ML19323D888

From kanterella
Jump to navigation Jump to search

TVA Pre-submittal Presentation Slides - Exigent Amendment
ML19323D888
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 11/15/2019
From:
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation
Buckberg P, NRR/DORL/LPL2-2, 415-1383
Shared Package
ML19323D956 List:
References
EPID L-2019-LLA-0239
Download: ML19323D888 (15)


Text

Sequoyah Nuclear Plant Unit 1 TS 4.2.2 Control Rod Assemblies Exigent LAR Pre-Submittal Conference Call November 15, 2019

Objectives

  • Provide overview of planned implementation actions
  • Provide overview of expected License Amendment Request (LAR) content
  • Discuss planned submittal date and need date
  • Answer NRC questions l 2

=

Background===

  • Sequoyah Units 1 & 2 are Westinghouse 4-loop 3455MWt ice condenser plant designs

- Framatome HTP 17x17 fuel

- 193 Fuel assemblies, 53 control rods

  • Unit 1 is currently shut down for the U1R23 refueling outage l 3

Background - H-08

  • On August 27, 2019 SQN Unit 1 center control rod (core location H-8) dropped into the core while the reactor was at 100% power causing an automatic scram of the unit.
  • Troubleshooting completed at the time investigated the electronic control system and no deficiencies were identified.

- The site initiated a root cause analysis which was indeterminate pending additional inspections during the fall refueling outage.

  • The reactor was returned to 100% power and a second set of grippers was used to assist the normal grippers in holding the H-8 rod in position. There were no issues for the remainder of the cycle.

l 4

Background - H-08 Troubleshooting

  • During the refueling outage, remote inspections of the inside of the control rod drive mechanism were performed using robotic cameras and action was taken to replace the H-08 jack shaft.
  • The inspections performed identified excessive wear on the faces of the stationary grippers along with wear marks along the interior walls of the control rod drive mechanism.
  • Throughout the process, the OEM has been reviewing inspection data as well as third party reviews.
  • During pre-startup testing the H-8 rod dropped into the reactor multiple times at various positions both above and below the normal operating position. The degradation in operating characteristics of the H-8 control rod was not anticipated.

l 5

Background - Control Rod Configuration

  • Total of 53 Rod Control Cluster Assemblies (RCCA)
  • RCCAs are grouped into Banks:

- Four Shutdown Banks

- Four Control banks

  • Rod H-08 is part of Control Bank D and located in the center of the core l 6

Background - H-08 Repairs

  • Replacement of the Control Rod Drive Mechanism (CRDM) grippers is a long lead activity with first-of-a-kind elements (custom tooling, processes, crew qual. on mockups, etc.)
  • Temporary modifications to utilize the H-08 movable gripper to hold the rod withdrawn were investigated but were not viable.
  • Design change package being prepared for physical removal of the H-08 rod for the upcoming cycle.

l 7

Plant Changes Required

  • Remove RCCA and associated drive shaft at core location H-08
  • Install control rod guide tube flow restrictor on the upper internals
  • Remove H-08 inputs to Rod Position Indication (RPI) system
  • Remove power fuses for H-08 CRDM from the Rod Control system
  • Revise Reload Safety Evaluation to include impact of control rod removal on nuclear design and safety analyses
  • Revise affected procedures and design documents l 8

Planned LAR Content

  • Evaluated Rod H-08 removal impacts on:

- Shutdown Margin

- Boron Concentration and Boron Worth

- Moderator Temperature Coefficient

  • UFSAR Chapter 15 parameters were analyzed using the NRC-approved methods described in TS 5.6.3 and showed that limits assumed in safety analysis remain bounded.
  • The Reload Safety Evaluation for the removal of H-08 validated all cycle-specific Reload Design Safety Analysis Review Checklist limits.

l 9

Overview of Proposed Change

  • Requesting proposed amendment to allow Unit 1 to operate with 52 full-length control rod assemblies for one cycle
  • No methodology changes
  • Proposed change to TS 4.2.2 (change bar on right):

l 10

Planned LAR Content

  • Current COLR limits remain unchanged.
  • No new operator actions are expected.
  • No impact on the functionality, structural integrity, or thermal hydraulic configuration of the reactor vessel upper internals

- Flow restrictor installed in place of the control rod drive shaft l 11

Precedence LAR

  • South Texas Project - Emergency LAR to Revise TS 5.3.2 to Allow Operation with 56 Full-Length Rod Assemblies for Unit 1 Cycle 20 (LAR -12/3/15, SE 12/11/15)

- LAR was to remove Rod H-08 from the core.

- LAR was submitted as a contingency if a repair to a thermal sleeve could not be performed. Repairs were successful l 12

Differences between SQN 1 and Precedence SQN Exigent LAR McGuire STP Not a contingency Contingency Not a contingency TS 4.2.2 note in TS 4.2.2 footnote TS 4.2.2. footnote accordance with ITS format Framatome analysis In-house analysis Westinghouse analysis No thimble plug Thimble plug Thimble plug Control bank RCCA Control bank RCCA Shutdown bank RCCA l 13

Proposed Schedule for Submittal and Requested Approval

  • Sequoyah plans to submit the exigent LAR on November 16
  • Plant is currently progressing to Mode 6 to perform initial field work
  • Plant is remaining in Mode 6 pending approval and implementation of the design change
  • Request NRC review 7 days after submittal l 14

Closing and Questions l 15