Forwards Revised Page 1 of Attachment 1 to Re Min Staffing Requirements,Per NUREG-0654
ML20041F124
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 03/08/1982
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
RTR-NUREG-0654, RTR-NUREG-654, TASK-1.A.1.1, TASK-1.A.1.3, TASK-1.C.5, TASK-1.C.6, TASK-3.A.2.1, TASK-TM TAC-44117, TAC-44118, TAC-46259, TAC-46260, TAC-48851, TAC-48852, NUDOCS 8203160210
Download: ML20041F124 (2)


Text

~

1 o

3 e

PRINCIPAL _STATF j

V DIR

.,EdLIS' a/o npo Wisconsin Electnc eom couem ao ho 231 W. MICHIGAN, P.O. BOX 2046, MILWAUKEE, WI 53201 y

b'pgpy M

/

March 8, 1982 DE&TI DEP&O:

File

+ r',

x 4

Mr. J. G.

Keppler, Regional Director Office of Inspection and Enforcement, RHCEIVED C

ggl'5 79826 Region III 9-12

~

U. S. NUCLEAR REGULATORY COMMISSION g

799 Roosevelt Road Glen Ellyn, Illinois 60137 9

/

4

Dear Mr. Keppler:

p MINIMUM STAFFING REQUIREMENTS FOR NRC LICENSEES FOR NUCLEAR POWER PLANT EMERGENCIES (TABLE III.A.l.2-1 OR TABLE B-1 OF NUREG-0654, REVISION 1):

AND POINT BEACH NUCLEAR PLANT CONFORMANCE My letter of February 18, 1982 provided a response to your letter of January 21, 1982 on the above subject. to our letter summarized how each major functional area of Table B-1 is implemented at Point Beach Nuclear Plant.

It has been called to my attention that page 1 of contains an error; please replace that page with the enclosed Revision 1.

I hope that the need for this correction has not caused any inconvenience.

Very truly yours, t((c/

C. W.

Fay Assistant Vice President Attachment Copy to NRC Resident Inspector

((

/

8203160210 B20308 PDR ADOCK 05000266 MAR 9E g

P PDR

Revision 1 March 8, 1982 i

ATTACHMENT 1 TABLE B-1 OF NUREG-0654 ON SHIFT MAJOR FUNCTIONAL AREA PBNP RESPONSE 1.

Plant Operations On Shift:

1 Shift Supervisor 1 Operating Supervisor 2 Control Operators 4 Auxiliary Operators 2.

Emergency Direction Technical Advisor on site 3.

Notification / Communication One of four Auxiliary Operators to handle until relieved by augmentation 4.

Radiation Assessment a.

In Plant Surveys All four Auxiliary Operators are qualified to do surveys.

Accounting for 3, above, three are available for surveys and other assignments noted below.

Additional health physics expertise on call.

b.

Chemistry / Radiochemistry Rad Chem Technician on shift 88 of 168 hours0.00194 days <br />0.0467 hours <br />2.777778e-4 weeks <br />6.3924e-5 months <br /> per week.

Auxiliary Operators qualified to perform certain chemical analysis work.

Additional chemistry expertise on call.

5.

Plant System Engineering a.

Shift Technical Advisor See 2 above.

b.

Mechanical Maintenance /

One of on-shift Auxiliary Rad Waste Operator Operators can perform work until augmentation.

c.

Electrical Maintenance A licensed operator or one of Auxiliary Operators on-shift can be assigned until augmentation. __