 Safety Insp Rept 50-293/92-23 on 921020-1123.No Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Emergency Preparedness, Security & Safety Assessment & Quality Verification IR 05000293/19920241992-11-23023 November 1992 Insp Rept 50-293/92-24 on Stated Date.No Safety Concerns or Violations Noted.Major Areas Inspected:Audits & Surveillances,Collective Personnel Exposure Status,Outage Radiological Controls & Implementation of Exposure Programs IR 05000293/19900201990-11-0707 November 1990 Safety Insp Rept 50-293/90-20 on 900816-1008.Violation Noted.Major Areas Inspected:Plant Operations,Security, Maint & Surveillance,Engineering & Technical Support, Radiological Controls,Emergency Preparedness & Safety IR 05000293/19900211990-10-11011 October 1990 Insp Rept 50-293/90-21 on 900905-07.Major Areas Inspected: 900902-03 Event Involving Number of Component Malfunctions & Operational Complications Following Shutdown.Operating Procedures Lacked Adequate Guidance for Operators IR 05000293/19900091990-08-20020 August 1990 Insp Rept 50-293/90-09 on 900806-10.No Violations or Deviations Noted.Major Areas Inspected:Control of Design, Design Changes,Mods,Engineering & Technical Support Organization,Staffing,Communications,Qa & Training IR 05000293/19900161990-07-30030 July 1990 Partially Withheld Physical Security Insp Rept 50-293/90-16 on 900625-29 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Mgt Support & Program Plans,Protected & Vital Area Physical Barriers & Detection & Assessment Aids 1999-08-27
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000293/19990051999-10-0808 October 1999 Insp Rept 50-293/99-05 on 990726-0905.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19990041999-08-27027 August 1999 Insp Rept 50-293/99-04 on 990610-0725.Non-cited Violations Noted.Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support ML20209G2331999-07-0909 July 1999 Insp Rept 50-293/99-03 on 990419-0609.Violations Noted & Being Treated as non-cited Violations.Major Areas Inspected: Operations,Maint,Engineering & Plant Support.Response to Main Transformer Fire by Fire Brigade Members Was Good PNO-I-99-026A, on 990518,main Transformer Was Damaged During Testing of Replacement Bushing While Unit Was in Refueling Outage.Current Refueling Outage Was Originally Scheduled to Be Completed on 990607,with Return to Full Power Operation1999-06-0101 June 1999 PNO-I-99-026A:on 990518,main Transformer Was Damaged During Testing of Replacement Bushing While Unit Was in Refueling Outage.Current Refueling Outage Was Originally Scheduled to Be Completed on 990607,with Return to Full Power Operation PNO-I-99-026, on 990518,fire Occurred at Pilgrim Station in Main Electrical Transformer.Licensee Requested off-site Firefighting Assistance.Resident Inspector Responded to Site Upon Notification of Event.Licensee Issued Press Release1999-05-19019 May 1999 PNO-I-99-026:on 990518,fire Occurred at Pilgrim Station in Main Electrical Transformer.Licensee Requested off-site Firefighting Assistance.Resident Inspector Responded to Site Upon Notification of Event.Licensee Issued Press Release IR 05000293/19990021999-05-17017 May 1999 Insp Rept 50-293/99-02 on 990308-0418.Two Level 4 Violations Occurred & Being Treated as Ncv.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000293/19990011999-04-20020 April 1999 Insp Rept 50-293/99-01 on 990125-0307.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support.Also Included Routine Core Insp of Security Program During Period of 990301-05 IR 05000293/19980101998-12-22022 December 1998 Insp Rept 50-293/98-10 on 981020-1208.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support,Including Implementation of Fire Protection Program IR 05000293/19980081998-12-0101 December 1998 Insp Rept 50-293/98-08 on 980907-1019.