ML20129A044

From kanterella
Jump to navigation Jump to search
Insp Rept 50-293/96-09 on 960916-20.Violations Noted. Major Areas Inspected:Miscellaneous Security & Safeguard Issues,Access Authorization Program & Administration Organization & Background Investigation Elements
ML20129A044
Person / Time
Site: Pilgrim
Issue date: 10/11/1996
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20129A027 List:
References
50-293-96-09, 50-293-96-9, NUDOCS 9610220009
Download: ML20129A044 (11)


See also: IR 05000293/1996009

Text

.

.

U.S. NUCLEAR REGULATORY COMMISSION

, REGION 1

Docket No: 50-293

License No: DPR-35

]

Report No: 50-293/96-09

,

Licensee: Boston Edison Company

Facility: Pilgrim Nuclear Power Station

.:

)

Location: Plymouth, Massachusetts

,

i

Dates: September 16-20,1996

j inspectors: Greg C. Smith, Senior Security Specialist

Edward B. King, Physical Security inspector

Approved by: Richard R. Keimig, Chief

'

Emergency Preparedness and Safeguards Branch

Division of Reactor Safety

5

,

l

1

!

a

.

4

l

I

l

l

l

l

I

9610220009 961011 "

"

PDR ADOCK 05000293

G PDR ,

_ . _ _ _ _ _ _ _ _

.

.

< EXECUTIVE SUMMARY

Pilgrim Nuclear Power Station

NRC Inspection Report No. 50-293/96-09

,

On April 25,1991, the Commission published the Personnel Access Authorization

Requirements for nuclear power plants,10 CFR 73.56 (the rule), requiring power reactor

+

licensees to implement an Access Authorization Program (AAP) by April 27,1992, and to

incorporate the AAP into the licensee's physical security plan. The objective of the rule is

to provide high assurance that individuals granted unescorted access are trustworthy and

reliable, and do not constitute an unreasonable risk to the health and safety of the public,

including a potential to commit radiological sabotage.

The licensee's Access Authorization Program was inspected during the period

September 16-20,1996. It was found to meet the above stated objective. However, two

violations were identified involving the failure to perform audits of the access authorization

program within 12 months of it's effective date of implementation and at least every 24 ,

months thereafter and the failure to audit properly the contractor / vendor access

authorization programs accepted by the licensee. )

l

'

1

l

,

.

l

.

W

4

ii

___ _

_

_ _ _ - . _ . - _ . _ _ _ _ _ . . . _ . _ _ _ _ _ . _ .

.

..

Report Details

-P8 . Miscellaneous Security and Safeguards issues

]

P8.1 General

'On April 25,1991, the Commission published the Personnel Access Authorization

Requirements for nuclear power plants,10 CFR 73.56 (the rule), requiring power

reactor licensees to implement an Access Authorization Program (AAP) by

April 27,1992, and to incorporate the AAP into the licensee's physical security l

plan. The objective of the rule is to provide high assurance that individuals granted i

unescorted access are trustworthy and reliable, and do not constitute an j

unreasonable risk to the health and safety of the public, including a potential to l

commit radiological sabotage.

A February 27,1992, letter from the licensee to the NRC forwarded Revision 10 to

its physical security plan. Additional clarification of certain commitments was  ;

deemed necessary as a result of NRC review. The licensee was notified of the i

results of that review during a telephone conversation and agreed to resubmit the

revision with the necessary clarifications. The licensee forwarded Revision 10a to

the NRC by letter, dated April 24,1992, which stated, in part, that all elements of

Regulatory Guide 5.66, " Access Authorization Program for Nuclear Power Plants,"

have been implemented to satisfy the requirements of 10 CFR Part 73.56. By

letter, dated May 19,1992, the NRC informed the licensee that the changes

submitted had been reviewed and were determined to be consistent with the

provisions of 10 CFR 50.54(p) and that the revision would be acceptable for

inclusion in the NRC-approved security plan.

This inspection, conducted in accordance with NRC Inspection Manual, Temporary

instruction 2515/127, " Access Authorization," dated January 17,1995, assessed i

the implementation of the licensee's AAP to determine if it was commensurate with

regulatory requirements and the licensee's physical security plan.

P8.2 Access Authorization Program and Administration Organization

1

a. insoection Scope  !

The inspectors reviewed organizational charts, applicable procedures and conducted

interviews to assess the licensee's access authorization program and administration

Organization.

b. Observations and Findinos

The Boston Edison Company (BECO) AAP requirements are contained in two

documents. The Pilgrim Nuclear Power Station Procedure No.1.3.60, Revision 9,

titled " Access Authorization Process," dated August 23,1994, defines the overall

requirements for the program. The fitness-for-duty and behavior observation i

portions of the AAP are contained in the Fitness-For-Duty Medical Department

, Procedure, revised September 11,1996.

