NUCLEAR REGULATORY COMMISSION W ASHINGTON, D.
C. 20555 March 19, 1975 Docket No. 50-219 Applicant: Jersey Central Power & Light Company (JCP&L)
Facility:
Oyster Creek Nuclear Generating Station
SUMMARY
OF MEETING HELD ON MARCH 4,1975 TO DISCUSS THE SCHEDULE FOR SUBMITTAL OF THE OYSTER CREEK ECCS REANALYSIS A meeting of General Public Utilities Service Corporation (GPUSC) and NRC representatives was held in Bethesda on March 4, 1974. The purpose of this meeting was to discuss the schedule for the submittal of the Oyster Creek ECCS reanalysis. Enclosure 1 is a list of attendees.
BACKGROUND The Oyster Creek Nuclear Generating Station is scheduled to shut down at the end of March 1975 for a refueling outage.
JCP&L has scheduled May 10, 1975 as the startup date following the reload.
Prior to startup, JCP&L must submit an ECCS reanalysis calculated in accordanc.e with an acceptable evaluation model that conforms with the provisions of 10 CFR Part 50, paragraph 50.46. ' Analyses are required for both the GE and Exxon fuel. GE will perform the complete reanalysis for the GE fuel.
Exxon will do the reanalysis for their fuel; however, Exxon uses the results of the GE blowdown calculations in their analysis.
SCHEDULE FOR SUBMITTAL OF ECCS REANALYSIS
' is the schedule presented by GPUSC for the submittal of the Oyster Creek ECCS reanalysis.
We discussed the schedule and stated that based on the April 11/12 submittal date for the design basis analysts, the time required for the prenotice would delay the startup beyond the May 10, 1975 scheduled date.
The GE blowdown calculations using the approved GE ECCS evaluation model will not be available until March 28, 1975. These blowdown i
calculations are on the critical path because Exxon needs the GE results as input to their calculations. The results of the GE blowdown calculations for Oyster Creek using the GE approved model are not expected to be significantly different from existing calculations.
GPUSC stated that they may have Exxon perform calculations using the existing blowdown calculations and then verify that the results of the revised calculations are, in fact, not significantly different. This approach may make the ECCS reanalysis available as much as two weeks earlier than shown on Enclosure 2.
owno m\\
g F
$a
/
T
(
(')
)
i Jersey Central Power & Light Co. March 19, 1975 The analyses of the small breaks will be available on April 25, 1975, according to JCP&L's schedule. These analyses are viewed as being confirmatory to verify that the big break is, in fact, the most limiting break.
We stated that JCPAL must indicate in the ECCS submittal exactly how the re-evaluations were performed using the approved GE and Exxon inodel s.
RELOAD SUBMITTAL In addition to the ECCS re-evaluation, we are reviewing JCP&L's reload submittal that includes fuel design, physics, thermal-hydraulic, transient, and accident analyses, etc. GPUSC stated t
that the control rod withdrawal error transient analysis, which was originally scheduled to be submitted on February 15, 1975, will not be provided until March 28, 1975.
We stated that we would look into whether the GETAB-GEXL correlation would be required for analyses of the balance of the GE fuel in the Core.
l tb$ b. dYW Walter A. Paulson Operating Reactors Branch #3 Division of Reactor Licensing
Enclosures:
As stated j
4 l
7 s
Q
)
'.l 4
ENCLOSURE 1 LIST OF ATTENDEES MEETING OF GENERAL PUBLIC UTILITIES SERVICE CORP.
AND NRC REPRESENTATIVES ON MARCH 4, 1975 NRC GPUSC W. Paulson T. Crimmins, Jr.
R. Schemel N. Trikouros G. Lear G. Bond R. Woods T. Robbins (PickardLowe& Assoc.)
J. Scinto E.Blake(Shaw,Pittman,Potts M. Kaufman
& Trowbridge)
R. Frahm T. Novak J. Wetmore i
J o
/
s
(~}
/
e ENCLOSURE 2 OYSTER CREEK - ECCS ANALYSIS By March 25 Exxon H/U model documentation available.-
March 29 GE B/D & H/U model documentation and analysis of GE fuel and proposed T. S.
limits on GE fuel available to J.
C.,
Exxon Nucl. & NRC - not yet approved by J. C. Safety Committees.
April 4 J. C. technical review and safety review of GE models, analysis and T. S. limits, and Exxon model complete and documented to NRC.