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19982031998-11-24024 November 1998 Insp Rept 50-293/98-203 on 980928-1023.No Violations Noted. Major Areas Inspected:Capability of Selected Sys to Perform Safety Functions Required by Design Bases,Adherence of Sys to Design & Licensing Bases & Consistency of Configuration IR 05000293/19983011998-11-24024 November 1998 NRC Operator Licensing Exam Rept 50-293/98-301OL (Including Completed & Graded Tests) for Tests Administered on 981016- 23.Exam Results:All Applicants Passed All Portions of Exam ML20154J8991998-10-0707 October 1998 Notice of Violation from Insp on 980726-0906.Violation Noted:Licensee Did Not Establish Measures to Assure Regulatory Requirements & Design Basis of Control Room High Efficiency Air Filtration Sys IR 05000293/19980071998-10-0707 October 1998 Insp Rept 50-293/98-07 on 980726-0906.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20239A1231998-08-28028 August 1998 Notice of Violation from Insp on 980609-0725.Violation Noted:From 1980 to 980609,licensee Failed to Maintain Provisions to Ensure That One Train of Cables Were Free from Fire Damage IR 05000293/19980061998-08-28028 August 1998 Insp Rept 50-293/98-06 on 980609-0725.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19980091998-08-20020 August 1998 Insp Rept 50-293/98-09 on 980713-24.No Violations Noted. Major Areas Inspected:Engineering Activities in Areas Including Evaluations to Address Operability Concerns,C/A Process & Actions Associated W/Findings from Previous Insps ML20237A3031998-08-0606 August 1998 Notice of Violation from Insp on 980427-0515.Violation Noted:From 960710-970427,licensee Elected Not to Monitor Performance or Condition of Control Rod Drive Sys Against Established Goals IR 05000293/19980051998-07-0909 July 1998 Insp Rept 50-293/98-05 on 980421-0608.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support.Concerns W/Fire Proctection Area Were Identified ML20247N8441998-05-19019 May 1998 Partially Deleted Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $55,000 (Ref 10CFR2.790(b) for Violations Noted During Insp on 980302-05 & 11-12 ML20247P0221998-05-19019 May 1998 Notice of Violation from Insp on 980225-0418.Violations Noted:Work Plan to Replace External Cooling Water Flexible Hoses to a Core Spray Pump Motor Not Commensurate with Complexity of Task.As Result,Physical Damage Occurred ML20248J3981998-05-14014 May 1998 EN-98-038:on 980519,notice of Proposed Imposition of Civil Penalty in Amount of $55,000 Issued to Licensee.Action Based on One Violation Involving Apparent Failures Associated W/Assessment Aids at Facility ML20217N5971998-04-27027 April 1998 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $165,000.Violations Noted:Between Jan 1995 & 970120 Licensee Failed to Take Prompt & Effective Corrective Action for Significant Condition Adverse to Quality ML20247M3891998-04-22022 April 1998 EN-98-032:on 980427,notice of Proposed Imposition of Civil Penalty in Amount of $165,000 Issued to Licensee.Action Based on Two Severity Level III Violations & One Severity Level III Problem Re Failure to Identify & Take C/As ML20217P7801998-04-0303 April 1998 Insp Rept 50-293/98-03 on 980302-05 & 11-12.Apparent Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Licensee Security Force Capability ML20217F0101998-03-24024 March 1998 Notice of Violation from Insp on 980107-0224.Violation Noted:Nrc Identified That Condition Outside Design Basis of Plant Involving EDG Fuel Oil Storage Sys Was Not Reported to NRC within 1 Hour IR 05000293/19980011998-03-24024 March 1998 Insp Rept 50-293/98-01 on 980107-0224.