ML20108E908

From kanterella
Jump to navigation Jump to search

Presentation Slides for Sequoyah Nuclear Plant, Unit 2 - Exigent License Amendment Request TS 4.2.2, Control Rod Assemblies, Pre-Submittal Conference Call - April 16, 2020
ML20108E908
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 04/16/2020
From:
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation
Buckberg P
References
Download: ML20108E908 (13)


Text

Sequoyah Nuclear Plant Unit 2 TS 4.2.2 Control Rod Assemblies Exigent LAR Pre-Submittal Conference Call April 16, 2020

Objectives

  • Provide overview of planned implementation actions
  • Provide overview of expected License Amendment Request (LAR) content
  • Discuss planned submittal date and need date
  • Answer NRC questions l 2

=

Background===

  • Sequoyah Units 1 & 2 are Westinghouse 4-loop 3455MWt ice condenser plant designs

- Framatome HTP 17x17 fuel

- 193 Fuel assemblies, 53 control rods

  • Unit 2 is currently shut down for the U2R23 refueling outage l 3

Background - H-08

  • During U2R23, excessive wear was identified on the faces of the stationary grippers along with wear marks along the interior walls of the control rod drive mechanism.
  • The wear is similar to the wear identified on Unit 1 during U1R23 in November 2019.
  • Unit 2 has not experienced the same dropped rod events as Unit 1.

l 4

Background - Control Rod Configuration

  • Total of 53 Rod Control Cluster Assemblies (RCCA)
  • RCCAs are grouped into Banks:

- Four Shutdown Banks

- Four Control banks

  • Rod H-08 is part of Control Bank D and located in the center of the core l 5

Background - H-08 Repairs

  • Replacement of the Control Rod Drive Mechanism (CRDM) grippers is a long lead activity with first-of-a-kind elements (custom tooling, processes, crew qual. on mockups, etc.)
  • Temporary modifications to utilize the H-08 movable gripper to hold the rod withdrawn were investigated during U1R23 but were not viable.
  • Design change package being prepared for physical removal of the H-08 rod for the upcoming cycle.

l 6

Plant Changes Required

  • Remove RCCA and associated drive shaft at core location H-08
  • Install control rod guide tube flow restrictor on the upper internals
  • Remove H-08 inputs to Rod Position Indication (RPI) system
  • Remove power fuses for H-08 CRDM from the Rod Control system
  • Revise Reload Safety Evaluation to include impact of control rod removal on nuclear design and safety analyses
  • Revise affected procedures and design documents l 7

Planned LAR Content

  • Evaluated Rod H-08 removal impacts on:

- Shutdown Margin

- Boron Concentration and Boron Worth

- Moderator Temperature Coefficient

  • UFSAR Chapter 15 parameters were analyzed using the NRC-approved methods described in TS 5.6.3 and showed that limits assumed in safety analysis remain bounding.
  • The Reload Safety Evaluation for the removal of H-08 validated all cycle-specific Reload Design Safety Analysis Review Checklist limits.

l 8

Overview of Proposed Change

  • Requesting proposed amendment to allow Unit 2 to operate with 52 full-length control rod assemblies for one cycle
  • No methodology changes
  • Proposed change to TS 4.2.2 (change bar on right):

l 9

Planned LAR Content

  • Current COLR limits remain unchanged.
  • No new operator actions are expected.
  • No impact on the functionality, structural integrity, or thermal hydraulic configuration of the reactor vessel upper internals

- Flow restrictor installed in place of the control rod drive shaft l 10

Precedence LARs

- LAR was to remove Rod H-08 from the core.

- LAR was submitted as a contingency if a repair to a thermal sleeve could not be performed. Repairs were successful

  • South Texas Project - Emergency LAR to Revise TS 5.3.2 to Allow Operation with 56 Full-Length Rod Assemblies for Unit 1 Cycle 20 (LAR -12/3/15, SE 12/11/15) l 11

Proposed Schedule for Submittal and Requested Approval

  • Sequoyah plans to submit the exigent LAR on April 17
  • Plant is currently in Mode 6, progressing into Core Empty (No Mode) and continuing with refueling outage activities
  • Plant will return to Mode 6 and remain in Mode 6 pending LAR approval and implementation of the design change
  • Request NRC review 7 days after submittal l 12

Closing and Questions l 13