ML20107C776

From kanterella
Jump to navigation Jump to search
Responds to 741004 Request for Explanation for Delay of Primary Sys Transient Analysis Submittal Beyond Mar 1975, Vendor Program for Completion of Analysis & Estimate of Actual Submittal Date
ML20107C776
Person / Time
Site: Oyster Creek
Issue date: 10/18/1974
From: Finfrock I
JERSEY CENTRAL POWER & LIGHT CO.
To: Anthony Giambusso
US ATOMIC ENERGY COMMISSION (AEC)
Shared Package
ML18039A986 List: ... further results
References
FOIA-95-258 NUDOCS 9604180005
Download: ML20107C776 (1)


Text

gv

' O-O y.1 rm:3 a.n Jersey Central Power & Light Compar1y 1 9 q)

MADISON AVENUE AT PUNCH BOWL ROAD

  • MORRISTOWN, N.J. 07960
  • 201-539-6111 mauens e was.

g,E, pubuc utihtees corporation Generst ann.

October 18, 1974g 7-Mr. A. Giambusso, Deputy Director 8

for Reactor Projects p f g %

[y by j t - N i d--l 00T24 T

r, g Directorate of Licensing Office of Regulation l

U.S. Atomic Energy Commission Washington, DC 20545 g

a, g

i tL ~

.A,

Dear Mr. Giambusso:

\\j

$6,.h,[(

SUBJECT:

Oyster Creek Nuclear Generating Station Docket No. 50-219 Anticipated Transients Without Scram Analysis (ATWS)

Your letter dated October 4,1974 transmitted your approval of November 1, 1974 as the date for submission of the Common Mode Failure Analysis for the Oyster Creek Nuclear Generating Station and requested further information with respect to our request for delay of the Primary System Transient Analysis sub-mittal beyond March, 1975.

Specifically, you requested an explanation for the delay, a vendor program for completion of the analysis and an estimate of the actual submittal date.

General Electric Company has indicated that insufficient manpower is avail-able to provide simultaneous resolution of ATWS concerns for all the nuclear i

generating stations for which they provide analytical support.

On this basis, it was decided that those plants which were listed as Category B, WASH 1270, would be given highest priority with respect to the Primary System Transient Analysis. Consequently, Category C plants, such as Oyster Creek, will experience delays.

At the present time, General Electric Company has stated that they are planning to initiate their Category C plant model refinement on September 1, 1974 i

with completion scheduled for March 1, 1975. The Oyster Creek Primary System Transient Analysis results will be available for our review on April 1,1975. We are scheduling a 30-day review of these results with subsequent submittal to the

- Regulatory Staff on May 1, 1975. The 30 days is necessary for technical and safety committee review, management approval and printing.

Very truly yours, 1

) /.