!

!

i

,

. _ _ .

.

2

The responsibility for implementation of the AAP is vested in the Protective Services

Department Manager, who reports to the Nuclear Services Group Manager. The

access screening and fitness for-duty personnel report to the Security Services

Supervisor who reports to the Protective Services Department Manager. The FFD

functions of the AAP are performed in the Medical Building and the personnel

screening functions are performed in the Support Building.

c. Conclusions

The inspectors' review of the applicable AAP and Medical Department Manuals

disclosed that both manuals were comprehensive and contained sufUcient detail to

provide adequate guidanco to implement the AAP in accordance with regulatory

requirements.

P8.3 Background investigations (BI) Elements

a. Inspection Scope

The inspectors reviewed records and conducted interviews to determine the

adequacy of the program to verify the true identity of an applicant and to develop ,

information concerning employment history, educational history, credit history, l

criminal history, military service, and character and reputation of the applicant prior l

to granting unescorted access to protected and vital areas. l

l

b. Observations. Findinas and Conclusions l

1

l

'

The inspectors reviewed the results of 55 background investigations (Bis)

representing a cross-section of licensee and contractor employees. The Bis are

performed by the licensee's Site Access Specialists. The scope and depth of the

Bis reviewed were found to meet the licensee's program commitments and provided

adequate information on which to base a determination for access authorization.

'

The 55 BI reports also contained the information on which temporary access was i

granted or denied. The records of those abbreviated scope and depth investigations I

permitted by the rule contained information on which to base a determination

regarding temporary access pending completion of the full BI, and fulfilled the

program requirements to which the licensee had committe1 The inspectors noted

that any matter of questionable or suspect information was thoroughly evaluated

and documented prior to granting or denying temporary access.

In accordance with 10 CFR 73.57, the licensee is responsible for initiating criminal

history checks on individuals applying for unescorted access authorization, and for

considering allinformation received from the U.S. Attorney General. Among the

records reviewed by the inspectors were those of eight individuals whose fingerprint

records had been returned with derogatory information. The inspectors determined

that the information had been properly evaluated and appropriate action had been

, implemented as a result of the derogatory information. I

1

. -. - . . . - --

-

l

l

!

'

.

3

l

P8.4 Psychological Evaluations

a. Insoection Scope i

The inspectors reviewed the licensee's psychological testing program procedures

and interviewed the individuals who administer and proctor the psychological tests.

!

b. Observations, Findinas and Conclusions

!

The licensee has contracted with a licensed psychologist to provide oversight of the

psychological testing program and to perform the requisite evaluations. All

individuals seeking unescorted access to the site are required to complete the

psychological questionnaire administered by licensee personnel that have been

trained and qualified as examination proctors. The answer sheets for the

psychological questionnaire are forwarded to the psychologist for evaluation and, if

the need for a clinical interview is indicated, the psychologist conducts the

interview and recommends either access or denial to the licensee. In all cases ,

reviewed, the licensee took the psychologist's recommendation. l

The inspectors determined that procedures were clear and that the proctors

demonstrated a sound knowledge of their duties.

The inspectors determined that the licensee's psychological evaluation program was

being effectively administered.

P8.5 Behavioral Observation Program (BOP)

a. inspection Scope

l

The inspectors reviewed the Behavioral Observation Program (BOP) training

procedures and lesson plans and conducted interviews to determine the  :

effectiveness of the licensee's program. Additionally, the BOP was reviewed to j

determine whether the licensee had a training and retraining program to ensure that j

supervisors have and maintain awareness and sensitivity to detect behavior changes

in employees that could adversely affect their trustworthiness and reliability, and to

report such changes to appropriate management for further evaluation and action, if

deemed necessary.

1

b. Observations and Findinos l

l

The program was instituted as part of, and is an element in common with, the

licensee's Fitness-for-Duty (FFD) Program. Interviews conducted throughout the

inspection with various individuals, representative of a cross-section of both

supervisory and non-supervisory employees, ';dicated a knowledge of program j

requirements. The supervisors interviewed also demonstrated an awareness and

i

)

_---__-____-_--__-_____i

.- . - .

i

.

.

4

sensitivity to detect and report adverse changes in behavior. The effectiveness of

the BOP training was further evidenced by employees who had been referred to the

employee assistance program and had been FFD for-cause tested as a result of

changes in behavior that were identified through the BOP.

c. Qonglusion

The inspectors concluded that the training program and lessons plans were

adequate to support the program. The inspectors also concluded that the BOP

training and retraining were effective and that the BOP was being effectively

implemented.