April 11/12 Exxon DBA Break analysis results and T. S. limits - not yet approved by J. C.
to NRC & J. C.
April 18 J. C. technical review and safety review of Exxon DBA analysis and T. S. limits complete and documented to NRC.
April 25 Exxon remaining analyses (small breaks) supplied to NRC & J. C.
May 2 Final J. C. Technical and safety review documents to NRC.
May 10 Startup H/U = Heat Up B/D = Blow Down j
i
__ -.. ~ _ _ _ _ _
J
./
O
)
^
/>
\\
UNITED ST ATES
' NUCLEAR REGULATORY COMMISSION W ASHINGTON. D. C. 20555 Docket No 50 219 March 21,~1975 DISTRIBUTION OF MEETING
SUMMARY
JERSEY CENTRAL POWER 6 LIGHT CO.
OYSTER CREEK NUCLEAR GENERATING STATION MARCH 4, 1975 Jersey Central Power 6 Light Co.
ATTN: Mr. I. R. Finfrock, Jr.
Vice President - Generation Madison Avenue at Punch Bow & Road Morristown, New Jersey 07960 Ocean County Library 15 Hooper Avenue Toms River, New Jersey 08753 l
.p.
T. Novak 1.
Docket File D. Ziemann D. Ross.
NRC PDR G. Lear R. W. Hous't'on Local PDR P. Collins T. Ippolito ORBf3 Rdg G. Knighton V. Moore G. Dicker C. Long G. Lainas R. DeYoung B. Youngblood D. Skovholt W. Regan, Jr.
V. Benaroya R. Vollmer D. Muller S. Varga B. Grimes R. Denise F. Williams W. Gamill J. Stolz F. Schroeder J. Kastner K. Kniel R. Maccary M. Spangler A. Schwencer V. Stello R. Ballard D. Vassallo R. Tedesco O. Parr W. Butler H. Denton ACRS (16)
K. Coller J. P. Knight S. A. Teets T. Speis' S. Pawlicki R. Clark L. Shao OETB
' d &E_ M '
OWT'%
NRC Participants Project Manager
- p b
A
\\,,,..,,,)
7 s
/
4
)
UNITED STATES NUCLEAR REGULATORY COMMISSION W ASHINGTON, D. C. 20555 March 19, 1975 Docket No. 50-219 Y
e
'r
- Applicant: Jersey Central Power & Light Company (JCP&L)
Facility:
Oyster Creek Nuclear Generating Station
SUMMARY
OF MEETING HELD ON MARCH 4, 1975 TO DISCUSS THE SCHEDULE FOR SUBMITTAL OF THE OYSTER CREEK ECCS REANALYSIS A meeting of General Public Utilities Service Corporation (GPUSC) and NRC representatives was held in Bethesda on March 4, 1974. The purpose of this meeting was to discuss the schedule for the submittal of the Oyster Creek ECCS reanalysis.
Enclosure"l'is a list of attendees.
BACKGROUND The Oyster Creek Nuclear Generating Station is scheduled to shut down at the end of March 1975 for a refueling outage. JCP&L has i
scheduled May 10, 1975 as the startup date following the reload.
Prior to startup, JCP&L must submit an ECCS reanalysis calculated in accordance with an acceptable evaluation model that conforms with the provisions of 10 CFR Part 50, paragraph 50.46. Analyses are required for both the GE and Exxon fuel. GE will perform the complete reanalysis for the GE fuel.
Exxon will do the reanalysis for their fuel; however, Exx~on uses the results of the GE blowdown calculations in their analysis.
SCHEDULE FOR SUBMITTAL 0F ECCS REANALYSIS is the schedule presented by GPUSC for the submittal of the Oyster Creek ECCS reanalysis. We discussed the schedule and stated that based on the April 11/12 submittal date for the design basis analysis, the time required for the prenotice would delay the startup beyond the May 10, 1975 scheduled date.
The GE blowdown calculations using the approved GE ECCS evaluation model will not be available until March 28, 1975. These blowdown calculations are on the critical path because Exxon needs the GE results as input to their calculations. The results of the GE blowdown calculations for Oyster Creek using the GE approved model are not expected to be significantly different from existing calculations.
GPUSC stated that they may have Exxon perform calculations using the existing blowdown calculations and then verify that the results of the revised calculations are, in fact, not significantly different. This approach may make the ECCS reanalysis available as much as two weeks earlier than shown on Enclosure 2.