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20202D2441998-02-0606 February 1998 Notice of Violation from Insp on 971111-980106.Violations Noted:Util Did Not Properly Evaluate Cause & Implement Corrective Actions to Preclude Repetition of Temporary Temp Detectors Deficiencies from Reactor Vessel Flange IR 05000293/19970131998-02-0606 February 1998 Insp Rept 50-293/97-13 on 971111-980106.Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19970121997-12-17017 December 1997 Insp Rept 50-293/97-12 on 971006-10 & 1119.Violations Noted. Major Areas Inspected:Eq Documents for EQ Equipment That Required Requalification Due to Containment Environ Changes Resulting from CS Flow Rate Reduction in 1988 ML20197K1101997-12-17017 December 1997 Notice of Violation from Insp on 971006-10 & 1119.Violation Noted:Nine Penetrations Were Not Qualified in That Qualification Methodology Used by Boston Edison Had Not Been Validated by Test Results to Be Equivalent to Type Testing ML20197H2411997-12-11011 December 1997 Notice of Violation from Insp on 970914-1110.Violation Noted:On 971001,licensee Identified That,Tagout T97-61-162 Was Incorrectly Prepared & Applied;Breaker 1021 Was Placed in Closed Vice Open Position as Required by Tagout IR 05000293/19970111997-12-11011 December 1997 Insp Rept 50-293/97-11 on 970914-1110.Violations Noted:Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970991997-11-26026 November 1997 Correction to SALP Rept 50-293/97-99.Page 2 of Subj Rept Corrected IR 05000293/19970101997-11-26026 November 1997 Insp Rept 50-293/97-10 on 971104-07.No Violations Noted. Major Areas Inspected:Emergency Response Organization, Simulated Events,Mitigation Actions Emergency Declarations & off-site Agencies PNO-I-97-072, on 971123,operators Initiated Plant Shutdown When Main Steam Isolation Valves AO-203-1C & AO-203-2B Were Declared Inoperable During Surveillance Test1997-11-24024 November 1997 PNO-I-97-072:on 971123,operators Initiated Plant Shutdown When Main Steam Isolation Valves AO-203-1C & AO-203-2B Were Declared Inoperable During Surveillance Test ML20198P8241997-11-0404 November 1997 SALP Rept 50-293/97-99 for Period 960407-970913 IR 05000293/19970081997-10-24024 October 1997 Insp Rept 50-293/97-08 on 970805-0913.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20198L9231997-10-21021 October 1997 Insp Rept 50-293/97-05 on 970514-0828.Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Engineering PNO-I-97-061, on 970922,util Informed Region I of Receipt of Internal Nuclear Safety Concern Potentially Involving Instance of Falsification of Control Room Log in 1989.Formal Investigation Initiated & Press Release Issued1997-09-23023 September 1997 PNO-I-97-061:on 970922,util Informed Region I of Receipt of Internal Nuclear Safety Concern Potentially Involving Instance of Falsification of Control Room Log in 1989.Formal Investigation Initiated & Press Release Issued ML20211A2741997-09-17017 September 1997 Notice of Violation from Insp on 970721-0801.Violation Noted:For Problem Rept PR97.9220,trip of B Residual Heat Removal Pump,Individual Performing Root Cause Analysis Was Not Formally Trained in HPI Methodology IR 05000293/19970071997-09-15015 September 1997 Insp Rept 50-293/97-07 on 970625-0816.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970801997-09-12012 September 1997 Insp Rept 50-293/97-80 on 970721-0801.Violations Noted.Major Areas Inspected:Effectiveness of Processes for Identifying Resolving & Preventing Issues That Degrade Quality of Plant Operations & Safety ML20216G8181997-09-0404 September 1997 Insp Rept 50-293/97-09 on 970827-28.No Violations Noted. Major Areas Inspected:Licensee Access Authorization Program PNO-I-97-053, on 970826,special Security Insp Will Be Performed,That Will Examine Security Activities at Vermont Yankee,Pilgrim & Indian Point 3.Team Will Include Security Specialists from Region I & NRR1997-08-22022 August 1997 PNO-I-97-053:on 970826,special Security Insp Will Be Performed,That Will Examine Security Activities at Vermont Yankee,Pilgrim & Indian Point 3.Team Will Include Security Specialists from Region I & NRR IR 05000293/19970041997-08-0707 August 1997 Insp Rept 50-293/97-04 on 970505-23.No Violations Noted. Major Areas Inspected:Effectiveness of Licensees Efforts in Maintaining Design Basis of safety-related Sys ML20149K0431997-07-22022 July 1997 Insp Rept 50-293/97-03 on 970429-0624.