P8.6 Grandfathering, Reinstatement and Transfer of Access Authorization

a. jnspection Scope

The inspectors reviewed a cross-section of records to evaluate the licensee's

appi; cation of the provisions for Grandfathering, Reinstatement and Transfers of

Access Authorizations.

b. Observations and Findinas

e "Grandfatherina" l

included in the records selected at random by the inspectors were records of :

personnel who did not meet the criteria for "grandfathering," i.e., those who ]

did not have uninterrupted, unescorted access authorization for at least 180 j

days on April 25,1991, the date of publication of the NRC's access i

authorization rule.

e Reinstatement

The licensee's criteria for reinstatement of access authorization was

reviewed. The criteria provided for reinstatement of unescorted access

authorization if one had been previously granted, that authorization was

terminated under favorable conditions no more than 365 days prior to the

reinstatement request, and FFD program requirements were met,

e ' Transfer of Access Authorization

The licensee incorporated the provision for the transfer of access

authorization, both receipts in and transfers out, into its program. The

records selected at random for review by the inspectors included several

examples of each.

- . . . . . -- . . - - - .

i*

. .

5

c. Conclusions

The inspectors determined that the requirements for grandf athering, reinstatement

and transfers of access authorizations were being met and that these portions of

the AAP were being implemented satisfactorily. No discreaancies were noted.

l P8.7 Temporary Access Authorization

a. Insoection Scoce

s

4

The inspectors reviewed records that included the results of abbreviated scope

investigations, which are used as the basis for granting temporary unescorted

access authorization, as permitted by the rule.

1

b. Observations. Findinas and Conclusions

The records of the abbreviated scope investigations were determined to contain

i adequate information (character and reputation from a developed reference, past

year's employment history, and a credit check) on which to base temporary access

authorization. The inspectors noted that, in these records of abbreviated scope

investigation, there were no instances in which rescission of access authorization

was necessitt .*d following receipt of the full 5-year investigation.

P8.8 Denial / Revocation of Unescorted Access

a. Insoection Scoce

The inspectors reviewed the licensee's provisions for the review of appeals of denial

or termination of access authorization.

b. Observations and Findinas

The inspectors determined that an individual is informed of the basis for denial or

revocation of access authorization, is provided the opportunity to provide additional

information for consideration and can have the decision, and any additional

information, reviewed by the Appeal Committee, which consists of representatives

from the Employee Relations and Legal Departments. After that review, the  !

decision on the appeal is final,

c. Conclusion

The inspectors concluded that this aspect of the program was in accordance with

the rule and was being adequately implemented.

s 1

.- . . .

..

.

6

,

P8.9 Audits

-

a. Inspection Scoce

The inspectors reviewed the most recent quality assurance audit of the security and

access authorization programs (Audit No. 93-11 conducted October 11-

2 November 19,1993),

b. Observations and Findinas

The inspectors' review of the audit report disclosed that the audit identified no

findings and one observation concerning the independence of the evaluations of

accepted self-screening contractor and vendor programs.

The Pilgrim Nuclear Power Station Physical Security Plan issue 2, Revision 11,

,

dated December 22,1993, Section 5.1.1, states, in part, that the requirements for

unescorted access shallinclude conformance to all elements of Regulatory Guide

< 5.66 to satisfy the requirements of 10 CFR 73.56. NRC Regulatory Guide 5.66,

states, in Section 13.0, paragraph 13.1, that an independent evaluation of the

unescorted access authorization program and its conformance must be made within

'

12 months of the effective date of implementation of the access authorization

program. Thereafter, an independent evaluation must be conducted at least once

every 24 months. The utility shall retain all reports of evaluation for a period of

three years. The Code of Federal Regulation,10 CFR 73.56(g)(1), states, in part,  !

that licensee's shall audit its Access Authorization Program within 12 months of its i

effective date of implementation of this program and at least every 24 months  ;

thereafter to ensure that the requirements of this section are satisfied.  ;

)

The inspectors determined during a review of the documentation associated with

the licensee's audit program and discussions with security management, that the

licensee failed to audit its access authorization program within 12 months of the

access authorization program's implementation (April 27,1992). The first audit of

the program was conducted between October 11 - November 19,1993,19 months  !

'

af ter the program was implemented. At the time of this inspection, the licensee had

not performed another audit of the access authorization program but has performed

limited surveillances of the program's elements as a substitute for conducting an

audit. Therefore, the requirement to perform an audit of the program at least 24

months thereafter to ensure that the requirements of the program were being j

satisfied was also not met. This is a violation of NRC requirements. (VIO

50-293/96-09-01)

The inspectors' review also found that the audit conducted was very limited in

scope and depth. The sample size consisted of the records of only two individuals i

as a basis for evaluating program effectiveness.

. - _ _ .