- oomo,
- 76 1910
,1
3>,
^ ^ -- -
)
\\
0-i Jersey' Central Power & Light Co. March 19, 1975 The analyses of the small breaks will be available on April 25, 1975, I
according to JCP&L's schedule. These analyses are viewed as being confinnatory to verify that the big break is, in fact, the most limiting break.
We stated that JCP&L must indicate in the ECCS submittal exactly how the re-evaluations were performed using the approved GE and Exxon inodel s.
RELOAD SUBMITTAL In addition to the ECCS re-evaluation, we are reviewing JCP&L's reload submittal that includes fuel design, physics, thermal-j hydraulic, transient, and accident analyses, etc. GPUSC stated that the control rod withdrawal error transient analysis, which was originally scheduled to be submitted on February 15, 1975, will not be provided until March 28, 1975.
We stated that we would look into whether the GETAB-GEXL correlation would be mquired for analyses of the balance of the GE fuel in the Core.
4[
h e
Walter A. Paulson Operating Reactors Branch #3 Division of Reactor Licensing j
Enclosures:
As stated l
i 1
m-w w+-
w m-
7
' f
._. i.. _
~
9
. (Ti
.I )
- o 4
ENCLOSURE 1 LIST OF ATTENDEES MEETING OF GENERAL PUBLIC UTILITIES SERVICE CORP.
AND NRC REPRESENTATIVES ON MARCH 4, 1975 NRC GPUSC
^
W. Paulson.
T. Crimmins, Jr.
R. Schemel N. Trikouros G. Lear G. Bond R. Woods T. Robbins (PickardLowe& Assoc.)
i J. Scinto E. Blake (Shaw, Pittman, Potts M. Kaufman
& Tecwbridge)
R. Frahm T. Novak J. Wetmore i
A 4
t P
e
/
e J-e t
a ENCLOSURE 2 OYSTER CREEK - ECCS ANALYSIS By March 25 Exxon H/U model documentation available.
March 29 GE B/D & H/U model documentation and analysis of GE fuel and proposed T. S.
limits on GE fuel available to J.
C.,
Exxon Nucl. & NRC - not yet approved by J. C. Safety Committees.
April 4 J. C. technical review and safety review of GE models, analysis and T. S. limits, and Exxon model complete and documented to NRC.
i' April 11/12 Exxon DBA Break analysis results and T. S. limits - not yet approved by J. C.
to NRC & J. C.
April 18 J. C. technical review and safety review of Exxon DBA analysis and T. S. limits complete and documented to NRC.
April 25 Exxon remaining analyses (small breaks) supplied to NRC & J. C.
May 2 Final J. C. Technical and safety review documents to NRC.
f May 10 Startup H/U = Heat Up B/D = Blow Down 1
4
/
A
)
U, *) f s
'Ap aj I
UNITEo ST ATLs NUCLEAR REGULATORY COMMISSION W ASHINGTON, o. C. 20555 Docket No 50 219 March 21, 1975 DISTRIBUTION OF MEETING
SUMMARY
JERSEY CENTRAL POWER S LIGHT CO.
OYSTER CREEK NUCLEAR GENERATING STATION MARCH 4, 1975 Jersey Central Power 6 Light Co.
ATTN: Mr. I. R. Finfrock, Jr.
Vice President - Generation Madison Avenue at Punch Bow & Road Morristown, New Jersey 07960 Ocean County L5brary 15 Hooper Avenue Toms River, New Jersey 08753 T. Novak I..,
Docket File D. Ziemann D. Ross
G. Lear NRC PDR R. W. Hous't'on Local PDR P. Collins T. Ippolito ORB #3 Rdg G. Knighton C. Long G. Dicker V. Moore G. Lainas B. Youngblood R. DeYoung V. Benaroya D. Skovholt W. Regan, Jr.
R. Vollmer D. Muller S. Varga B. Grimes R. Denise F. Williams W. Gammill l
J. Stolz F. Schroeder J. Kastner K. Kniel R. Maccary M.'Spangler V. Stello A. Schwsncer R. Ballard D. Vassallo R. Tedesco O. Parr W. Butler H. Denton ACRS (16)
K. Coller J. P. Knight S. A. Teets S. Pawlicki T. Speis OELD R. Clark L. Shao Mr (3f3 oM%
NRC Participants Project Manager a