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20149K0401997-07-22022 July 1997 Notice of Violation from Insp on 970429-0624.Violation Noted:On 970602,station Services Dept Worker Tied Open Boiler Room Door Which Forms Part of Radiologically Controlled Area & Action Not Directed by RP Personnel ML20149K1311997-07-18018 July 1997 NRC Operator Licensing Exam Rept 50-293/97-06 (Including Completed & Graded Tests) for Tests Administered on 970505-09 ML20149K1291997-07-18018 July 1997 Notice of Violation from Exam on 970505-09.Violation Noted: Two SRO Applications Dtd 970418,documented Five Manipulations Based on Credit Taken for Multiple Manipulations Due to Power Change & One Should Be Credited ML20141K7861997-05-22022 May 1997 Insp Rept 50-293/97-02 on 970303-0428.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support 1999-08-27
[Table view] |
See also: IR 05000293/1996009
Text
.
.
U.S. NUCLEAR REGULATORY COMMISSION
, REGION 1
Docket No: 50-293
License No: DPR-35
]
Report No: 50-293/96-09
,
Licensee: Boston Edison Company
Facility: Pilgrim Nuclear Power Station
.:
)
Location: Plymouth, Massachusetts
,
i
Dates: September 16-20,1996
j inspectors: Greg C. Smith, Senior Security Specialist
Edward B. King, Physical Security inspector
Approved by: Richard R. Keimig, Chief
'
Emergency Preparedness and Safeguards Branch
Division of Reactor Safety
5
,
l
1
!
a
.
4
l
I
l
l
l
l
I
9610220009 961011 "
"
PDR ADOCK 05000293
G PDR ,
_ . _ _ _ _ _ _ _ _
.
.
< EXECUTIVE SUMMARY
Pilgrim Nuclear Power Station
NRC Inspection Report No. 50-293/96-09
,
On April 25,1991, the Commission published the Personnel Access Authorization
Requirements for nuclear power plants,10 CFR 73.56 (the rule), requiring power reactor
+
licensees to implement an Access Authorization Program (AAP) by April 27,1992, and to
incorporate the AAP into the licensee's physical security plan. The objective of the rule is
to provide high assurance that individuals granted unescorted access are trustworthy and
reliable, and do not constitute an unreasonable risk to the health and safety of the public,
including a potential to commit radiological sabotage.
The licensee's Access Authorization Program was inspected during the period
September 16-20,1996. It was found to meet the above stated objective. However, two
violations were identified involving the failure to perform audits of the access authorization
program within 12 months of it's effective date of implementation and at least every 24 ,
months thereafter and the failure to audit properly the contractor / vendor access
authorization programs accepted by the licensee. )
l
'
1
l
,
.
l
.
W
4
ii
___ _
_
_ _ _ - . _ . - _ . _ _ _ _ _ . . . _ . _ _ _ _ _ . _ .
.
..
Report Details
-P8 . Miscellaneous Security and Safeguards issues
]
P8.1 General
'On April 25,1991, the Commission published the Personnel Access Authorization
Requirements for nuclear power plants,10 CFR 73.56 (the rule), requiring power
reactor licensees to implement an Access Authorization Program (AAP) by
April 27,1992, and to incorporate the AAP into the licensee's physical security l
plan. The objective of the rule is to provide high assurance that individuals granted i
unescorted access are trustworthy and reliable, and do not constitute an j
unreasonable risk to the health and safety of the public, including a potential to l
commit radiological sabotage.