. __ . _ - . _ .. _ _ . _ . .___ ._ _ _ _ __ _.. - _ _ _ _ - - _ _

l

.-

s

1

'

I

1

.. 7

1

Additionally, the inspectors reviewed the audit program requirements for

contractor / vendor approved access authorization programs accepted by the

. licensee. At the time of this inspection, the licensee had accepted nine

i contractor / vendor programs.

1

,

NRC Regulatory Guide 5.66, states, in Section 13.0, paragraph 13.2, that the utility  ;

j or its designated representative shall conduct annual audits of contractor or vendor j

.

access authorization programs to ensure compliance with these guidelines. Other  ;

i utilities may accept the originating utility's audit and need not reaudit the same-  ;

j contractor or vendor for the same period of time providing the scope of the audit ]

3

meets the minimum auditing criteria contained in Attachment A. A copy of the j

audit report to include findings, recommendations, and corrective action must be  ;

provided to the sharing utility.

The Code of Federal Regulation,10 CFR 73.56(g)(2), states, in part, that each

a licensee who accepts the access authorization program of a contractor or vender )

i shall have access to records and shall audit contractor / vendor programs every 12

,

months to ensure that the requirements are satisfied. Licensees may accept audits

! of contractor / vendor program conducted by other licensees. Each sharing utility i

i

i shall maintain a copy of the audit report, to include findings, recommendations and

j corrective actions.

j

j The inspectors determined during a review of the documentation associated with

i the licensee's audit program and discussions with security management, that the

j licensee failed to conduct audits of accepted contractors and vendor access

authorization programs every 12 months and could not produce a copy of another

utility's audit of the same contractor or vendor. This is a violation of NRC

i requirements. (VIO 50-293/96-09-02)

[ Apparently, nu one in the licensee's organization had tracked the audit requirements

associated with the AAP. The licensee agreed to perform an audit of its AAP prior

i to its scheduled outage in February 1997, and to correct the audit weaknesses

'

i associated with the accepted contractor / vendor programs.

c. Conclusion

l

j Two violations of NRC requirements were identified. Both were related to the

! licensee's auditing of the access authorization program as required by NRC

'

regulations. The one audit of the program that had been conducted was very

shallow in depth and limited in scope.

~l'

P8.10 Record Retention

!

a. Insoection Scooe

The inspectors reviewed the onsite record retention program for the AAP records.

l

.

t

,

- , - -

,- --

- - _ _ - _ . - -. - .=. ..

.

+

.

8

b. Observations and Findinas

Records are stored in locked file cabinets, accessible only to authorized personnel.

The inspectors noted that the secords were very well organized and complete.

.

c. Conclusions

The inspectors determined that the storage facilities provided adequate security,

and that access to those records was adequately controlled to protect personal

information from unauthorized personnel.

1

X1 Exit interview

The inspectors presented the inspection results to members of licensee management at the j

conclusion of the inspection on September 20,1996. At that time, the purpose and scope

of the inspection were reviewed and the prelirrhary findings were presented. The licensee i

acknowledged the preliminary inspection findings.

X2 Updated Final Safety Analysis Report (UFSAR) Review j

i A recent discovery of a licensee operating its facility in a manner contrary to the UFSAR l

description highlighted the need for a special focused review that compares plant practices,  !

, procedures, and parameters to the UFSAR description. Since the UFSAR does not

'

specifically include security program requirements, tne inspector compared licensee

activities to the NRC-approved physical security plan, which is the applicable document.

While performing the inspecticn discussed in this report, the inspectors reviewed Section

5.3.4 of the Plan, issue 2, Revision 11, dated December 22,1993, titled, " Package and

Vehicle Access," and observed package and vehicle searches. The review disclosed that

package and vehicle searches were being performed in accordance with the Plan and

security p.sgram procedures.

4

h

.

J

t

i

- . --

o

'

e

.

9

PARTIAL LIST OF PERSONS CONTACTED

Boston Edison Comoany

J. Alexander, Acting Station Director to Manager

R. Haladyna, Sr. Regulatory Affairs Engineer

W. Grieves, Sr. Quality Assurance (QA) Engineer

J. Quinn, Sr. QA Engineer

T. Venkataraman, Quality Assurance Department Manager

M. McAlister, Security Operations Supervisor

T. Campbell, Protective Security Department Manager

E. Neary, Protective Services

J. Keene, Regulatory Affairs Department Manager

R. Wheat, Protection Technology incorporated (PTI), Operations Manager

N. Metcalf, PTl Project Manager '

W. Stone, independent Oversight Team Manager

T. Beneduci, Nuclear Computer Application Department (NCAD) Manager

B. Barry, NCAD ,

H. Oheim, General Manager, Technical Section ]

Nuclear Reaulatory Commission

R. Laura, Senior Resident inspector

B. Korona, Residant inspector

,

d