A February 27,1992, letter from the licensee to the NRC forwarded Revision 10 to
its physical security plan. Additional clarification of certain commitments was ;
deemed necessary as a result of NRC review. The licensee was notified of the i
results of that review during a telephone conversation and agreed to resubmit the
revision with the necessary clarifications. The licensee forwarded Revision 10a to
the NRC by letter, dated April 24,1992, which stated, in part, that all elements of
Regulatory Guide 5.66, " Access Authorization Program for Nuclear Power Plants,"
have been implemented to satisfy the requirements of 10 CFR Part 73.56. By
letter, dated May 19,1992, the NRC informed the licensee that the changes
submitted had been reviewed and were determined to be consistent with the
provisions of 10 CFR 50.54(p) and that the revision would be acceptable for
inclusion in the NRC-approved security plan.
This inspection, conducted in accordance with NRC Inspection Manual, Temporary
instruction 2515/127, " Access Authorization," dated January 17,1995, assessed i
the implementation of the licensee's AAP to determine if it was commensurate with
regulatory requirements and the licensee's physical security plan.
P8.2 Access Authorization Program and Administration Organization
1
a. insoection Scope !
The inspectors reviewed organizational charts, applicable procedures and conducted
interviews to assess the licensee's access authorization program and administration
Organization.
b. Observations and Findinos
The Boston Edison Company (BECO) AAP requirements are contained in two
documents. The Pilgrim Nuclear Power Station Procedure No.1.3.60, Revision 9,
titled " Access Authorization Process," dated August 23,1994, defines the overall
requirements for the program. The fitness-for-duty and behavior observation i
portions of the AAP are contained in the Fitness-For-Duty Medical Department
, Procedure, revised September 11,1996.
!
!
i
,
. _ _ .
.
2
The responsibility for implementation of the AAP is vested in the Protective Services
Department Manager, who reports to the Nuclear Services Group Manager. The
access screening and fitness for-duty personnel report to the Security Services
Supervisor who reports to the Protective Services Department Manager. The FFD
functions of the AAP are performed in the Medical Building and the personnel
screening functions are performed in the Support Building.
c. Conclusions
The inspectors' review of the applicable AAP and Medical Department Manuals
disclosed that both manuals were comprehensive and contained sufUcient detail to
provide adequate guidanco to implement the AAP in accordance with regulatory
requirements.
P8.3 Background investigations (BI) Elements
a. Inspection Scope
The inspectors reviewed records and conducted interviews to determine the
adequacy of the program to verify the true identity of an applicant and to develop ,
information concerning employment history, educational history, credit history, l
criminal history, military service, and character and reputation of the applicant prior l
to granting unescorted access to protected and vital areas. l
l
b. Observations. Findinas and Conclusions l
1
l
'
The inspectors reviewed the results of 55 background investigations (Bis)
representing a cross-section of licensee and contractor employees. The Bis are
performed by the licensee's Site Access Specialists. The scope and depth of the
Bis reviewed were found to meet the licensee's program commitments and provided
adequate information on which to base a determination for access authorization.
'
The 55 BI reports also contained the information on which temporary access was i
granted or denied. The records of those abbreviated scope and depth investigations I
permitted by the rule contained information on which to base a determination
regarding temporary access pending completion of the full BI, and fulfilled the
program requirements to which the licensee had committe1 The inspectors noted
that any matter of questionable or suspect information was thoroughly evaluated
and documented prior to granting or denying temporary access.
In accordance with 10 CFR 73.57, the licensee is responsible for initiating criminal
history checks on individuals applying for unescorted access authorization, and for
considering allinformation received from the U.S. Attorney General. Among the
records reviewed by the inspectors were those of eight individuals whose fingerprint
records had been returned with derogatory information. The inspectors determined
that the information had been properly evaluated and appropriate action had been
, implemented as a result of the derogatory information. I
1
. -. - . . . - --
-
l
l
!
'
.
3
l
P8.4 Psychological Evaluations
a. Insoection Scope i
The inspectors reviewed the licensee's psychological testing program procedures
and interviewed the individuals who administer and proctor the psychological tests.
!
b. Observations, Findinas and Conclusions
!
The licensee has contracted with a licensed psychologist to provide oversight of the
psychological testing program and to perform the requisite evaluations. All
individuals seeking unescorted access to the site are required to complete the
psychological questionnaire administered by licensee personnel that have been
trained and qualified as examination proctors. The answer sheets for the
psychological questionnaire are forwarded to the psychologist for evaluation and, if
the need for a clinical interview is indicated, the psychologist conducts the
interview and recommends either access or denial to the licensee. In all cases ,
reviewed, the licensee took the psychologist's recommendation. l
The inspectors determined that procedures were clear and that the proctors
demonstrated a sound knowledge of their duties.
The inspectors determined that the licensee's psychological evaluation program was
being effectively administered.
P8.5 Behavioral Observation Program (BOP)
a. inspection Scope
l
The inspectors reviewed the Behavioral Observation Program (BOP) training
procedures and lesson plans and conducted interviews to determine the :
effectiveness of the licensee's program. Additionally, the BOP was reviewed to j
determine whether the licensee had a training and retraining program to ensure that j
supervisors have and maintain awareness and sensitivity to detect behavior changes
in employees that could adversely affect their trustworthiness and reliability, and to
report such changes to appropriate management for further evaluation and action, if
deemed necessary.
1
b. Observations and Findinos l
l
The program was instituted as part of, and is an element in common with, the
licensee's Fitness-for-Duty (FFD) Program. Interviews conducted throughout the
inspection with various individuals, representative of a cross-section of both
supervisory and non-supervisory employees, ';dicated a knowledge of program j
requirements. The supervisors interviewed also demonstrated an awareness and
i
)
_---__-____-_--__-_____i
.- . - .
i
.
.
4
sensitivity to detect and report adverse changes in behavior. The effectiveness of
the BOP training was further evidenced by employees who had been referred to the
employee assistance program and had been FFD for-cause tested as a result of
changes in behavior that were identified through the BOP.
c. Qonglusion
The inspectors concluded that the training program and lessons plans were
adequate to support the program. The inspectors also concluded that the BOP
training and retraining were effective and that the BOP was being effectively
implemented.
P8.6 Grandfathering, Reinstatement and Transfer of Access Authorization
a. jnspection Scope
The inspectors reviewed a cross-section of records to evaluate the licensee's
appi; cation of the provisions for Grandfathering, Reinstatement and Transfers of
Access Authorizations.
b. Observations and Findinas
e "Grandfatherina" l
included in the records selected at random by the inspectors were records of :
personnel who did not meet the criteria for "grandfathering," i.e., those who ]
did not have uninterrupted, unescorted access authorization for at least 180 j
days on April 25,1991, the date of publication of the NRC's access i
authorization rule.
e Reinstatement
The licensee's criteria for reinstatement of access authorization was
reviewed. The criteria provided for reinstatement of unescorted access
authorization if one had been previously granted, that authorization was
terminated under favorable conditions no more than 365 days prior to the
reinstatement request, and FFD program requirements were met,
e ' Transfer of Access Authorization
The licensee incorporated the provision for the transfer of access
authorization, both receipts in and transfers out, into its program. The
records selected at random for review by the inspectors included several
examples of each.
- . . . . . -- . . - - - .
i*
. .
5
c. Conclusions
The inspectors determined that the requirements for grandf athering, reinstatement
and transfers of access authorizations were being met and that these portions of
the AAP were being implemented satisfactorily. No discreaancies were noted.
l P8.7 Temporary Access Authorization
a. Insoection Scoce
s
4
The inspectors reviewed records that included the results of abbreviated scope
investigations, which are used as the basis for granting temporary unescorted
access authorization, as permitted by the rule.
1
b. Observations. Findinas and Conclusions
The records of the abbreviated scope investigations were determined to contain
i adequate information (character and reputation from a developed reference, past
year's employment history, and a credit check) on which to base temporary access
authorization. The inspectors noted that, in these records of abbreviated scope
investigation, there were no instances in which rescission of access authorization
was necessitt .*d following receipt of the full 5-year investigation.
P8.8 Denial / Revocation of Unescorted Access
a. Insoection Scoce
The inspectors reviewed the licensee's provisions for the review of appeals of denial
or termination of access authorization.
b. Observations and Findinas
The inspectors determined that an individual is informed of the basis for denial or
revocation of access authorization, is provided the opportunity to provide additional
information for consideration and can have the decision, and any additional
information, reviewed by the Appeal Committee, which consists of representatives
from the Employee Relations and Legal Departments. After that review, the !
decision on the appeal is final,
c. Conclusion
The inspectors concluded that this aspect of the program was in accordance with
the rule and was being adequately implemented.
s 1
.- . . .
..
.
6
,
P8.9 Audits
-
a. Inspection Scoce
The inspectors reviewed the most recent quality assurance audit of the security and
access authorization programs (Audit No. 93-11 conducted October 11-
2 November 19,1993),
b. Observations and Findinas
The inspectors' review of the audit report disclosed that the audit identified no
findings and one observation concerning the independence of the evaluations of
accepted self-screening contractor and vendor programs.
The Pilgrim Nuclear Power Station Physical Security Plan issue 2, Revision 11,
,
dated December 22,1993, Section 5.1.1, states, in part, that the requirements for
unescorted access shallinclude conformance to all elements of Regulatory Guide
< 5.66 to satisfy the requirements of 10 CFR 73.56. NRC Regulatory Guide 5.66,
states, in Section 13.0, paragraph 13.1, that an independent evaluation of the
unescorted access authorization program and its conformance must be made within
'
12 months of the effective date of implementation of the access authorization
program. Thereafter, an independent evaluation must be conducted at least once
every 24 months. The utility shall retain all reports of evaluation for a period of
three years. The Code of Federal Regulation,10 CFR 73.56(g)(1), states, in part, !
that licensee's shall audit its Access Authorization Program within 12 months of its i
effective date of implementation of this program and at least every 24 months ;
thereafter to ensure that the requirements of this section are satisfied. ;
)
The inspectors determined during a review of the documentation associated with
the licensee's audit program and discussions with security management, that the
licensee failed to audit its access authorization program within 12 months of the
access authorization program's implementation (April 27,1992). The first audit of
the program was conducted between October 11 - November 19,1993,19 months !
'
af ter the program was implemented. At the time of this inspection, the licensee had
not performed another audit of the access authorization program but has performed
limited surveillances of the program's elements as a substitute for conducting an
audit. Therefore, the requirement to perform an audit of the program at least 24
months thereafter to ensure that the requirements of the program were being j
satisfied was also not met. This is a violation of NRC requirements. (VIO
50-293/96-09-01)
The inspectors' review also found that the audit conducted was very limited in
scope and depth. The sample size consisted of the records of only two individuals i
as a basis for evaluating program effectiveness.
. - _ _ .
. __ . _ - . _ .. _ _ . _ . .___ ._ _ _ _ __ _.. - _ _ _ _ - - _ _
l
.-
s
1
'
I
1
.. 7
1
- Additionally, the inspectors reviewed the audit program requirements for
contractor / vendor approved access authorization programs accepted by the
. licensee. At the time of this inspection, the licensee had accepted nine
i contractor / vendor programs.
1
,
NRC Regulatory Guide 5.66, states, in Section 13.0, paragraph 13.2, that the utility ;
j or its designated representative shall conduct annual audits of contractor or vendor j
.
access authorization programs to ensure compliance with these guidelines. Other ;
i utilities may accept the originating utility's audit and need not reaudit the same- ;
j contractor or vendor for the same period of time providing the scope of the audit ]
3
meets the minimum auditing criteria contained in Attachment A. A copy of the j
audit report to include findings, recommendations, and corrective action must be ;
- provided to the sharing utility.
The Code of Federal Regulation,10 CFR 73.56(g)(2), states, in part, that each
a licensee who accepts the access authorization program of a contractor or vender )
i shall have access to records and shall audit contractor / vendor programs every 12
,
months to ensure that the requirements are satisfied. Licensees may accept audits
! of contractor / vendor program conducted by other licensees. Each sharing utility i
i
i shall maintain a copy of the audit report, to include findings, recommendations and
j corrective actions.
j
j The inspectors determined during a review of the documentation associated with
i the licensee's audit program and discussions with security management, that the
j licensee failed to conduct audits of accepted contractors and vendor access
authorization programs every 12 months and could not produce a copy of another
utility's audit of the same contractor or vendor. This is a violation of NRC
i requirements. (VIO 50-293/96-09-02)
[ Apparently, nu one in the licensee's organization had tracked the audit requirements
associated with the AAP. The licensee agreed to perform an audit of its AAP prior
i to its scheduled outage in February 1997, and to correct the audit weaknesses
'
i associated with the accepted contractor / vendor programs.
c. Conclusion
l
j Two violations of NRC requirements were identified. Both were related to the
! licensee's auditing of the access authorization program as required by NRC
'
regulations. The one audit of the program that had been conducted was very
- shallow in depth and limited in scope.
~l'
P8.10 Record Retention
!
a. Insoection Scooe
The inspectors reviewed the onsite record retention program for the AAP records.
l
.
t
,
- , - -
,- --
- - _ _ - _ . - -. - .=. ..
.
+
.
8
b. Observations and Findinas
Records are stored in locked file cabinets, accessible only to authorized personnel.
The inspectors noted that the secords were very well organized and complete.
.
c. Conclusions
The inspectors determined that the storage facilities provided adequate security,
and that access to those records was adequately controlled to protect personal
information from unauthorized personnel.
1
X1 Exit interview
The inspectors presented the inspection results to members of licensee management at the j
conclusion of the inspection on September 20,1996. At that time, the purpose and scope
of the inspection were reviewed and the prelirrhary findings were presented. The licensee i
acknowledged the preliminary inspection findings.
X2 Updated Final Safety Analysis Report (UFSAR) Review j
i A recent discovery of a licensee operating its facility in a manner contrary to the UFSAR l
description highlighted the need for a special focused review that compares plant practices, !
, procedures, and parameters to the UFSAR description. Since the UFSAR does not
'
specifically include security program requirements, tne inspector compared licensee
activities to the NRC-approved physical security plan, which is the applicable document.
While performing the inspecticn discussed in this report, the inspectors reviewed Section
5.3.4 of the Plan, issue 2, Revision 11, dated December 22,1993, titled, " Package and
Vehicle Access," and observed package and vehicle searches. The review disclosed that
package and vehicle searches were being performed in accordance with the Plan and
security p.sgram procedures.
4
h
.
J
t
i
- . --
o
'
e
.
9
PARTIAL LIST OF PERSONS CONTACTED
Boston Edison Comoany
J. Alexander, Acting Station Director to Manager
R. Haladyna, Sr. Regulatory Affairs Engineer
W. Grieves, Sr. Quality Assurance (QA) Engineer
J. Quinn, Sr. QA Engineer
T. Venkataraman, Quality Assurance Department Manager
M. McAlister, Security Operations Supervisor
T. Campbell, Protective Security Department Manager
E. Neary, Protective Services
J. Keene, Regulatory Affairs Department Manager
R. Wheat, Protection Technology incorporated (PTI), Operations Manager
N. Metcalf, PTl Project Manager '
W. Stone, independent Oversight Team Manager
T. Beneduci, Nuclear Computer Application Department (NCAD) Manager
B. Barry, NCAD ,
H. Oheim, General Manager, Technical Section ]
Nuclear Reaulatory Commission
R. Laura, Senior Resident inspector
B. Korona, Residant inspector
,
d